FY 2002 Columbia Plateau proposal 198402100
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
198402100 Narrative | Narrative |
198402100 Sponsor Response to the ISRP | Response |
Columbia Plateau: John Day Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Columbia Plateau: John Day Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Protect and Enhance Anadromous Fish Habitat in The John Day Subbasin |
Proposal ID | 198402100 |
Organization | Oregon Department of Fish and Wildlife (ODFW) |
Proposal contact person or principal investigator | |
Name | Jeff Neal |
Mailing address | PO Box 515 John Day, OR 97845 |
Phone / email | 5415751167 / janeal@centurytel.net |
Manager authorizing this project | Tim Unterwegner |
Review cycle | Columbia Plateau |
Province / Subbasin | Columbia Plateau / John Day |
Short description | Project develops and implements riparian fencing and instream structure projects to protect, enhance and restore riparian and instream habitat to improve anadromous salmonid production. |
Target species | Spring Chinook, Summer Steelhead, Redband rainbow trout, Westslope cutthroat trout, Bull Trout, Pacific Lamphrey |
Project location
Latitude | Longitude | Description |
---|---|---|
Implement long-term riparian, fish habitat and tributary passage improvements on private lands within the John Day Subbasin. | ||
44.78 | -119.59 | John Day subbasin |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS | Action 153 | NMFS | BPA shall, working with agricultural incentive programs such as the Conservation Reserve Enhancement Program, negotiate and fund long-term protection for 100 miles of riparian buffers per year in accordance with criteria BPA and NMFS will develop by June 1, 2001. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1985 2001 | Constructed 136 miles of riparian livestock exclosure fencing protecting and enhancing 77 miles of stream and 2005 acres of riparian habitat. Planted 7,450 riparian trees and shrubs, installed 3,040 instream structures and restored 1.8 mi. of |
dredge mined floodplain. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
9605300 | Upper Clear Cr. Dredge Tailings Restoration. | Share equipment and personnel between public and private lands |
9801800 | John Day Watershed Restoration. | Share storage, eqiupment, designs and personnel. |
8402500 | Grand Ronde Habitat Enhancement | Share equipment and personnel. |
8710002 | Umatilla Habitat Improvement | Share equipment and personnel. |
20131 | Enhance N.fk John Day Fish Habitat | Share designs, landownership regimes and data. |
299 | Oregon Fish Screening Project | Share offices, shop, storage yard, equipment and personnel. |
9801600 | Monitor Natural Escapement & Productivity of John Day Basin Spring Chinook. | Share storage, equipment, personnel and provide access to private lands. |
20102 | Research/Evaluate restoration of NE Ore. streams | Provide restoration summary and access to private lands. |
20064 | Pacific Lamprey migration in the John Day River | Provide restoration summary and access to private lands. |
93033800 | North Fork John Day Area Riparian Fencing. | Share designs, equipment and personnel between public and private lands. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
Obj. 1 Develop plans for enhancing fish habitat and riparian areas. | Task a. Develop "reference reach" data to determine functionality and stability of project streams. | On-going | $7,500 | |
Task b. Work cooperatively with private landowners to develop long-term easements, riparian leases or agreements. | On-going | $7,500 | ||
Task c. Conduct Rosgen level III assessment of instream project streams. | On-going | $4,000 | ||
Task d. Conduct project design surveys. | On-going | $3,966 | ||
Task e. Develop instream project designs. | On-going | $5,000 | ||
Task f. Prepare contract documents and specifications. | On-going | $21,034 | Yes | |
Task g. Complete NEPA | On-going | $5,000 | Yes | |
Obj. 2. Develop plans for maintaining fish habitat improvement projects. | Task a. Prepare contract documents and specifications. | On-going | $1,500 | Yes |
Task b. Conduct on-site preparation activities. | On-going | $2,500 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
Obj. 1 Develop plans for enhancing fish habitat and riparian areas. | 2003 | 2006 | $232,000 |
Obj. 2. Develop plans for maintaining fish habitat improvement projects. | 2003 | 2006 | $20,000 |
Outyear budgets for Planning and Design phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$60,000 | $62,000 | $64,000 | $66,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
Obj.1. Improve stream channel function, instream habitat diversity and streambank stability by constructing bioengineering treatments, instream structures and placing large wood. | Task a. Remove, transport and level dredge tailings along tributaries. | On-going | $60,000 | Yes |
Task b. Spread soil uncovered in task a over all disturbed sites. | On-going | $22,000 | Yes | |
Task c. Place excavated trees and boulders instream for fish habitat. | On-going | $30,000 | Yes | |
Obj. 2. Improve the quantity and quality of riparian communities along the John Day River and tributaries. | Task a. Construct approximately 6 miles of riparian corridor fencing to exclude livestock. | On-going | $87,000 | Yes |
Task b. Develop off-site livestock water developments to better utilize range resources. | On-going | $21,000 | Yes | |
Task c. Revegetate 3 miles of riparian areas by seeding and planting. | On-going | $2,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
Obj.1. Improve stream channel function, instream habitat diversity and streambank staibity by floodplain reconstruction, constructing bioengineering treatments, installing instream structures and placing large wood along the John Day River and tributaries | 2003 | 2006 | $475,800 |
