FY 2002 Columbia Plateau proposal 200001900
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Section 1. Administrative
Proposal title | Tucannon River Spring Chinook Captive Broodstock Program |
Proposal ID | 200001900 |
Organization | Washington Department of Fish & Wildlife (WDFW) |
Proposal contact person or principal investigator | |
Name | Michael P. Gallinat |
Mailing address | 401 S. Cottonwood Dayton, WA 99328-1501 |
Phone / email | 5093824755 / gallimpg@dfw.wa.gov |
Manager authorizing this project | Mark L. Schuck |
Review cycle | Columbia Plateau |
Province / Subbasin | Columbia Plateau / Tucannon |
Short description | Conduct the Tucannon River spring chinook captive broodstock program. Rear and spawn broodstock, raise their progeny and release up to an additional 150,000 smolts into the Tucannon River to rebuild their run and prevent extinction. |
Target species | Tucannon River Spring Chinook (Part of Snake River Spring/Summer ESU) |
Project location
Latitude | Longitude | Description |
---|---|---|
46.589 | -117.2295 | Lyons Ferry Hatchery - 13780 Hwy 261, Starbuck, WA 99359-0278 |
46.322 | -117.6575 | Tucannon Fish Hatchery - 2303 Tucannon Rd., Pomeroy, WA 99347-9601 |
46.2527 | -117.6738 | Curl Lake Acclimation Pond - Range 44E, Township 07N, Section 33, Columbia County |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Action 177 |
Action 176 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS | Action 176 | NMFS | BPA shall, in coordination with NMFS, USFWS, and the relevant state and Tribal comanagers, fund the development of HGMPs for the Grande Ronde and Tucannon spring/summer chinook safety-net programs. |
NMFS | Action 177 | NMFS | In 2002, BPA shall begin to implement and sustain NMFS-approved, safety-net projects. |
NMFS/BPA | Action 177 | NMFS | In 2002, BPA shall begin to implement and sustain NMFS-approved, safety-net projects. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1997 | Collect 1997 brood year eggs (from supplementation program) to initiate captive broodstock. |
1998 | Collect 1998 brood year eggs (from supplementation program) to continue captive broodstock. |
Rear 1997 brood year juveniles at Lyons Ferry Hatchery. | |
Planning, site modification designs, and budget proposal for captive broodstock program. | |
Submit FY2000 proposal to CBFWA under the NPPC Fish and Wildlife Program for review and funding by BPA. | |
1999 | Collect 1999 brood year eggs to continue captive broodstock program. |
Use LSRCP funds ($120,000) to begin site modifications at Lyons Ferry Hatchery. | |
Rear and mark by "family" the 1997 and 1998 brood year juveniles. | |
Write and submit the Tucannon Master Plan for 3-step review process. | |
Partially complete site modifications at LFH (ponds to rear captive fish, but no security alarms or overhead covers. | |
Work with BPA in drafting the Environmental Assessment for NEPA compliance. | |
Monitor and document mortality of captive brood fish (1997 and 1998 broods). | |
2000 | Work with BPA to complete Environmental Assessment for NEPA compliance. |
Reply to questions from the ISRP on the Tucannon Master Plan for the captive broodstock program. | |
Install security fencing around the captive rearing ponds. | |
Master Plan accepted by the ISRP and NPPC. | |
Rear and mark by "family" the 1999 brood year juveniles. | |
Sort and conduct first spawning of mature fish from the 1997 brood year. | |
Collect 2000 brood year eggs (from supplementation program) to continue captive broodstock. | |
2001 | Write 2000 Annual Captive Broodstock Report. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
RPA Action 176 | HGMP for Tucannon spring/summer chinook safety-net program. | |
RPA Action 177 | BPA shall implement and sustain NMFS approved safety-net projects. | |
9401806 | Tucannon Model Watershed Program | Provide habitat improvements which may increase in-river survival and aid in recovery of the stock. |
8805301 | Northeast Oregon Hatchery Master Plan | NEOH is linked with Grande Ronde Basin captive broodstock programs, NEOH co-managers support captive broodstock plans for the Tucannon River and will assist in planning and coordination. |
8805305 | NE Oregon Hatchery Master Plan and Facilities - ODFW | NEOH is linked with Grande Ronde Basin captive broodstock programs. |
9604400 | Grande Ronde Basin Spring Chinook Captive Broodstock Program | Provide expertise and advice in captive broodstock rearing, and assist in overall recovery of Snake River spring chinook salmon. |
9801006 | Captive Broodstock Artificial Propagation | Provide expertise and advice in captive broodstock rearing. |
