FY 2003 Mainstem/Systemwide proposal 200100300
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
200100300 Narrative | Narrative |
200100300 Powerpoint Presentation | Powerpoint Presentation |
200100300 Sponsor Response to the ISRP | Response |
Section 1. Administrative
Proposal title | ISO Adult Pit Interrogation System Installations |
Proposal ID | 200100300 |
Organization | Pacific States Marine Fisheries Commission (PSMFC) |
Proposal contact person or principal investigator | |
Name | Carter Stein |
Mailing address | 45 SE 82nd Ave. Gladstone, OR 97027-2522 |
Phone / email | 5036505400 / carters@psmfc.org |
Manager authorizing this project | Randy Fisher |
Review cycle | Mainstem/Systemwide |
Province / Subbasin | Mainstem/Systemwide / |
Short description | Provides for procurement of PIT tag interrogation system electronic components and labor for assembly and installation in adult fish ladders at Ice Harbor, Lower Granite and the Dalles in FY02/03 and at John Day, Lower Monumental and Little Goose in FY03. |
Target species | Anadromous Salmonids, Lamprey, others. |
Project location
Latitude | Longitude | Description |
---|---|---|
46.2501 | -118.8783 | Ice Harbor Dam |
46.5614 | -118.5351 | Lower Monumental Dam |
46.5852 | -118.0272 | Little Goose Dam |
46.659 | -117.4304 | Lower Granite Dam |
45.9365 | -119.2966 | McNary Dam |
45.7155 | -120.6915 | John Day Dam |
45.6134 | -121.1329 | The Dalles Dam |
45.6446 | -121.9407 | Bonneville Dam |
46.644 | -119.9099 | Priest Rapids Dam |
Chandler Dam |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
166 |
50,192,109,118,119 |
45,46,47,189 |
82,83,71,104,134, |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS/BPA | Action 50 | NMFS | BPA and the Corps shall install necessary adult PIT-tag detectors at appropriate FCRPS projects before the expected return of adult salmon from the 2001 juvenile outmigration. |
NMFS/BPA | Action 189 | NMFS | The Action Agencies and NMFS shall work within the annual planning and congressional appropriation processes to establish and provide the appropriate level of FCRPS funding for studies to investigate the causes of discrepancies in adult return rates for juvenile salmonids that have different passage histories through the hydrosystem. |
NMFS | Action 192 | NMFS | As set out in Action 50 (Section 9.6.1.3.4), BPA and the Corps shall install necessary adult PIT-tag detectors at appropriate FCRPS projects before the expected return of adult salmon from the 2001 juvenile outmigration. These adult PIT-tag detectors shall be used as needed for calculating transport benefits, conversion rates, and SARs for listed salmon and steelhead. |
NMFS/BPA | Action 192 | NMFS | As set out in Action 50 (Section 9.6.1.3.4), BPA and the Corps shall install necessary adult PIT-tag detectors at appropriate FCRPS projects before the expected return of adult salmon from the 2001 juvenile outmigration. These adult PIT-tag detectors shall be used as needed for calculating transport benefits, conversion rates, and SARs for listed salmon and steelhead. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
2001 | Installed orifice PIT tag detection systems at Bonneville Dam Cascade Island Fish ladder |
2001 | Installed orifice PIT tag detection systems at Bonneville Dam Bradford Island Fish ladder |
2001 | Installed orifice PIT tag detection systems at McNary Dam Oregon Shore Fish Ladder |
2001 | Installed orifice PIT tag detection systems at McNary Dam Washington Shore Fish Ladder |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
198331900 | New Markinand Monitoring Techniques for Fish | Developed prototype ladder orifice detection system installed at Bonneville Washington Shore Ladder in 2000/2001 |
198335000 | Nez Perce Tribal Hatchery | PIT Tagging project 13,500 tags. |
198335003 | Nez Perce Tribal Hatchery Monitoring And Evaluation | PIT Tagging project 18,200 tags. |
198605000 | White Sturgeon Mitigation And Restoration In The Columbia And Snake Rivers | PIT Tagging project. 4,300 tags. |
198712700 | Smolt Monitoring by Federal and Non-Federal Agencies | PIT Tagging project. 54,100 tags. |
198712703 | Imnaha River Smolt Monitoring Program Project | PIT Tagging project 4,600 tags |