Obj. 2. Improve the quantity and quality of riparian communities along the John Day River and tributaries. | 2003 | 2006 | $500,000 |
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$229,800 | $237,600 | $245,400 | $263,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
Obj. 1. Provide maximum project benefits by providing maintenance on existing projects. | Task a. Inspect 136 miles of fence and conduct maintenance on 23 miles. | On-going | $47,000 | Yes |
Task b. Inspect 123 watergaps and conduct maintenance on 20. | On-going | $27,000 | Yes | |
Task c. Inspect 25 spring developments and conduct maintenance on 6. | On-going | $8,500 | Yes | |
Task d. Inspect 10 solar watering devices and conduct maintenance on 6. | On-going | $5,000 | Yes | |
Task e. Coordinate O&M activities with private landowners. | On-going | $2,500 | ||
Task f. Inspect completed instream work and conduct maintenance where necessary. | On-going | $8,500 | Yes | |
Task g. Repair and maintain project vehicles, tools and equipment. | On-going | $6,700 | ||
Task h. Inspect 2005 acres for noxious weeds and control on 60 acres. | On-going | $6,000 | Yes | |
Obj. 2. Provide administrative oversight and secretarial support for project activities. | Task a. Prepare and review all contract documents, competitive bid packages, riparian leases and reports. | On-going | $4,000 | |
Task b. Prepare annual work statements and budgets for submittal to BPA. | On-going | $7,500 | ||
Task c. Liaison with BPA, federal and state agencies and tribes on issues that effect successful implementation of on-the-ground projects. | On-going | $2,000 | ||
Task d. Supervision of project personnel. | On-going | $4,000 | ||
Task e. Provide secretarial support for project activities. | On-going | $3,000 | ||
Task f. Provide offices and support services for project personnel. | On-going | $3,000 | ||
Task g. Develop project procedures and protocols for development, maintenance and construction of projects. | On-going | $2,500 | ||
Obj. 3. Insure maximum communication, education and coordination of habitat enhancement activities by actively pursuing opportunities to work with, educate and learn from individuals and entities. | Task a. Coordinate field activities with other agencies. | On-going | $5,000 | |
Task b. Answer correspondence, respond to information needs and make presentations to other agencies, private organizations, schools/youth groups and news media. | On-going | $2,500 | ||
Task c. Work cooperatively with private landowners to promote projects and management activities beneficial to the protection and enhancement of fish habitat. | On-going | $7,300 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
Obj. 1. Provide maximum project benefits by providing maintenance on existing projects. | 2003 | 2006 | $456,000 |
Obj. 2. Provide administrative oversight and secretarial support for project activities. | 2003 | 2006 | $98,500 |
Obj. 3. Insure maximum communication, education and coordination of habitat enhancement activities by actively pursuing opportunities to work with, educate and learn from individuals and entities. | 2003 | 2006 | $98,500 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$156,500 | $161,000 | $165,500 | $170,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
Obj. 1. Monitor and evaluate existing riparian habitat enhancement projects within the mainstem John Day River basin. | Task a. Establish photopoints on new project sites and retake pictures at established photopoint sites. | On-going | $5,000 | |
Task.b. Monitor temperature changes as a result of enhancement activities. | On-going | $0 | ||
Task.c. Establish channel morphology transects on new project sites and collect data from established channel morphology transects. | On-going | $6,500 | ||
Task. d. Summarize and report monitoring results in annual reports. | On-going | $5,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
Obj. 1. Monitor and evaluate existing riparian habitat enhancement projects within the mainstem John Day River basin. | 2003 | 2006 | $99,200 |
Outyear budgets for Monitoring and Evaluation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$23,700 | $24,400 | $25,100 | $26,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: 3 | $114,852 |
Fringe | @ 39.9 % of Personnel | $45,826 |
Supplies | $92,000 | |
Travel | $18,000 | |
Indirect | @ 20.1% of Personnel, Fringe, Supplies & Travel. | $54,406 |
NEPA | $5,000 | |
Subcontractor | $124,916 | |
$455,000 |
Total estimated budget
Total FY 2002 cost | $455,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $455,000 |
FY 2002 forecast from 2001 | $455,000 |
% change from forecast | 0.0% |
Reason for change in estimated budget
No change in Budget
Reason for change in scope
No change in Scope
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Oregon Watershed Enhancement Board | Fence construction materials | $20,000 | cash |
John Day Acid Spill Fund | Habitat improvement materials | $20,000 | cash |
Private Landowners | Fence and water development construction and maintenance. | $38,000 | in-kind |
Oregon Dept.of Transportation | Design and construct 1.3 mi.of riparian fence on Granite Creek. | $9,250 | in-kind |
Oregon State Parks | Design and Construct 1.4 mi. of riparian fence on Camas Creek. | $6,000 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Jun 15, 2001
Comment:
Do not fund unless a response is provided that adequately addresses the ISRP concerns. Many of these concerns were raised in the FY2000 review but are not adequately addressed in the proposal.
