FY 2001 High Priority proposal 23016

Additional documents

TitleType
23016 Narrative Narrative

Section 1. Administrative

Proposal titleReconnection of floodplain slough habitat to the Kootenai River
Proposal ID23016
OrganizationKootenai Tribe of Idaho (KTOI)
Proposal contact person or principal investigator
NameScott Soults
Mailing addressP.O. Box 1269 Bonners Ferry, ID 83805
Phone / email2082673620 / soults@kootenai.org; jascott@jub.com
Manager authorizing this projectScott Soults
Review cycleFY 2001 High Priority
Province / SubbasinMountain Columbia / Kootenai
Short descriptionReconnect slough and floodplain habitat that has been isolated from the Kootenai River by dikes.
Target speciesKootenai River white sturgeon
Project location
LatitudeLongitudeDescription
48.9999 -116.5027 Kootenai River
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2002
$500,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase
FY 2003FY 2004FY 2005
$40,000$40,000$40,000

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: 0.25 @ $16/hr $8,320
Fringe 33% of salaries $2,746
Indirect 59% of salaries $4,908
Subcontractor For tasks identified in Section 2, including lab work and sample analysis. $124,000
$139,974
Total estimated budget
Total FY 2001 cost$139,974
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$139,974
FY 2001 forecast from 2000$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
N/A
Date:
Feb 1, 2001

Comment:

This resident fish proposal does not address imminent risks to ESA stocks by offering direct on-the-ground benefits with one-time funding. The proposal focuses on assessment and planning. The on-the-ground element appears to be planned for 2002. This proposal is being reviewed as part of the Mountain Columbia review, which is an appropriate venue for review and potential funding.
Recommendation:
HP "B" S
Date:
Feb 1, 2001

Comment: