FY 2003 Mainstem/Systemwide proposal 198907201

Additional documents

TitleType
198907201 Narrative Narrative

Section 1. Administrative

Proposal titleIndependent Scientific Advisory Board Support
Proposal ID198907201
OrganizationDepartment of Energy/Oak Ridge National Laboratory (DOE/ORNL)
Proposal contact person or principal investigator
NameCharles C. Coutant
Mailing addressORNL/ESD/ PO Box 2008/Bldg. 1505: Mail Stop 6036 Oak Ridge, TN 37831-6036
Phone / email8655766830 / coutantcc@ornl.gov
Manager authorizing this projectMike Schiewe (NMFS), Chip McConnaha (NPPC)
Review cycleMainstem/Systemwide
Province / SubbasinMainstem/Systemwide /
Short descriptionProvide support through contract with DOE for Dr. Charles Coutant for the Independent Scientific Advisory Board (ISAB), for scientific advice to the NWPPC’s FWP, NMFS's ESA program, and the Columbia River Basin Indian Tribes fish and wildlife programs.
Target speciesna
Project location
LatitudeLongitudeDescription
na
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
2002 Completion of one review to date: Review of Council briefing document, "Mainstem Passage Strategies in the Columbia River System: Transportation, Spill, and Flow Augmentation." Also working on Supplementation and Tributary Habitat reviews.
2001 Completed 7 reviews including reviews of salmon recovery strategies, the role of hatchery surplus, models (PATH, CRI, EDT, ICBEMP, COHORT), Lower Snake River flow augmentation studies, emergency spill, and 2000 FWP biological objectives.
2000 Completed 5 reviews including reviews of Council's Artificial Production Review performance standards, The Dalles spill research program, and the impact of estuary conditions on the FWP. Conducted most of Model Synthesis Review (2001).
1999 Completion of 7 reviews requested by NMFS, the Council, and Congress including review of the Corps Capital Construction Program (adult passage and scientific overview), a scientific synthesis of recovery plans, and NMFS's Anadromous Fish Appendix.
1998 Completion of 8 reviews requested by NMFS, the Council, and Congress including review of the Corps Capital Construction Program, PIT tag workplan, and the Multi-Species Framework Scientific Principles.
1997 Completion of 8 reviews requested by NMFS and the Council including reviews of downstream passage for salmon, PIT tag research, NMFS Waiver of Dissolved Gas Standard, ecological impacts of BiOp flow provisions on Hungry Horse and Libby resident fishes.
1996 Review of the Fish and Wildlife Program. The Council Report 96-6 by Independent Scientific Group: Return to the River.

Section 3. Relationships to other projects

Project IDTitleDescription
199600500 Independent Scientific Advisory Board This project is to fund Dr. Coutant's participation in the ISAB.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
1) Provide scientific review and recommendations to the Council, NMFS, and Columbia River Basin Indian Tribes as requested. 3 $100,027
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1) Provide scientific review and recommendations to the Council, NMFS, and Columbia River Basin Indian Tribes as requested. 2003 2005 $300,000
Outyear budgets for Construction and Implementation phase
FY 2004FY 2005
$100,000$100,000

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
na na na $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2003 cost
Personnel FTE: 446 hrs x $78.75 $35,122
Fringe 47.85% $16,806
Travel 11 trips @ $135/day @ 4 days per trip; $1,800 airfare/travel Oak Ridge, TN to Portland or Seattle $25,740
Indirect General and Administrative Expense; 41.63% for labor; 2.88% for travel. $22,359
$100,027
Total estimated budget
Total FY 2003 cost$100,027
Amount anticipated from previously committed BPA funds$0
Total FY 2003 budget request$100,027
FY 2003 forecast from 2002$100,000
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Not applicable - no response required
Date:
Aug 2, 2002

Comment:

Not applicable, conflict of interest.
Recommendation:
NWPPC responsibility
Date:
Oct 24, 2002

Comment:


Recommendation:
Not Reviewed
Date:
Nov 5, 2002

Comment:

Not applicable, conflict of interest.
Recommendation:
Date:
Jan 21, 2003

Comment:

Statement of Potential Biological Benefit
Indirect benefit through scientific review of all proposals submitted under the Fish and Wildlife Program

Comments
The ISRP function is legislatively mandated.

Already ESA Required?
No

Biop?
No


Recommendation:
Do Not Fund (Tier 3)
Date:
Jun 11, 2003

Comment:

Category:
3. Other projects not recommended by staff

Comments:
Placeholder


Recommendation:
Date:
Sep 20, 2003

Comment: