FY 2002 Columbia Plateau proposal 199009200
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199009200 Narrative | Narrative |
199009200 Powerpoint Presentation | Powerpoint Presentation |
Columbia Plateau: Umatilla Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Columbia Plateau: Umatilla Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Protect and Enhance the Wanaket Wildlife Mitigation Area. |
Proposal ID | 199009200 |
Organization | Confederated Tribes of the Umatilla Indian Reservation DNR Wildlife Program (CTUIR) |
Proposal contact person or principal investigator | |
Name | Eric Quaempts |
Mailing address | PO Box 638 Pendleton, OR 97801 |
Phone / email | 5419662389 / ericquaempts@ctuir.com |
Manager authorizing this project | Carl Scheeler |
Review cycle | Columbia Plateau |
Province / Subbasin | Columbia Plateau / Mainstem Columbia |
Short description | Protect, enhance, and mitigate wildlife and wildlife habitats impacted by the McNary Hydroelectric Project |
Target species | California quail, western meadowlark, mallard, yellow warbler, downy woodpecker, spotted sandpiper, and mink. |
Project location
Latitude | Longitude | Description |
---|---|---|
45.875 | -119.2583 | Directly adjacent to the south shore of Lake Wallula (Columbia River) at River Mile 295, approximately 1.4 miles upstream of McNary Dam. |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1993 | BPA acquires Wanaket Wildlife Area Mitigation Project under Columbia Basin Fish and Wildlife Program, securing an estimated 2,274 Habitat Units of protection credit. CTUIR assumes management responsibility. |
1995 | Management plan and update of original HEP analysis completed.Developed management objectives (protect existing habitats, upgrade irrigation infrastructure) and range of acceptable management activities. |
1997 | Rebuilt pumpstation irrigation infrastructure to increase irrigation efficiency. |
1998 | Completed management plan objective of increasing irrigation efficiency through canal and headgate improvements and created an additional 8 acres of emergent wetland habitats. |
1999 | Created 7 additional acres of wetlands. Succession of wetlands to emergent wetland habitats, and moist soil management will contribute toward HU enhancement objectives. |
2000 | Draft management plan initiated to plan operations, maintenance, and enhancements for next five-year period. |
2000 | Created 11 ecological reconnaissance survey plots to document current ecological status of shrub-steppe habitat, compare current conditions to historical conditions, and develop priorities for the management plan update. |
2001 | Through a co-operator funded agreement, created an additional 2 acres of wetland habitats, added 3 additional irrigation headgates to improve water control, and removed 20 acres of Russian olive to increase ease of irrigation operations and maintenance. |
2001 | Completion of management plan update, emphasizing shrub-steppe/grassland enhancements, protection of recently enhanced wetland habitats, and wildlife protection through access and travel management. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Develop 60% native perennial herbaceous cover and limit competing and unwanted vegetation <40% cover on 400 acres of shrub-steppe/grassland habitat to contribute towards the provision of 2,495 HU's of enhancement. | a. Develop site-preparation treatments, planting prescriptions, and monitoring design for FY04 implementation. | 4 | $2,226 | |
b. Planning coordination (Cultural Resources, water rights coordination, interagency and private organizations coordination). | 5 | $6,350 | ||
INDIRECT (.34) | 1 | $2,916 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Develop 60% native perennial herbaceous cover and limit competing and unwanted vegetation <40% cover on 200 acres of shrub-steppe/grassland habitat to contribute towards the provision of 2,495 HU's of enhancement (Task 1.a). | $0 | ||
1.a. Develop site preparation/planting prescriptions and monitoring design. | 2003 | 2006 | $5,930 |
1.b. Planning Coordination. | 2003 | 2006 | $31,951 |
2. Update 5 year, site specific management plan. Review current plan's effectiveness, update existing condtion characterizations, conduct public scoping, develop and publish 5-year action plan w/goals, objectives, desired future conditions, and budget. | 2006 | 2006 | $17,265 |
Outyear budgets for Planning and Design phase
FY 2004 | FY 2003 | FY 2005 | FY 2006 |
---|---|---|---|
$11,615 | $11,917 | $11,733 | $20,440 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Develop 60% native perennial herbaceous cover and limit competing and unwanted vegetation <40% cover on 400 acres of shrub-steppe/grassland habitat to contribute towards the provision of 2,495 HU's of enhancement. | a. Implement noxious weed control subcontracts for control of competing and unwanted vegetation. | 5 | $7,103 | Yes |
b. Implement subcontract for collection, propagation, and acquisition of native perennial bunchgrasses, shrubs. | 2 | $8,688 | Yes | |
c. Implement subcontract for operated equipment for seeding. | 1 | $5,000 | Yes | |