9305600 | Assessment of Captive Broodstock Technology | Provide expertise and advice in captive broodstock rearing. |
9801002 | Captive Rearing Initiative for Salmon River Chinook Salmon - M&E | Provide expertise and advice in captive broodstock rearing, and assist in overall recovery of Snake River spring chinook salmon. |
9606700 | Manchester Spring Chinook Broodstock Project | Provide expertise and advice in captive broodstock rearing techniques. |
9801001 | Grande Ronde Basin Spring Chinook Captive Broodstock Program | Provide expertise and advice in captive broodstock rearing, and assist in overall recovery of Snake River spring chinook salmon. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Raise captive brood fish | a. Conduct daily rearing and raising of captive brood fish (daily feeding, pond cleaning, medical treatments to control mortalities, basic hatchery record keeping for feed fed, mortalities, water inflow, etc. | 5 | $25,096 | |
2. Spawn mature captive brood fish | a. Sort mature fish from immature fish, and separate mature fish to spawning tank. Conduct weekly checks for ripeness during spawning season, and spawn all ripe fish and incubate fertilized eggs. | 5 | $8,229 | |
3. Rear captive brood progeny | a. Pick and record all dead eggs after shocking and determine fecundity and mortality of eggs from each spawned female. Incubate fry until ponding, and then place all captive brood progeny in standard raceways for rearing. | 7 | $9,956 | |
4. Disseminating or collating information | a. Attend captive broodstock meetings, workshops, etc. to learn or pass on information from/to other hatchery programs regarding the captive broodstock program. | 7 | $2,182 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Raise captive brood fish | 2003 | 2006 | $121,716 |
2. Spawn mature captive brood fish | 2003 | 2006 | $39,910 |
3. Rear captive brood progeny | 2003 | 2006 | $48,290 |
4. Disseminating or collating information | 2003 | 2006 | $10,584 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$55,500 | $60,000 | $55,000 | $50,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Monitor and document survival, mortality, and maturity rates of captive brood fish. | a. Assist hatchery staff in monthly record keeping of mortalities and maturation (by family groups) for each brood year. | 5 | $16,778 | |
2. Monitor and document mortality, survival, and viability of captive brood progeny. | a. Assist hatchery staff in egg picking to determine mortality, survival, fecundity, and egg viability of collected captive brood eggs that were fertilized. | 7 | $4,223 | |
3. Permanently identify all 15 families from the 2000 brood year for captive broodstock rearing. | a. Assist hatchery and tagging staff with marking (CWT and VI) of 2000 brood year fish for captive broodstock rearing. | 1 | $1,000 | |
4. Spawn mature captive brood adults. | a. Assist hatchery staff in sorting and spawning of mature captive broodstock (Obj. 2, Task a, O&M phase). | 5 | $14,534 | |
5. Conduct Genetic Monitoring | a. Collect and analyze DNA samples from captive broodstock spawners, from parents to captive broodstock program, and returning spawners. | 7 | $10,000 | |
6. Disseminating or collating information. | a. Write and disseminate annual captive brood report, report monthly progress through Section 10 monthly reports to NMFS, coordination meetings with the CBTOC, and through meetings with the Captive Brood Technical Working Group (co-managers). | 7 | $2,511 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Monitor captive brood fish | 2003 | 2006 | $94,154 |
2. Monitor captive brood progeny | 2003 | 2006 | $23,698 |
3. Permanently identify family groups | 2003 | 2003 | $1,000 |
4. Spawn mature captive brood adults | 2003 | 2006 | $81,557 |
5. Conduct genetic monitoring | 2003 | 2006 | $54,000 |
6. Disseminating and collating information | 2003 | 2006 | $14,091 |
Outyear budgets for Monitoring and Evaluation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$66,000 | $66,000 | $71,500 | $65,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: Hatch. Spec. 3; Fish Health Spec.; Supervision; Sci. Tech. 3; Fish Bio. 2 | $31,200 |
Fringe | Calculated @ 28.5% | $8,892 |
Supplies | Chemicals, genetic sampling, utilities, misc. supplies | $24,110 |
Travel | $1,500 | |
Indirect | Agency overhead @ 25.2% | $16,557 |
PIT tags | # of tags: 1000 | $2,250 |
Other | Fish food | $10,000 |
$94,509 |
Total estimated budget
Total FY 2002 cost | $94,509 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $94,509 |
FY 2002 forecast from 2001 | $94,500 |
% change from forecast | 0.0% |
Reason for change in estimated budget
Not applicable.