198712702 | Comparative Survival Rate Study (CSS) of Hatchery Pit Tagged Chinook | PIT Tagging project 221,500 tags. |
198806400 | Kootenai River White Sturgeon Studies and Conservation Aquaculture | PIT Tagging project |
198902401 | Evaluate Juvenile Salmonid Outmigration and Survival in the Lower Umatilla River Basin | PIT Tagging Project 8,600 tags. PIT interrogation data collection project. |
198909800 | Idaho Supplementation Studies | PIT Tagging Project. 24,000 tags. |
198909801 | Evaluate Supplementation Studies in Idaho Rivers (ISS) | PIT Tagging Project. 3,000 tags |
198909802 | Evaluate Salmon Supplementation Studies in Idaho Rivers- Nez Perce Tribe | PIT Tagging Project 12,000 tags |
198909803 | Salmon Supplementation Studies in Idaho- Shoshone-Bannock Tribes | PIT Tagging Project 2,500 tags |
199000500 | Umatilla Fish Hatchery Monitoring and Evaluation | PIT Tagging Project 8,600 tags |
199000501 | Umatilla Basin Natural Production Monitoring and Evaluation Project | PIT Tagging Project 6,000 tags |
199005200 | Performance/Stock Productivity Impacts of Hatchery Supplementation. | PIT Tagging Project 2,000 tags |
199005500 | Steelhead Supplementation Studies in Idaho Rivers | PIT Tagging Project 28,000 tags |
199102800 | Monitoring smolt migrations of wild Snake River sp/sum chinook salmon | PIT Tagging Project 16,000 tags |
199102900 | Understanding the effects of summer flow augmentation on the migratory behavior and survival of fall chinook salmon migrating through L. Granite Res. | PIT Tagging Project 13,500 tags |
199105500 | NATURES [Formerly Supplementation Fish Quality (Yakima)] | PIT Tagging Project 6,000 tags |
199107100 | Snake River Sockeye Salmon Habitat and Limnological Research | Utilizes PIT tag data for research |
199107200 | Redfish Lake Sockeye Salmon Captive Broodstock Program | PIT Tagging Project 6,000 tags |
199107300 | Idaho Natural Production Monitoring and Evaluation | PIT Tagging Project 12,500 tags |
199202604 | Investigate Life History of Spring Chinook Salmon and Summer Steelhead in the Grande Ronde River Basin and Monitor Salmonid Populations and Habitat | PIT Tagging Project 18,900 tags |
199302900 | Survival Estimates for the Passage of Juvenile Salmonids Through Snake and Columbia River Dams and Reservoirs | PIT Tagging Project 100,000 tags |
199305600 | Assessment of Captive Broodstock Technology | PIT Tagging Project 4,000 tags |
199403400 | Assessing Summer And Fall Chinook Restoration In The Snake River Basin | PIT Tagging Project 28,000 tags |
199506300 | Yakima/Klickitat Monitoring and Evaluation Program | PIT Tagging Project 37,092 tags |
199602000 | Comparative Survival Rate Study (CSS) of Hatchery Pit Tagged Chinook & Comparative Survival Study Oversight Committee | PIT Tagging Project 220,000 tags |
199603201 | Begin Implementation of Year 1 of the K Pool Master Plan Program | PIT Tagging Project 500 tags |
199604000 | Evaluate The Feasibility And Risks Of Coho Reintroduction In Mid-Columbia | PIT Tagging Project 40,000 tags |
199604300 | Johnson Creek Artificial Propagation Enhancement Project | PIT Tagging Project 24,500 tags |
199700100 | Captive Rearing Project for Salmon River Chinook Salmon | PIT Tagging Project 1,000 tags |
199701501 | Imnaha Smolt Survival and Smolt to Adult Return Rate Quantification | PIT Tagging Project 11,300 tags |
199701901 | Evaluation of the Life History of Native Salmonids in the Malheur Basin (2) | PIT Tag recaputure project |
199800702 | Grande Ronde Supplementation: Lostine River O&M and M&E | PIT Tagging Project 8,000 tags |
199800703 | Facility O&M And Program M&E For Grande Ronde Spring Chinook Salmon and Summer Steelhead | PIT Tag data analysis project |
199801001 | Grande Ronde Basin Spring Chinook Captive Broodstock Program | PIT Tagging Project 1,600 tags |
199801002 | Captive Rearing Initiative for Salmon River Chinook Salmon - M & E | PIT Tagging coordination with other NWPPC FWP projects |
199801004 | Monitor and EvaluateYearling Snake River Fall Chinook Released Upstream Of Lower Granite Dam | PIT Tagging Project 27,500 tags |
199801006 | Captive Broodstock Artificial Propagation | PIT Tagging Project 8,000 tags |
199801600 | Monitor Natural Escapement & Productivity of John Day Basin Spring Chinook | PIT Tagging Project 8,000 tags |
