FY 2002 Columbia Plateau proposal 199901300
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199901300 Narrative | Narrative |
199901300 Sponsor Response to the ISRP | Response |
199901300 Powerpoint Presentation | Powerpoint Presentation |
Columbia Plateau: Yakima Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Columbia Plateau: Yakima Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Ahtanum Creek Watershed Assessment |
Proposal ID | 199901300 |
Organization | Yakama Nation Fisheries Program (YN) |
Proposal contact person or principal investigator | |
Name | Tom McCoy |
Mailing address | P.O. Box 151 Toppenish, WA 98948 |
Phone / email | 5098656262 / tmccoy@yakama.com |
Manager authorizing this project | Lynn Hatcher |
Review cycle | Columbia Plateau |
Province / Subbasin | Columbia Plateau / Yakima |
Short description | Conduct a watershed assessment in the agricultural portion of the Ahtanum Creek watershed to complete assessment of the entire watershed, facilitate protection and restoration of salmon, steelhead, bull trout. |
Target species | Bull trout (Threatened, June 1998); Mid-Columbia ESU Summer Steelhead (Threatened, March 1999) |
Project location
Latitude | Longitude | Description |
---|---|---|
46.5098 | -121.0217 | Western and Upstream Terminus, Unnamed irrigation diversion on South Fork Ahtanum Creek near USGS Gage (inactive) 12501000 South Fork Ahanum Creek at Conrad Ranch near Tampico, WA, S. Fk. Ahtanum River Mile 4.0. |
46.5365 | -120.4767 | Eastern and Downstream Terminus, Confluence of Ahtanum Creek and the Yakima River, Yakima River Mile 106.9. |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS | Action 154 | NMFS | BPA shall work with the NWPPC to ensure development and updating of subbasin assessments and plans; match state and local funding for coordinated development of watershed assessments and plans; and help fund technical support for subbasin and watershed plan implementation from 2001 to 2006. Planning for priority subbasins should be completed by the 2003 check-in. The action agencies will work with other Federal agencies to ensure that subbasin and watershed assessments and plans are coordinated across non-Federal and Federal land ownerships and programs. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1999 | Project inaugurated May, 1999. Identified locations for discharge transects and thermograph emplacements, began weekly discharge data collection, began Project GIS, performed cursory investigations into salmonid species utilization in Project waterways. |
2000 | Collected weekly discharge and daily water temperatures, operated 5-foot screwtrap to determine outmigrant timing, species composition, age and DNA status, documented steelhead juveniles in dewatered reaches, expanded steelhead spawning survey coverage. |
2001 | Continued 5-foot screwtrap operation, increased discharge collection frequency to twice weekly, expanded steelhead spawning survey coverage, began analysis Landsat Thematic Image data, expanded Project GIS, expanded coho spawning survey coverage. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
199705300 | Toppenish-Simcoe Instream Flow Restoration and Assessment | Companion project interms of philosophy, personnel and logistics. Data collection routines and methods for 199901300 were derived from 199705300. In the past, personnel have been shared between the two projects, saving money and maximizing efficiency. |
199206200 | Yakima Nation Wetlands and Riparian Restoration | The land acquisition, wildlife management and vegetation restoration portion of 199901300 is totally dependent on expertise and personnel covered under 199206200. |
199603501 | Satus Watershed Restoration | 199603501 provides upland restoration technical assistance, technician assistance for spawner surveys, PFC expertise, equipment and manpower for field data collection. |
199803300 | Restore Upper Toppenish Creek Watershed | Support from this project comes mainly in the form of technical expertise and manpower assistance during spawning surveys and other field activities. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Map irrigation systems utilizing creek water. | 1a. Continue to incorporate GIS coverages, orthophotos, district maps into overall Project GIS. | Ongoing yearly activity | $8,500 | |
1b. Add new delivery and drainage system features as they are discovered. | Ongoing yearly activity | $2,500 | ||
1c. Add cropping patterns from crop reports as they are received, continue Landsat Thematic Mapper Image analysis. | Ongoing yearly activity | $2,500 | ||
1d. Ground-truth GIS data, update Project GIS. | Ongoing yearly activity | $7,500 | ||
2. Model irrigation water use. | 2a. Continue to measure water withdrawals from and returns to Ahtanum Creek. | Ongoing yearly activity | $7,500 | |
2b. Assess consumptive use and irrigation efficiency, update assessment data. | Ongoing yearly activity | $6,500 | Yes | |
3. Describe streamflow and water temperature regime. | 3a. Continue measurement of temporal and spatial watercourse (creeks, canals, ditches, drains) flow and temperature regime to provide adequate data for descriptive flow model (Overlaps with 2a but focuses more on detecting seepage losses and gains). | Ongoing yearly activity | $5,500 | |
3b. Analyze Project and historic discharge data to determine magnitude and timing of alternative diversion strategies. | Ongoing yearly activity | $2,500 | ||