d. Provide coordination, oversight, and inspection of subcontracts. | 5 | $5,815 | ||
e. Coordinate with Bureau of Reclamation to develop and complete opportunity for transfer of 40 acres of grassland from the BOR to the Wanaket Wildlife Area. | 1 | $1,990 | ||
INDIRECT (.34) for tasks d, e. | $2,654 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1.a. Implement noxious weed control subcontracts to control competing and unwanted vegetation < 40% cover. | 2003 | 2006 | $26,268 |
1.b. Implement subcontract for collection, propagation, and acquisition of native plant materials. | 2003 | 2006 | $51,878 |
1.c. Implement subcontract for seeding. | 2003 | 2006 | $29,650 |
1.d. Provide coordination, oversight, and inspection of subcontracts. | 2003 | 2006 | $35,265 |
1.f. Prescribe burning of restoration sites for site preparation. | 2004 | 2005 | $6,865 |
2. Plant native shrubs to provide 15% shrub cover on restoration sites. | 2006 | 2006 | $3,883 |
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$34,790 | $39,658 | $41,115 | $37,453 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Operate and maintain the Wanaket Wildlife Area to provide 3,832 Habitat Units of protection credit. | a. Maintain 12 miles of project boundary fence, signs, pumphouse, outbuildings, kiosks. | 5 | $14,303 | |
b. Develop subcontract for irrigation pump maintenance. | 1 | $1,706 | ||
c. Implement subcontract for irrigation pump maintenance. | 1 | $18,835 | Yes | |
d. Develop subcontract for intake fish screen maintenance. | 5 | $255 | ||
e. Implement subcontract for intake fish screen maintenance. | 5 | $1,323 | Yes | |
f. Maintain irrigation canals, headgates. | 5 | $19,733 | ||
g. Irrigation costs (electricity). | 5 | $11,101 | Yes | |
h. Develop subcontract for noxious weed control. | 5 | $255 | ||
i. Implement subcontract for noxious weed control. | 5 | $10,800 | Yes | |
j. Coordinate/inspect implementation of subcontracts. | 5 | $6,700 | ||
k. Implement and provide oversight of Access and Travel Management regulations. | 5 | $12,503 | ||
l. Develop subcontract for mosquito (vector) control. | 5 | $255 | ||
m. Provide mosquito control to reduce potential vector problems. | 5 | $4,000 | Yes | |
n. Coordinate with BPA, including development and submission of annual Statement of Work and Budget, quarterly reports, annual report, purchasing, financial reporting, and other coordination as needed. | 5 | $30,538 | ||
INDIRECT (.34) a, b, d, f, h, j - l. | Ongoing | $29,238 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Operate and maintain the Wanaket Wildlife Area to provide 3,832 Habitat Units of protection credit. | 2003 | 2006 | $0 |
a. Maintain 12 miles project boundary fence, signs/kiosks, pumphouse, outbuildings. | 2003 | 2006 | $64,730 |
d. Develop subcontract for fish screen maintenance. | 2003 | 2006 | $1,154 |
e. Implement subcontract for fish intake screen maintenance. | 2003 | 2006 | $5,987 |
f. Maintain irrigaiton canals, headgates. | 2003 | 2006 | $89,304 |
g. Irrigaration costs (electricity). | 2003 | 2006 | $59,421 |
h. Develop subcontract for noxious weed control. | 2003 | 2006 | $1,546 |
i. Implement subcontract for noxious weed control. | 2003 | 2006 | $48,877 |
j. Coordinate/inpsect implementation of contracts. | 2003 | 2006 | $30,322 |
k. Provide oversight of ATM programs. | 2003 | 2006 | $56,584 |
l. Develop subcontract for mosquito (vector) control. | 2003 | 2006 | $1,154 |
m. Implement mosquito control to reduce/eliminate potential vector problems. | 2003 | 2006 | $38,792 |
n. Coordinate with BPA, including development and submission of annual Statement of Work and Budget, quarterly reports, annual report, purchasing, financial reporting, and other coordination as needed. | 2003 | 2006 | $138,204 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$153,113 | $161,639 | $170,696 | $180,322 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Monitor effectiveness of habitat protection and enhancement activities and Access/Travel Management Regulations. | a. Repeat photography at monitoring points of FY01 restoration sites. | 3 | $2,845 | |
b. Read transects and monitor % cover by species on FY01 restoration sites. | 3 | $2,226 | ||
c. Process, label, and organize photography. | 5 | $1,219 | ||
d. Establish pre-implementation monitoring transects and photo-points for out-year enhancements (FY04-06). | 1 | $1,627 | ||
e. Develop sub-contract for plant taxonimist to assist with reading monitoring transects, reporting results. | 1 | $397 | ||
f. Implement sub-contract for plant taxonimist to assist with reading monitoring transects and reporting results. | 1 | $3,480 | Yes | |
g. Conduct 2 breeding pair surveys for avifauna, enter data in e-database. | 5 | $1,089 | ||
h. Conduct 3 brood counts for waterfowl, enter data in e-database. | 5 | $1,448 | ||
i. Record recreation hours of use and upland/waterfowl harvest in e-database. | 5 | $1,089 | ||
INDIRECT (.34) | $3,758 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1.a. Repeat photography at monitoring points of FY01 & FY04 restoration sites. | 2004 | 2006 | $13,250 |