Reason for change in scope
Not applicable.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Lower Snake River Compensation Plan (U.S. Fish and Wildlife Service) | Annual LSRCP M&E program for Tucannon spring chinook will provide long-term history and add to evaluation of the captive broodstock program. Annual activities include spawning surveys, adult return estimation, parr production, smolt trapping, etc. | $120,000 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Jun 15, 2001
Comment:
Do not fund unless a response is provided that adequately addresses the ISRP concerns. The proposal failed to adequately address previous ISRP concerns.
The ISRP reviewed the Tucannon 3-Step Master Plan and approved it with a set of conditions focusing on the integration of artificial production issues and timing with habitat improvement actions in the subbasin. An additional requirement was for place greater emphasis on statistical analysis of the data collected during the program's monitoring and evaluation activities. The ISRP noted that future funding would be determined on an annual basis with consideration of the project's results and linkage with habitat work.
This project, the Tucannon River Spring Chinook Captive Broodstock Program, is part of the overall supplementation program designed to rebuild the depressed spring chinook population in the Tucannon River. The very low numbers of returning adults may justify the captive brood aspect of the program, however, it confounds the supplementation portion of the project as far as evaluation or for demonstration as to the efficacy of supplementation.
The proposal provides some recent history on within hatchery results for the last few years, but did not address either of the ISRP's first two conditions:
- WDFW will work with the Tucannon Watershed Council to develop explicit milestones that forge linkages and a coordinated timeline between the habitat restoration activities in the basin and those of the artificial production programs (captive brood and supplementation). The coordinated milestones will help optimize the results of the habitat restoration activities in the Tucannon subbasin with the development of the captive broodstock and supplementation activities; and
- Future annual reports from the WDFW Tucannon artificial production program will place greater emphasis on statistical analysis of the data collected during the program's monitoring and evaluation activities. Statistical analysis and consulting assistance is available within WDFW and should be utilized.
Comment:
Addresses NMFS RPA 176 AND 177. Short-term project that will end in 2008. The goal is establish a return of 3550 adult chinook.Comment:
Fundable. The response effectively addressed the ISRP's concerns, which included a lack of focus on the integration of artificial production issues and timing with habitat improvement actions in the subbasin and a need for greater emphasis on statistical analysis of the data collected during the program's monitoring and evaluation activities.The sponsor's response effectively addressed these issues. Their conclusions concerning supplementation are important and should be an important consideration in other supplementation programs in the Basin. These are findings in support of what was an intuitively obvious limitation for supplementation from the outset. This project was conceived as an emergency action to protect Tucannon chinook until habitat could be restored to the extent needed to support a viable population. The run has subsequently improved and the emergency action may no longer be needed. A problem that may need some attention, however, is the fact that the effective population now consists of fewer than 100 animals (from the 1995 run).
Comment:
Statement of Potential Biological Benefit to ESUprevent extinction of endemic population of SR SSCH in Tucannon River using "safety net" artificial production techniques
Comments
Tucannon River Project specifically identified in RPA 176, implemented consistent with RPA 177.
Already ESA Req? NO
Biop? YES
Comment:
This is a very good project and appears to employ a least-cost approach. This project will last for a defined, short period of time. The primary concern is genetics. Fish for captive broodstock are taken from fish that are already “in the program”. They need to infuse wild gametes more frequently.Comment:
Comment:
Comment:
Somewhat linked to captive propagation. This project will end in FY2008. Captive broodstock will be spawned through FY2006, and progeny from these fish will be reared and marked before release as yearling smolts through FY 2008. .Comment:
Marking costs have gone up, we are switching to medicated feed (Aquamycin) which is more expensive, we had to select fish from the 2002 BY to have extra males on hand at the end of the program for spawning with our females, we are also planting parr along with the smolts due to excess eggs which are the result of better than expected survival of our adult broodstock, more fish also means more genetic samples. All of this is now included under our budget request.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$126,500 | $126,500 | $126,500 |
Sponsor comments: See comment at Council's website