FY 2002 Columbia Plateau proposal 200203400

Section 1. Administrative

Proposal titleWheeler SWCD Riparian Buffer Planning and Implementation
Proposal ID200203400
OrganizationWheeler Soil and Water Conservation District (Wheeler SWCD)
Proposal contact person or principal investigator
NameJudy Potter
Mailing addressPO Box 431 Fossil, OR 97830
Phone / email5414683265 / judypotter@centurytel.net
Manager authorizing this projectJudy Potter
Review cycleColumbia Plateau
Province / SubbasinColumbia Plateau / John Day
Short descriptionThis project will implement a riparian buffer program using cost share funding from USDA, State of Oregon and private landowners.
Target speciesSummer steelhead, Spring Chinook, Pacific Lamprey, resident redband trout
Project location
LatitudeLongitudeDescription
Wheeler SWCD Conservation District Boundaries - (County boundary) - NW Corner
NE Corner
SW Corner
SE Corner
44.75 -120.03 Wheeler County
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
Action 153

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription
NMFS/BPA Action 153 NMFS BPA shall, working with agricultural incentive programs such as the Conservation Reserve Enhancement Program, negotiate and fund long-term protection for 100 miles of riparian buffers per year in accordance with criteria BPA and NMFS will develop by June 1, 2001.
NMFS Action 153 NMFS BPA shall, working with agricultural incentive programs such as the Conservation Reserve Enhancement Program, negotiate and fund long-term protection for 100 miles of riparian buffers per year in accordance with criteria BPA and NMFS will develop by June 1, 2001.

Section 2. Past accomplishments

YearAccomplishment
2001 3.94 miles of riparian buffers on anadromous fish bearing waterways
2000 Parrish Creek riparian pasture manages livestock distribution on five miles of anadromous fish bearing riparian area
2000 Kahler/Corncob Creek Project. Riparian buffer created and bioengineered bank stabilization installed on 2000 feet of fish bearing streams
2000 Johnson Creek riparian improvement project. Removed livestock access from 3000 feet of anadromous fish bearing stream and installed off-channel water for excluded livestock.
1999 Lower John Day River Riparian Enclosure Project installed riparian corridor fence along both sides of thirteen miles of the Mainstem of the John Day River
1999 Bridge Creek Noxious Weed Control Project used biological and chemical controls on over 200 acres of noxious weeds along riparian areas and in the uplands
1999 Bridge Creek Demonstration Project involved 13 private landowners & 80,000+ acres, all implementing individual conservation practices on their respective properties
1997 Bridge Creek CRMP developed with private landowners, BLM and USFS on 204,000 acres.

Section 3. Relationships to other projects

Project IDTitleDescription
199802200 Pine Creek Ranch This project will be implementing riparian buffers along much of Pine Creek (approximately 10 miles)
0 acquisition of Wagner Ranch - pending Possible riparian buffer implementation along six miles of the John Day River
B.O. RPA 153 This proposal focuses on accelerating the protection of riparian areas on private lands by utilizing the Conservation Reserve Enhancement Program (CREP) and Continuous Conservation Reserve Program.
B.O. RPA 154 Through this proposal, staff assistance will be provided to the Subbasin Assessment and Planning process to coordinate local input needs.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1. Implement 60 new CREP / CCRP riparian buffer system agreements with participating landowners on 78 miles of stream to improve 1,135 acres during the three year duration. a. Develop landowner interest in programs with an outreach effort. Meet with interested landowners on site and assess eligibility of stream reach for program. (10%) 3 $7,509
b. Obtain landowner sign-up for program. (2%) 3 $1,502
c. Develop CREP / CCRP plans for review and approval, including planting prescriptions, fencing design and other practice elements as necessary. (70%) 3 $52,560
d. Report progress, complete documentation. (4%) 3 $3,003
2. Subbasin assessment & plan assistance. a. Provide assistance to BPA & NWPPC with development and update of subbasin plans. (5%) 3 $3,754
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Implement 60 new CREP / CCRP riparian buffer system agreements with participating landowners on 78 miles of streams to improve 1,135 acres during the 3 year project. 2003 2004 $142,865
Outyear budgets for Planning and Design phase
FY 2003FY 2004
$70,377$72,488

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1. Provide technical assistance during implementation as necessary. a. After contract is approved, provide additional technical assistance as may be required by the landowner to implement the approved plan. (9%) 3 $6,758
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Fy 2002 objective is continued. 2003 2004 $14,129
Outyear budgets for Construction and Implementation phase
FY 2003FY 2004
$6,960$7,169