199801900 | Wind River Watershed Restoration | PIT Tagging Project 1,000 tags |
199901800 | Characterize and quantify residual steelhead in the Clearwater River, Idaho | PIT Tagging Project 6,000 tags |
199902400 | Bull trout population assessment in the Columbia River Gorge, WA. | PIT Tag data analysis project |
200001700 | Recondition Wild Steelhead Kelts | PIT Tagging Project 600 tags |
199105100 | Run Timing Predictions for the Columbia River Basin Including Individual ESA Demes and Analysis of Tagging Data | Utilizes PIT Tag Data for Basic Research |
198910800 | CRISP Modelling | Utilizes PIT Tag Data for basic research |
195500100 | Analysis of Smolt Migration Rate & Survival Based on Pit-Tag Recoveries | Utilizes PIT Tag Data for basic research |
199008001 | PIT Tag Purchase and Distribution | This is the placeholder account for the purchase and distribution of PIT tags. Contact John Rowan @ BPA. |
199007700 | Northern Pikeminnow Management Program | Recaputure of PIT tags from smolt ingested by Norther Pike Minnow. Require PTAGIS training, software and data management services. |
999999999 | USACE task 4 tpe-w-00-1 | MCN Transportation Study w/ Leavenworth Fish |
999999999 | USACE ADS-02-06 | Kelt Study at LGR |
999999999 | USACE TPE-W-001 | McNary Mid-Columbia Transport Study Leavenworth Fish |
999999999 | USACE no-code-provided by usace | NMFS Hammond Columbia River Estuary Tagging |
999999999 | USACE no-code-provided by usace | USFWS tagging at Winthrop and Entiat for NMFS transportation Study at McNary Dam |
999999999 | USACE BPS-00-9, 10 | USFWS CSS supplementation for Congletons' physiological work from Dworshak Hatchery |
999999999 | USACE BPS-00-9,10 | NMFS Delayed mortality study at Bonneville tagged at Rapid River and McCall, ID by IDFG. |
999999999 | USACE no-code-provided | NMFS Full Flow Bypass Tests at McNary Dam |
999999999 | Others | Other projects that depend upon the adult PIT tag data that fall outside the scope of the NWPPC FWP. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Develop construction documentation and project plans for Adult Counting Window Installations at The Dalles, Ice Harbor and Lower Granite | a. Site reconnaissance | 1 | $18,354 | Yes |
b. Determine overall requirements and test antenna configurations based upon McNary Counting window prototype | 1 | $25,530 | Yes | |
c. Create Electrical / Mechanical Antenna Drawings | 1 | $6,900 | Yes | |
d. Design Production Cable Assembly | 1 | $42,320 | Yes | |
e. Design Reviews | 1 | $25,438 | Yes | |
2. Preliminary planning for Installation of Counting Window PIT Tag detectors in fish ladders at John Day, Little Goose and Lower Monumental | a. Site reconnaissance 3 sites | 1 | $18,354 | Yes |
b Generate Site Specific PIT Tag System Requirements 3 sites | 1 | $11,500 | Yes | |
c. Generate Site Specific Antenna Requirements 3 sites | 1 | $26,974 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
This form will not allow Out Year Objective Based Budget estimates for the Construction implementation phase, so future installations are listed here: | $0 | ||
1. Install Adult PIT Tag Counting Window systems at John Day, Lower Monumental and Little Goose Dam | 2004 | 2005 | $1,500,000 |
2. Install Adult PIT Tag Counting Window system at Bonneville Dam | 2005 | 2006 | $500,000 |
3. Assist BPA and COE to plan future installations for adult salmonids | 2004 | 2007 | $99,600 |
4. Evaluate performance of installed interrogations systems for adult salmonids | 2004 | 2007 | $361,100 |
5. Project reporting | 2004 | 2007 | $96,700 |
Outyear budgets for Planning and Design phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$1,660,200 | $665,000 | $169,900 | $62,300 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Acquire necessary electronic components and install counting window PIT Tag detection systems at Ice Harbor | a. Site reconnaissance | i | $2,829 | Yes |
b. EMI Testing | 1 | $2,248 | Yes | |
c. Generate Site Specific PIT Tag System Requirements | 1 | $11,500 | Yes | |
d. Generate Site Specific Antenna Requirements | 1 | $26,973 | Yes | |
e. Manufacture and deliver antennas | 1 | $115,000 | Yes | |
f. Manufacture and deliver readers | 1 | $62,100 | Yes | |
