FY 2002 Columbia Plateau proposal 199503300

Section 1. Administrative

Proposal titleO&M Of Yakima Phase II Fish Facilities*
Proposal ID199503300
OrganizationU.S. Bureau of Reclamation, Yakima Field Office (BOR)
Proposal contact person or principal investigator
NameKate Puckett
Mailing addressPO Box 1749 Yakima, WA 98907-1749
Phone / email5095755848 / kpuckett@pn.usbr.gov
Manager authorizing this projectDavid Murillo, USBR, Yakima Field Office Manager
Review cycleColumbia Plateau
Province / SubbasinColumbia Plateau / Yakima
Short descriptionOperate and maintain BPA owned fish screening and trapping facilities located throughout the Yakima River basin to prevent injury or mortality to anadromous and resident fish, and to protect BPA's capital investment.
Target speciesAnadromous steelhead (ESA listed), spring & fall chinook and coho Incidental benefits to resident bull trout (ESA listed), rainbow and brook trout and whitefish.
Project location
LatitudeLongitudeDescription
46.628 -120.7703 Bachelor-Hatton Screens
46.9783 -120.5702 Bull Screens
46.7318 -120.7307 Clark Screens
46.6752 -120.6525 Congdon Screens
47.0233 -120.6052 Ellensburg Mill Screens
46.6248 -120.5597 Fruitvale Screens
46.6848 -120.652 Gleed Screens
46.5375 -120.8817 Johncox Screens
46.7318 -120.731 Kelly/Lowery Screens
46 -120 LaFortune/Powell Screens
46.853 -120.954 Lindsey Screens
46.7387 -120.8005 Naches/Cowiche Screens
46.7387 -120.8008 Naches/Selah Screens
47.0397 -120.631 New Cascade Screens
46.6248 -120.5513 Old Union Screens
46.75 -120.4583 Roza Adult Fish Trap
46.4357 -120.3383 Snipes/Allen Screens
46.6847 -120.4853 Taylor Screens
46.329 -120.5525 Toppenish Pump Screens
46.625 -120.5582 Union Gap Screens
46 -120 Wilson/Bull Screens
46.5347 -120.606 WIP Lower Screens
46.5275 -120.7768 WIP Upper Screens
47.1827 -120.9257 Younger Screens
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1992 Construction of the first Phase II fishscreens (Nachess-Cowiche & Kiona) is completed and USBR begins O&M duties.
1993 Add new sites: Gleed, Snipes Allen & Taylor fishscreens for a total of 5. O&M performed on all sites.
1994 Add new sites: New Cascade, Congdon & Kelly-Lowery fishscreens for a total of 8. O&M performed on all sites.
1995 Add new sites: Roza Adult Fish Trap & Bachelor-Hatton fishscreens for a total of 10. O&M performed on all sites.
1996 Add new sites: Toppenish Pump, Fruitvale & Naches-Selah fishscreens, abandon Kiona Screens, for a total of 12. O&M performed on all sites.
1997 Add new sites: Bull, Ellensburg Mill, Clark, Lindsey , Union Gap, WIP Upper & WIP Lower fishscreens for a total of 19. O&M performed on all sites.
1998 Add new sites: Younger & Old Union fishscreens for a total of 21. O&M performed on all sites.
1999 Add new sites: Johncox fishscreens for a total of 22. O&M performed on all sites.
2000 No new sites added: O&M performed on all sites.
2001 Add new sites: Wilson/Bull & LaFortune/Powell fishscreens for a total of 24. O&M will be performed on all sites.