3c. Continue development and calibration of descriptive model of flow by location and season. | Ongoing yearly activity | $6,250 | ||
3d. Finalize integration of WA-DNR information and recommendations from upper watershed analysis. | Ongoing yearly activity | $3,500 | ||
4. Survey creek channel and floodplain. | 4a. Conduct qualitative assessment of riparian functional status (PFC). | Ongoing (re-evaluated every 2 years) | $2,500 | |
5. Describe fish population response to habitat changes. | 5a. Assess current and potential salmon and steelhead production (pre-development conditions) as well as extent of bull trout in creek. | Ongoing yearly activity | $4,500 | |
5b. Describe response to changes in water withdrawal, return flows and riparian management. | Ongoing yearly activity | $11,649 | ||
5c. Continue development of Project Assessment document. | Ongoing (continued until all pertinent info and options are described and the Assessment Document is complete) | $32,500 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Map irrigation systems utilizing creek water. | 2003 | 2006 | $64,500 |
2. Model irrigation water use (Subcontractor). | 2003 | 2004 | $6,500 |
3. Describe streamflow and water temperature regime. | 2003 | 2006 | $45,000 |
4. Survey creek channel and floodplain. | 2003 | 2006 | $29,500 |
5. Describe fish population response to habitat changes. | 2003 | 2006 | $94,500 |
Outyear budgets for Planning and Design phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$75,000 | $65,000 | $55,000 | $45,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Adaptively update Project Assessment document, begin implementation of recommendations (late in FY2002). | 1a. Integrate products of Objectives 1-5, Planning and Design Phase. | Ongoing yearly activity | $11,225 | |
1b. Finalize Irrigation Assessment Alternative Report produced by subcontractor in FY2001. | 0.5 | $2,500 | ||
1c. Approach Yakama Tribal Council for approval of Project Assessment by Tribal Council Resolution, management support and help in disseminating Project scope and objectives to affected landowners. | 0.5 | $3,200 | ||
1d. Restore instream flow to dewatered Project stream reaches by system modifications and/or land purchase or lease. | Ongoing, will continue task until all available water is returned to Project streams | $8,197 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Adaptively update Project Assessment document, begin implementation of recommendations (late in FY2002). | 2003 | 2006 | $40,000 |
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$10,000 | $10,000 | $10,000 | $10,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Work with YN Wildlife Program and BIA Realty to acquire leases or purchase lands. | 1a. Prepare written justification for leases or purchase, assist other YN and BIA personnel with lease/purchase agreements. | Ongoing, As Required | $3,200 | |
1b. Present any required background information to appropriate Council and colleagues. | Ongoing, As Required | $2,500 | ||
1c. Maintain and enforce lease requirements. | Ongoing, Duration of leases (10 years) | $12,800 | ||
1d. On lands purchased with Project funds, decommission withdrawal structures and work with other YN programs to inaugurate any restoration measures needed to return land to native state. | Ongoing, As Required | $2,500 | ||
2. Restrict diversion timing, where possible, to periods when discharge is not limiting to aquatic ecosystem health. | 2a. Monitor discharge in and around project watercourses affected by Objective 2 to enforce Project goals. | Ongoing, Duration of leases (10 years) | $20,600 | |
2b. Identify willing landowners to decrease or cease late spring-summer diversions to benefit fish and aquatic life (can hopefully be used in conjunction with Objective 3). | Ongoing, As Required | $3,500 | ||
3. Work with agricultural interests to enact voluntary diversion reductions that leave water in-stream for fish and aquatic ecosystem purposes. | 3a. Work with BIA, YN and private landowners to develop plans for diversion reduction agreements. | Ongoing, As Required | $3,200 | |
3b. Identify funding sources when monies are needed to develop agreements. | Ongoing, As Required | $1,500 | ||
3c. Enforce diversion reduction scenarios and monitor compliance | Ongoing, Duration diversion reduction agreeements | $2,592 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Work with YN Wildlife Program and BIA Realty to acquire leases or purchase lands. | 2003 | 2006 | $200,000 |
2. Restrict diversion timing, where possible, to periods when discharge is not limiting to aquatic ecosystem health. | 2003 | 2006 | $110,000 |
3. Work with agricultural interests to enact voluntary diversion reductions that leave water in-stream for fish and aquatic ecosystem purposes. | 2003 | 2006 | $110,000 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$150,000 | $120,000 | $75,000 | $75,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Monitor Project Area Water budget. | 1a. Measure watercourse discharge and temperature over time and space at key locations specified by O&M Objectives 1-3. | Ongoing pending funding | $22,500 | |
2. Maintain database of channel and riparian condition. | 2a. Assess channel morphology and condition as necessary pursuant to streamflow restoration efforts. PFC index sites will be re-evaluated every 2 years to establish trends over time. | Ongoing pending funding | $2,500 | |
3. Monitor aquatic ecosystem health and aquatic species assemblages. | 3a. Continue operation of 5-foot screwtrap to describe steelhead smolt outmigration timing, age structure and relative number of outmigrants per year. | Ongoing pending funding | $7,500 | |
3b. Continue yearly electrofishing and snorkel surveys to index relative abundance of salmonid juveniles in Project Area. | Ongoing pending funding | $7,500 | ||
3c. Monitor numbers of returning steelhead adults by yearly spawning ground surveys and adult counts at Prosser and Roza monitoring windows. | Ongoing pending funding | $13,680 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Monitor Project Area Water budget. | $20,000 | ||
2. Maintain database of channel and riparian condition. | $15,000 | ||
3. Monitor aquatic ecosystem health and aquatic species assemblages. | $15,000 |
Outyear budgets for Monitoring and Evaluation phase
FY 2006 | FY 2003 | FY 2004 | FY 2005 |
---|---|---|---|
$50,000 | $50,000 | $50,000 | $50,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: 3.775 | $117,128 |
Fringe | 17.6% for Exempt FTE's, 20% for Non-Exempt | $22,018 |
Supplies | Office supplies, field supplies, repairs, field and office equipment | $12,700 |
Travel | Travel, per diem, and tuition for presentations, workshops and meetings (lumped for all personnel) | $5,000 |
Indirect | 19.5% on all items in budget except Professional Services | $37,302 |
Capital | Land Rental (160 acres land w/ water @ $80/acre) | $12,800 |
NEPA | BPA Supplemental Analysis Complete | $0 |
PIT tags | # of tags: 0 | $0 |
Subcontractor | Irrigation consultant assistance with analyses and assessment of alternative methods | $6,500 |
Other | Utilities, building depreciation, vehicle rental and mileage, insurance, repairs and maintenance | $21,645 |
$235,093 |
Total estimated budget
Total FY 2002 cost | $235,093 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $235,093 |
FY 2002 forecast from 2001 | $225,000 |
% change from forecast | 4.5% |
Reason for change in estimated budget
The slight increase in budget reflects cumulative salary merit increases, awarded on a yearly basis.
Reason for change in scope
No appreciable change in scope has occurred since the inauguration of this Project.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Jun 15, 2001
Comment:
Fundable if adequate responses are given to ISRP concerns. The proposal was too vague to enable assessment. The presentation was good and the proposal needs to raise to that level; e.g. the presentation included data, clear objectives, maps, trend data, etc . What are the fish benefits? Is this a system that has potential? The proposal would be stronger if there were better quantification of the potential for beneficial management intervention that would be guided by the assessment. This one like the Toppenish-Simcoe, needs tribal council approval in near future. What are the alternatives if there is not tribal council approval?
Comment:
This creek could be a substantial piece for steelhead recovery in the Yakima subbasin. This project will help design the fix.Comment:
Fundable, but in future submittals and in the statement of work to BPA they should include milestones specifically a date when the assessment is going to be done. The response was marginal and the proposal was not up to the standards of the other Yakama Nation habitat proposals.Comment:
Statement of Potential Biological Benefit to ESUIndirect effect since the project is to design treatments for instream flow and other watershed problems based on understanding of the ecology of anadromous fish in Ahtanum Creek.
Comments
Solid approach to assessing and eventually treating watershed scale problems. Concerned that assessment phase has taken or will take 6 years to complete. There are no milestones specifying when the assessment is going to be done.
Already ESA Req? no
Biop? yes
Comment:
No cost-share. Does not appear to be currently highly productive habitat or a high priority sub-basin. The sponsor requests the same funding as for productive areas (Satus, Toppenish); potentially not cost-effective.Comment:
Comment:
Comment:
Looking for the review process numbers proposed. Accruals are looking good. Possible within year request for additional funds. 05 number represents implementation of the assessment work, would be a scope change. Assessment should be complete in the next few months. Would go into full implementation in next year.Comment:
The existing project was initially intended to perform the analytical steps necessary to identify fish rehabilitation measures. Preliminary recommendations have been implemented and the results have been positive and immediate. We have observed juvenile chinook in Ahtanum Creek for the first time in decades. Similarly, adult bull trout have been observed in the lower creek for the first time since the early 1960's. Steelhead redd counts have also increased steadily as have outmigrating smolt numbers. Ahtanum Creek is also one of the strongholds for coho in the Yakima Subbasin. The final watershed analysis document is nearing completion. To effectively continue implementing the rehabilitation recommendations we will require the full $245,000 requested in the original FY2001 proposal. Considering the success achieved to date, increased funding in FY2005 would be warranted and well spent. Thus, we are requesting an FY2005 budget of $327,000.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$221,314 | $221,314 | $221,314 |
Sponsor comments: See comment at Council's website