g. Installation Integeration and Management | 1 | $69,863 | Yes | |
h. Develop and construct multi-plexing scheme (High Speed Interface or USB alternatives) | 1 | $8,970 | Yes | |
i. Install PIT Tag Data Collection Platforms | 1 | $17,940 | Yes | |
j. Configure Systems at Site | 1 | $3,220 | Yes | |
k. Configure new systems in PTAGIS | 1 | $2,875 | Yes | |
l. Test Systems | 1 | $3,220 | Yes | |
m. Final Walkthrough | 1 | $5,032 | Yes | |
n. Project Management | 1 | $41,860 | Yes | |
2. Acquire necessary electronic components and install counting window PIT Tag detection systems at Lower Granite | a. Site reconnaissance | 1 | $2,829 | Yes |
b. EMI Testing | 1 | $2,249 | Yes | |
c. Generate Site Specific PIT Tag System Requirements | 1 | $11,500 | Yes | |
d. Generate Site Specific Antenna Requirements | 1 | $26,974 | Yes | |
e. Manufacture and deliver antennas | 1 | $57,500 | Yes | |
f. Manufacture and deliver readers | 1 | $34,500 | Yes | |
g. Installation Integeration and Management | 1 | $60,203 | Yes | |
h. Develop and construct multi-plexing scheme (High Speed Interface or USB alternatives) | 1 | $4,370 | Yes | |
i. Install PIT Tag Data Collection Platforms | 1 | $8,740 | Yes | |
j. Configure Systems at Site | 1 | $3,220 | Yes | |
k. Configure new systems in PTAGIS | 1 | $2,875 | Yes | |
l. Test Systems | 1 | $6,412 | Yes | |
m. Final Walkthrough | 1 | $9,057 | Yes | |
n. Project Management | 1 | $41,860 | Yes | |
3. Acquire necessary electronic components and install counting window PIT Tag detection systems at The Dalles | a. Site reconnaissance | 1 | $2,829 | Yes |
b. EMI Testing | 1 | $2,249 | Yes | |
c Generate Site Specific PIT Tag System Requirements | 1 | $11,500 | Yes | |
d. Generate Site Specific Antenna Requirements | 1 | $26,974 | Yes | |
e. Manufacture and deliver antennas | 1 | $115,000 | Yes | |
f. Manufacture and deliver readers | 1 | $62,100 | Yes | |
g. Installation Integeration and Management | 1 | $69,863 | Yes | |
h. Develop and construct multi-plexing scheme (High Speed Interface or USB alternatives) | 1 | $8,970 | Yes | |
i. Install PIT Tag Data Collection Platforms | 1 | $17,940 | Yes | |
j. Configure Systems at Site | 1 | $3,220 | Yes | |
k. Configure new systems in PTAGIS | 1 | $2,875 | Yes | |
l. Test Systems | 1 | $6,412 | Yes | |
m. Final Walkthrough | 1 | $9,057 | Yes | |
n. Project Management | 1 | $41,860 | Yes | |
4. Assist BPA and COE in developing design and constructional documents for future installs of interrogation systems to detect migrating adult salmonids in fish ladders. | a. Visit dams, attend meetings and conference calls, review drawings, provide technical assistance to solving problems that arise unexpectedly because of uniqueness of a dam site | 3 | $31,100 | Yes |
5. Evaluate the performance of the installed interrogations systems for migrating adult salmonids in fish ladders | a. Use the direct method of tagging fish from multiple species at Washington Shore Ladder to get known number of fish for comparison to statistical models and information on fish behavior, annual flucuations, etc | 3 | $85,500 | Yes |
b. Analyze data from the installed ladders to determine the the accuracy of the data collected including a comparison between the counting-station interrogation system and orifice-based system migration. | 3 | $16,500 | Yes | |
6. Project planning, administration, and reporting | a. Perform administrative tasks (write management plans, budgets, workplans, contracts, summary reports, and annual reports | 3 | $22,500 | Yes |
7. Upgrade McNary Oregon Shore Counting Window from Prototype to Production | a. Move transceiver enclosure from the counting window closet. | 1 | $4,284 | Yes |
b. Provide clean power to the transceivers. | 1 | $7,284 | Yes | |
c. Test and tune. | 1 | $2,800 | Yes | |
8. Cost Share with Grant Co. PUD to install Adult PIT system at Priest Rapids Fish Ladders | Provide financial assistance. | 1 | $300,000 | Yes |
9. Cost Share with Bureau of Reclaimation and Yakama Indian Nation to install adult PIT tag detection system at the Chandler dam / irrigation diversion near Prosser, WA on the Yakima River. | Provide financial assistance | 1 | $300,000 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