1.b. Read monitoring transects (% cover) of FY01 & FY04 restoration sites. | 2004 | 2006 | $22,241 |
1.c. Process, label, organize photography. | 2004 | 2006 | $5,676 |
d. Establish pre-implementation monitoring transects and photo-points for out-year enhancements (FY04-06). | 2003 | 2003 | $2,289 |
e Developsub-contract for plant taxonimist to assist with reading monitoring transects and reporting results. | 2006 | 2006 | $587 |
f. Implement sub-contract for plant taxonimist to assist with reading monitoring transects and reporting results. | 2003 | 2006 | $4,230 |
1.g. Conduct 2 breeding pair surveys for avifauna, enter data in e-database. | 2003 | 2006 | $6,604 |
1.h. Conduct 3 brood counts for waterfowl, enter data in e-database. | 2003 | 2006 | $8,781 |
1.i. Collect records of public use, upland game/waterfowl harvest, enter data in e-database. | 2003 | 2006 | $6,604 |
Objective 2. Conduct 10-year HEP analysis to measure changes in habitat suitability for project mitigation species since project acquisition. | 2003 | 2003 | $0 |
2.a Conduct field surveys for target mitigation species. | 2003 | 2003 | $13,829 |
2.b. Prepare HEP Report . | 2003 | 2003 | $3,992 |
Outyear budgets for Monitoring and Evaluation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$25,211 | $18,416 | $19,336 | $25,121 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: 2.1 | $71,209 |
Fringe | .30 of salaries. | $21,512 |
Supplies | fence material, signs, office supplies | $15,190 |
Travel | GSA Rental, mileage, insurance | $10,093 |
Indirect | .34 (applies to all budget items NOT subcontracted). | $39,131 |
Capital | $0 | |
NEPA | Incorporated into planning coordination costs. | $0 |
Subcontractor | Umatilla County Weed Control | $17,903 |
Subcontractor | Unidentified scuba diver/intake screen cleaner contractor. | $1,323 |
Subcontractor | Unidentified irrigation pump servicing contractor. | $18,835 |
Subcontractor | Unidentified nursery/seed propagation contractor. | $8,688 |
Subcontractor | Unidentified seed application equipment contractor. | $5,000 |
Subcontractor | Umatilla Electric Co-Operative, electricity provider. | $11,101 |
Subcontractor | Unidentified botanist/taxonomist contractor for surveys. | $3,480 |
$223,465 |
Total estimated budget
Total FY 2002 cost | $223,465 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $223,465 |
FY 2002 forecast from 2001 | $220,056 |
% change from forecast | 1.5% |
Reason for change in estimated budget
Increase is a result of refining budget over previous estimate.
Reason for change in scope
n/a
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable - no response required
Jun 15, 2001
Comment:
Fundable. This proposal identifies its significance. Cost is relatively high compared to other areas perhaps due to irrigation costs for wetlands. M&E is adequate for Tier 1 level monitoring. However, evaluation and monitoring efforts should be strengthened by specifying how much improvement/change in target species is to be accomplished and how the changes will be documented (see ISRP general comments at beginning of this report).
This proposal is for routine continuation of operation and maintenance on 2750 acres. Irrigation of wetlands must be continued indefinitely causing concern about electricity costs in tight energy markets and availability of water in drought years. During the presentation they demonstrated that they had a plan for alternative activities if power prices become prohibitive.
Comment:
Comment:
Fundable. This proposal identifies its significance. This proposal is for routine continuation of operation and maintenance on 2750 acres. Irrigation of wetlands must be continued indefinitely causing concern about electricity costs in tight energy markets and availability of water in drought years. During the presentation they demonstrated that they had a plan for alternative activities if power prices become prohibitive. M&E is adequate for Tier 1 level monitoring. However, evaluation and monitoring efforts should be strengthened by specifying how much improvement/change in target species is to be accomplished and how the changes will be documented (see ISRP general comments at beginning of this report). Cost is relatively high compared to other areas perhaps due to irrigation costs for wetlands.Comment:
Statement of Potential Biological Benefit to ESUN/A
Comments
Already ESA Req? N/A
Biop? no
Comment:
Comment:
Comment:
Behind on irrigation for intake screen approval. Could be heavy invoicing toward end of year. Indirect cost increases.Comment:
For FY 04 CTUIR is seeking a total increase of $26,677 to cover NMFS recommendations and unfunded Indirect Increases. In mid-2003, NMFS determined that the intake screens at Wanaket needed to be replaced, this replacement will cost $15,976. The other increase for FY 04 is to cover unfunded increases in Indirect Rates for previous years. Unfunded 2002 Indirect Increase @ $3,374 and Unfunded 2003 Indirect Increase @ $7.327.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$150,000 | $225,978 | $225,978 |
Sponsor comments: See comment at Council's website