- Break the proposal into individual components with separate budgets, objectives, time schedule, etc.
- Give example results of past efforts in the form of graphs and tables, e.g., plots of data over time; show biologically measurable results (from FY 2000 review:" the proposal should be able to demonstrate biologically measurable results. They should use science-based quantitative data to demonstrate cost-effective gains toward the primary objective. The reviewers urge more complete measurements of quantity/quality of all life stages of fish species of concern, documented and analyzed, with appropriate comparisons with unfenced areas for statistical analysis. The costs of fencing and protecting riparian corridors, combined with the politics of fencing issues, require comprehensive science-based analysis, which then can be used to plot successful long-term, cost-effective strategies.")
- Coordinate the monitoring for juvenile and adult chinook with the other monitoring proposals 199801600 and potentially 25010 and 25088, see general ISRP comments at front of report.
- Describe and ensure that data collection procedures are the same and meaningful, give adequate references to published literature on methods (from FY 2000 review:". (monitoring and evaluating) relies on indirect measurement of larval and juvenile salmon productivity indexes, including redd counts. Because adult salmon returns are influenced by many factors other than stream improvement, this is not an adequate indicator unless accompanied by appropriate statistical analysis and comparisons to relevant controls (unimproved areas).")
- Consider terminating the fencing portion of this project and replacing it with personnel support to initiate CRP and CREP contracts with landowners for riparian buffers and to provide landowner maintenance of fences. Cost share proposed is small (~20% of project) as compared to CRP and CREP habitat projects that lever larger amounts.
- Landowner leases are beginning to expire. Explain the incentives for landowners to continue maintenance of fences. (from FY 2000 review "The proposal argues persuasively for 15-year leases and continued maintenance, but there is inadequate information on what may follow. Are there appropriate incentives for landowners to continue maintenance?").
- Show linkages to other JD basin habitat projects, coordination may be desirable with other entities, such as SWCD, CTWSR, OWT, etc. in addition to ODFW.
- Improve resumes of personnel.
Comment:
Comment:
Fundable, only if effectiveness is being adequately monitored and evaluated by methods compatible with regional monitoring projects (e.g. #s 25088, 199801600, 25010). Monitoring of physical characteristics must be implemented with compatible methods so that inferences can be drawn about changes observed in the John Day in the context of changes occurring in the larger region. Tier 1 monitoring for presence or absence of salmonid species of concern must occur on project sites.Comment:
Statement of Potential Biological Benefit to ESUProject develops and implements riparian fencing and instream structure projects to protect, enhance and restore riparian and instream habitat to improve anadromous salmonid production.
Comments
Effectiveness needs to be adequately monitored & evaluated by methods compatible with regional monitoring projects (e.g., #25088, #199801600, #25010). Monitoring of physical characteristics must be implemented with compatible methods so that inferences can be drawn about changes observed in the John Day in the context of changes occurring in the larger region. Tier 1 monitoring for presence or absence of salmonid species of concern must occur on project sites.
Already ESA Req? no
Biop? yes
Comment:
Although expensive, short-term leases (15 years) are as long or longer than any other program doing riparian protection except those that purchase perpetual easements or buy the land in fee title. Some of these 15-year leases are just about to come up for renewal. ODFW has been experiencing positive feedback from most landowners that they want to continue in the program. There have been some significant improvements to the riparian habitat and stream width-to-depth ratios from this project. ODFW has developed a very good program with the same ODFW representative managing the project for the last 17 years. They know how to implement effectively the fencing, watering devices, maintenance and monitoring of the project. Other groups trying to initiate similar programs use their expertise. They focus the work in the highest priority areas for salmon and steelhead in the John Day Subbasin.Comment:
Comment:
Comment:
Accruals look good. Slight decrease from Council recommendation. Capped some of cost increases.Comment:
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$447,889 | $447,889 | $447,889 |
Sponsor comments: See comment at Council's website