7. Project Administration and Management | 2004 | 2007 | $389,416 |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2003 cost |
---|---|---|
Supplies | $443,508 | |
Travel | $152,855 | |
Indirect | $158,674 | |
PIT tags | $0 | |
Subcontractor | $617,069 | |
Other | Grant County PUD Cost Share Priest Rapids Adult PIT Installation and BOR / YIN Cost share @ Chandler | $600,000 |
$1,972,106 |
Total estimated budget
Total FY 2003 cost | $1,972,106 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2003 budget request | $1,972,106 |
FY 2003 forecast from 2002 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Grant Count PUD | Installation of Adult PIT Tag System at Priest Rapids Dam | $750,000 | in-kind |
BOR & YIN | Installation of Adult PIT Tag System at Chandler irrigation diversion at Prosser, WA on the Yakima River. | $750,000 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Aug 2, 2002
Comment:
Generally fundable -- the proposal deserves high priority -- but a response is needed. The proposal includes a Monitoring and Evaluation component. However, more detail should be given on study design and determination of sample size. The power to detect important "failures", etc. should also be given. Are there quality control standards in place for performance of such devices?Comment:
An evaluation should be done to determine the extent of cost share by GPUD and the USBOR for operating the monitoring systems. It is not appropriate for the F&W Program to pay the full price of the monitoring system that is applied at non-BPA dams. This project meets RPA 194 of the NMFS BiOp. This project was spun off of Project Number 198331900 in 2001 to separate Adult monitoring technology.Comment:
The costs for the "ISO Adult PIT Interrogation System Installations" are based upon the implementation schedule discussed in regional planning forums. Costs could be deferred by making a decision to delay deployment of Adult PIT tag installations on a site by site basis. Some funds have been identified as cost share. I do not recommend removing this cost from that of the overall project. The reason for this is that the Corps of Engineers plans for installation are different from the installation assumptions made in the proposal. For example, at Ice Harbor, the proposal assumed four PIT tag detectors located at the counting windows of the Ice Harbor fish ladders. The Corps decided not to pursue the counting window approach due to technical difficulties, and have instead opted to install detectors in the weirs. This approach doubles the amount of electronics required and makes the antenna cost increase by a substantial amount.Comment:
Fundable. Agree with CBFWA's Core Program ranking. The ISRP preliminary comments asked for more detail on quality control, study design and determination of the sample size and power. The response addressed these issues satisfactorily. If funded, this project should be coordinated with other monitoring projects to ensure compatibility of objectives, common methods and protocols. This coordination could be accomplished under the favorably reviewed CBFWA proposal #35033.Comment:
Statement of Potential Biological BenefitBenefits are indirect. Adult PIT tag interrogation system will allow assessment of adult performance standards and will allow assessment of critical adult passage issues such as interdam loss, delay and fallback.
Comments
This is an important step in determining biological performance standards for adult migrants and for reducing handling of adults by reducing the need for massive radio tag studies. Also implements ITS 10.5.1.6.
Already ESA Required?
No
Biop?
Yes
Comment:
Category:Capital Projects recommended by staff
Comments:
Capital project not counted toward expense budget
Comment:
Comment:
Scope of project and budget have been reduced based on regional discussion on priority of new adult PIT Tag facilities at Bonneville and John Day Dams. NPCC recommended capitalizing all costs associated with this project. This project does not meet criteria for capitalization; project does not provide a future benefit to BPA that would last for 15 years or more.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$600,000 | $200,000 | $200,000 |
Sponsor comments: See comment at Council's website