Section 3. Relationships to other projects

Project IDTitleDescription
9107500 Yakima Phase II Screen Construction Funding source for design and construction of Phase II facilities by USBR.
9200900 Yakima Screens - Phase II O&M Funding source for O&M of Phase II facilities by Washington Dept of Fish & Wildlife. Facility custody is passed to USBR by BPA, however O&M duties are accomplished through a cooperative effort between USBR and WDFW
9105700 Yakima Phase II Screen Fabrication Funding source for fabrication of Phase II facility drumscreens by Washington Dept of Fish & Wildlife.
8506200 Passage Improvement Evaluation Funding source for periodic independent monitoring and evaluation of the effectiveness of Phase II facilities by Battelle Pacific NW Laboratories scientists.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1. O&M of Bachelor-Hatton Screens a. Technical support & supervision Life of facility $480
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $210
f. Materials & supplies " " $2,000
g. O&M contract reimbursements " " $4,700 Yes
2. O&M of Bull Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
3. O&M of Clark Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
4. O&M of Congdon Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
5. O&M of Ellensburg Mill Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
6. O&M of Fruitvale Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
7. O&M of Gleed Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
8. O&M of Johncox Screens a. Technical support & supervision " " $480
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $210
f. Materials & supplies " " $2,000
9. O&M of Kelly-Lowery Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
10. O&M of LaFortune/Powell Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
11. O&M of Lindsey Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
12. O&M of Naches-Cowiche Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
13. O&M of Naches-Selah Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
14. O&M of New Cascade Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
15. O&M of Old Union Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
16. O&M of Roza Adult Fish Trap a. Technical support & supervision " " $1,200
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $1,048
f. Facility modifications " " $5,129
g. Materials & supplies " " $14,000
17. O&M of Snipes-Allen Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
18. O&M of Taylor Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
19. O&M of Toppenish Pump Screens a. Technical support & supervision " " $480
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $210
f. Materials & supplies " " $2,000
g. O&M contract reimbursements " " $5,000 Yes
20. O&M of Union Gap Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
21. O&M of Wilson/Bull Screens a. Technical support & supervision " " $120
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
22. O&M of WIP Lower Screens a. Technical support & supervision " " $480
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $210
f. Materials & supplies " " $2,000
g. O&M contract reimbursements " " $3,000 Yes
23. O&M of WIP Upper Screens a. Technical support & supervision " " $480
b. PM recordkeeping & operation manuals " " $53
c. Facility operation & maintenance " " $1,710
d. Gantry crane & lock maintenance " " $85
e. Electrical maintenance & callout " " $210
f. Materials & supplies " " $2,000
g. O&M contract reimbursements " " $3,000 Yes
24. O&M of Younger Screens a. Technical support & supervision " " $134
b. PM recordkeeping & operation manuals " " $53
c. Gantry crane & lock maintenance " " $85
d. Electrical maintenance & callout " " $52
e. Mutual assistance to WDFW " " $85
f. Materials & supplies " " $500
25. Benefits & Additives a. Benefits & Additives " " $13,938
26. Indirect Costs a. Indirect Costs " " $16,116
27. Review of Operation & Maint. Exams a. Congdon Screens FY2001 $500
b. Johncox Screens " " $500
c. Snipes/Allen Screens " " $500
d. Taylor Screens " " $500
e. WIP Upper Screens " " $500
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. O&M of above listed sites will continue for the life of those facilities. An additional $4,000 has been added to 2003 to account for 3 additional sites, plus $,4,000/yr has been added to account for inflation. 2003 2006 $496,000
Outyear budgets for Operations and Maintenance phase
FY 2003FY 2004FY 2005FY 2006
$118,000$122,000$126,000$130,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2002 cost
Personnel FTE: 1 $29,039
Fringe 48% of labor $13,938
Supplies $33,000
Indirect 35% of labor & fringe $16,116
Subcontractor Wapato Irrigation Project $11,000
Subcontractor Athanam Irrigation District $4,700
Other RO&M Examinations $2,500
$110,293
Total estimated budget
Total FY 2002 cost$110,293
Amount anticipated from previously committed BPA funds$0
Total FY 2002 budget request$110,293
FY 2002 forecast from 2001$115,000
% change from forecast-4.1%
Reason for change in estimated budget

Refinement of estimates

Reason for change in scope

n/a

Cost sharing
OrganizationItem or service providedAmountCash or in-kind
None $0 cash

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable - no response required
Date:
Jun 15, 2001

Comment:

This proposal would continue O & M on Yakima basin screens, clearly an essential, routine component of the process. Reviewers appreciated the itemization of the facilities receiving that O & M, as well as the detailed description of the complicated operational and fiscal interactions among the groups and agencies involved.


Recommendation:
High Priority
Date:
Aug 3, 2001

Comment:


Recommendation:
Fund
Date:
Aug 10, 2001

Comment:

Fundable. This proposal would continue O & M on Yakima basin screens, clearly an essential, routine component of the process. Reviewers appreciated the itemization of the facilities receiving that O & M, as well as the detailed description of the complicated operational and fiscal interactions among the groups and agencies involved.
Recommendation:
Date:
Oct 1, 2001

Comment:

Statement of Potential Biological Benefit to ESU
Operate and maintain BPA owned fish screening and trapping facilities located throughout the Yakima basin/

Comments
The proposal would continue O&M clearly an essential, routine component of the process.

Already ESA Req? no

Biop? no


Recommendation:
Rank A
Date:
Oct 16, 2001

Comment:

There is no cost sharing and the project appears to overlap with 1992-009-00. See Phase II screen comments above. There may be excessive costs because of redundancy.
Recommendation:
Fund
Date:
Jan 3, 2002

Comment:


Recommendation:
Fund
Date:
Mar 6, 2002

Comment:


Recommendation:
Fund
Date:
Sep 20, 2003

Comment:

Ongoing O&M for screens.
Recommendation:
Date:
Sep 20, 2003

Comment:


REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$110,551 $100,551 $100,551

Sponsor comments: See comment at Council's website