FY 2001 High Priority proposal 23005

Additional documents

TitleType
23005 Narrative Narrative
Budget Erratum Narrative Attachment

Section 1. Administrative

Proposal titleDevelop an Anadromous Salmonid Habitat Carrying Capacity Model
Proposal ID23005
OrganizationUniversity of Idaho (UI)
Proposal contact person or principal investigator
NameErnie Brannon, Ph.D.
Mailing addressUniversity of Idaho Aquaculture Research Institute Moscow, ID 83844-2260
Phone / email2088857860 / aqua@uidaho.edu
Manager authorizing this projectTed Morhorst
Review cycleFY 2001 High Priority
Province / SubbasinMountain Snake /
Short descriptionDevelop a model of carrying capacity for juvenile salmonids using a combination of field laboratory and field sites.
Target specieschinook, coho, steelhead
Project location
LatitudeLongitudeDescription
46.474 -116.7653 Potlatch Canal
46.3717 -116.1697 Lolo Creek
46.5114 -114.7606 Papoose Creek
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel $137,358
Fringe $31,494
Supplies $7,500
Travel $15,000
Indirect $49,758
Subcontractor $134,785
$375,895
Total estimated budget
Total FY 2001 cost$375,895
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$375,895
FY 2001 forecast from 2000$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Potlatch electricity/maintanence $105,000 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
N/A
Date:
Feb 1, 2001

Comment:

This proposal does not address imminent risks to ESA stocks by offering direct on-the-ground benefits with one-time funding. This proposal offers assessment capabilities.
Recommendation:
HP "B" S
Date:
Feb 1, 2001

Comment:

This project should be considered for subbasin assessments and subbasin planning. The model would greatly assist subbasin planning for supplementation activities.