FY 2001 Action Plan proposal 26037

Additional documents

TitleType
26037 Narrative Narrative

Section 1. Administrative

Proposal titleOn-Farm Water Conservation opportunities in Oregon, Washington and Idaho
Proposal ID26037
OrganizationIRZ Consulting, LLC (IRZ)
Proposal contact person or principal investigator
NameFred Ziari
Mailing address505 East Main Hermiston, OR
Phone / email / irz@irz.com
Manager authorizing this projectFred Ziari
Review cycleFY 2001 Action Plan
Province / SubbasinColumbia Plateau / Umatilla
Short descriptionConduct on-farm water conservation sevices for farms in Oregon, Washinton and Idaho. We will contact and enlist farms to particiapte in a one year water conservtion measures. Anticipated water savings ranging from 10% to 50% & energy savings 10 to 20%.
Target speciesALL
Project location
LatitudeLongitudeDescription
45.57 -118.93 Farms in Oregon, Washington and Idaho
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Conserve Water and have it dedicated for fihsery for 2001 irrigation season Conduct On-Farm Water Conservation on over 100,000 acres 6 $2,500,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Subcontractor Lump Sum $2,500,000
$2,500,000
Total estimated budget
Total FY 2001 cost$2,500,000
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$2,500,000
FY 2001 forecast from 2000$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Various farms $200,000 cash

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Do not fund - inadequate proposal
Date:
Jun 21, 2001

Comment:

Not fundable, inadequate proposal. This proposal is incomplete and does not include the necessary information to meet the solicitation criteria such as description of direct on the ground benefits to species impacted by the power emergency. Specific activities, location of activities, populations to benefit, and methods are not described. There is no basis for judging the potential of the proposal for helping to address problems caused by the emergency action.