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Operation and maintenance costs are included in the contract payments and are the responsibility of the landowner. $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Operation and maintenance costs are included in the contract payments and are the responsibility of the landowner $0
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Farm Service Agency has programmatic responsiblity for monitoring $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2002 cost
Personnel FTE: 1.0 $42,000
Fringe Includes all personnel exp. (FICA/WC/Med) $12,600
Supplies Field equipment and office equipment. Includes computer system & software $4,000
Travel Technical training NRCS $1,500
Indirect Administrative overhead (10%) $6,826
NEPA Covered under NRCS Planning Process $0
Subcontractor vehicle lease and operations $6,240
Other office rent $1,920
$75,086
Total estimated budget
Total FY 2002 cost$75,086
Amount anticipated from previously committed BPA funds$0
Total FY 2002 budget request$75,086
FY 2002 forecast from 2001$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
State of Oregon Implementation cost share (25%) est. $265,513 cash
USDA Farm Service Agency Implementation cost share (50%) est. $531,025 cash
Private Landowners Implementation cost share (25%) est. $265,513 in-kind
USDA Farm Service Agency Bonus payments 1 time (100%) est. $666,695 cash
Wheeler SWCD and NRCS Office supplies / telephone / computer $4,500 in-kind
USDA Farm Service Agency Lease payments 10-15 yr. (100%) est. $950,562 cash
USDA NRCS Training & Technical Supervision $46,500 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable - no response required
Date:
Jun 15, 2001

Comment:

Fundable. See comments above for this set of SWCD proposals. This proposal is to implement riparian buffer systems in the Lower John Day subbasin. It includes 1 FTE to provide the technical planning support to implement 60 riparian buffer system contracts on private lands under the USDA CRP and CREP. Activities will include planting and fencing. Willing landowners have been identified but technical support to help them develop conservation plans is missing. This project has excellent coordination with other agencies and close ties to related projects. Another cost-effective project from a SWCD that will leverage large amounts of USDA money for riparian restoration.


Recommendation:
High Priority
Date:
Aug 3, 2001

Comment:

This raises an in-lieu issue. This project needs to be implemented consistent with limiting factors and problem locations identified in subbasin summaries and eventually subbasin planning to insure fisheries benefits to target species. There needs to be oversight by the COTR to insure that actions taken will benefit fish and wildlife. If activities are not consistent with those described above, funding should be eliminated.
Recommendation:
Fund
Date:
Aug 10, 2001

Comment:

Fundable. See comments below for this set of SWCD proposals. This proposal is to implement riparian buffer systems in the Lower John Day subbasin. It includes 1 FTE to provide the technical planning support to implement 60 riparian buffer system contracts on private lands under the USDA CRP and CREP. Activities will include planting and fencing. Willing landowners have been identified but technical support to help them develop conservation plans is missing. This project has excellent coordination with other agencies and close ties to related projects. Another cost-effective project from a SWCD that will leverage large amounts of USDA money for riparian restoration.
See detailed ISRP Comments on CRP, CREP, Buffer, and No-till Proposals
Recommendation:
Date:
Oct 1, 2001

Comment:

Statement of Potential Biological Benefit to ESU
This project will implement a riparian buffer program using cost share funding from USDA, State of Oregon and private landowners

Comments
Project will implement RPA 153 only if permanent or long term easement. Support if permanent easement, or at least > 15 years. Easement should be consistent with Oregon CREP. This project needs to be implemented consistent with limiting factors & problem locations identified in subbasin summaries & and eventually subbasin planning to ensure fisheries benefits to target species.

Already ESA Req? no

Biop? yes


Recommendation:
Rank A
Date:
Oct 16, 2001

Comment:

This proposal would implement a riparian buffer program using cost-share funding from USDA, State of Oregon and private landowners ($2.7 million).
Recommendation:
Fund
Date:
Jan 3, 2002

Comment:

Proposals 25073, 25080 and 25006 may all be relevant to resolving the approach to implementing Biological Opinion RPA 153NMFS commented that these projects will implement RPA 153 only through permanent or long term easements. Bonneville commented that all proposals would meet RPA 153 and ranked 25073 and 25080 in the A funding category. Bonneville placed proposal 25006 in the C category. Staff Recommendation: Staff believes these proposals will help implement RPA 153 and Oregon places great emphasis on these types of locally driven proposals in implementing the Oregon Plan. The proposals would be strengthened if Bonneville, though its contracting process, encouraged coordination of SWCD personnel with the local fish and wildlife managers to develop priorities for contracting and enrolling participants in the CREP programs. Bonneville's comments on these proposals would appear to further emphasize this necessary coordination.

Staff recommends that 25006 would enable the Council to anticipate subbasin planning under the program by providing technical assistance to watershed councils that will be focal points in helping develop subbasin plans in the John Day. Proposal 25006 budgeted for purchase of a vehicle and an ATV during FY 2002. Staff does not find the purchase of these vehicles necessary to implement this project and has decreased the budget for FY 2002 to reflect that change.

Budget effect on base program (Project 25006):

FY 2002 FY 2003 FY 2004
Increase $71,000 Increase $65,770 Increase $68,337

Budget effect on base program (Project 25073):

FY 2002 FY 2003 FY 2004
Increase $75,086 Increase $77,337 Increase $79,657

Budget effect on base program (Project 25080):

FY 2002 FY 2003 FY 2004
Increase $75,086 Increase $77,337 Increase $79,657

Recommendation:
Fund
Date:
Mar 6, 2002

Comment:


Recommendation:
Fund
Date:
Sep 20, 2003

Comment:

Position not filled until January 03, delays due to personnel. Project shifting a year. No 02 implementation.
Recommendation:
Date:
Sep 20, 2003

Comment:


REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$79,657 $79,657 $79,657

Sponsor comments: See comment at Council's website