FY 2003 Upper Snake proposal 200302500

Section 1. Administrative

Proposal titleImprove Yellowstone cutthroat trout recruitment and survival in the South Fork of the Snake River
Proposal ID200302500
OrganizationIdaho Department of Fish and Game (IDFG)
Proposal contact person or principal investigator
NameJim Fredericks
Mailing address1515 Lincoln Road Idaho Falls, ID 83401
Phone / email2085257290 / jfrederi@idfg.state.id.us
Manager authorizing this projectBob Saban, Regional Supervisor, IDFG
Review cycleUpper Snake
Province / SubbasinUpper Snake / Headwaters
Short descriptionIncrease juvenile cutthroat trout recruitment and survival in the South Fork of the Snake River by minimizing entrainment losses and side channel stranding mortality, and by restoring tributary habitat.
Target speciesYellowstone cutthroat trout
Project location
LatitudeLongitudeDescription
43.7525 -111.9397 confluence of South Fork and Henry's Fork of the Snake River (downstream project boundary)
43.3297 -111.201 Palisades Dam (upsteam project boundary)
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
9.1.1
9.1.3
(NMFS BiOp of May 2001)

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1982 annual population estimates were begun in representative reaches of the South Fork
1992 South Fork winter flow study completed to identify
1998 rainbow trout harvest encouraged through use of liberalized regulations (6 fish daily limit)
1992 screening facility installed in Palisades Creek irrigation diversion
1999 fish trap and weir installed in Palisades Creek
2000 fish trap and weir installed in Rainey Creek
1999 diversion screen installed in Rainey Creek diversion
2000 diversion screen and fish trap and weir installed in Burns Creek
2002 fish trap and weir installed in Pine Creek
1998 rainbow x cutthroat hybridization in mainstem study completed

Section 3. Relationships to other projects

Project IDTitleDescription
98002 Snake River Native Salmonid Assessment Inventory/evaluation of current distribution of native salmonids

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
1. Reduce juvenile entrainment in tributary diversions 1a—Inventory existing diversions 1 $15,000
2. Increase tributary spawning and rearing habitat 2a--Compile existing habitat data 1 $2,000
2b--Conduct field surveys 1 $25,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
1. Reduce juvenile entrainment in tributary diversions 1b—design and implement screens on tributary diversions 3 $0
2. Increase tributary spawning and rearing habitat 2c--improve habitat with riparian fences, bank barbs 3 $0 Yes
2d--restore connectivity to tributary spawning habitat 3 $0
3. Evaluate flow/survival relationship of rainbow and cutthroat trout. 3a--compile historical data of flows and refine estimates of year-class strength abundance 3 $25,000
3b--use radiotelemetry to identify juvenile winter habitat use and movement 3 $65,000
4. Assess juvenile fish losses in Great Feeder and other lower river irrigation diversions 4a--Estimate entrainment in Great Feeder 2 $40,000
4c--Identify seasonal movements and spawning areas of adult fish in lower river 3 $52,700
4d--estimate fish losses in lower river diversions 3 $40,000
4e--model impacts of diversion entrianment 1 $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Reduce juvenile entrainment in tributary diversions 2004 2006 $750,000
2. Increase tributary spawning and rearing habitat 2005 2007 $600,000
3. Evaluate flow/survival relationship of rainbow and cutthroat trout. 2004 2005 $120,000
4. Assess juvenile fish losses in Great Feeder and lower river irrigation diversions 2004 2005 $220,000
Outyear budgets for Construction and Implementation phase
FY 2004FY 2005FY 2006FY 2007
$590,000$570,000$450,000$200,000

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
1. Reduce juvenile entrainment in tributary diversions 1b—maintain screens on tributary diversions ongoing $0 Yes
2. Increase tributary spawning and rearing habitat 2c--maintain riparian fences ongoing $0 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Reduce juvenile entrainment in tributary diversions 2004 2007 $40,000
2. Increase tributary spawning and rearing habitat 2006 2007 $20,000
Outyear budgets for Operations and Maintenance phase
FY 2004FY 2005FY 2006FY 2007
$10,000$10,000$20,000$20,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2003 costSubcontractor
1. Reduce juvenile entrainment in tributary diversions 1c--monitor effectiveness of diversion screen 3 $0
2. Increase tributary spawning and rearing habitat 2e--monitor fishery response to increase in tributary spawning habitat 3 $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Reduce juvenile entrainment in tributary diversions 2005 2007 $60,000
2. Increase tributary spawning and rearing habitat 2005 2007 $60,000
Outyear budgets for Monitoring and Evaluation phase
FY 2005FY 2006FY 2007
$40,000$40,000$40,000

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2003 cost
Personnel FTE: 3 - 1 full time biologist (2080 hrs @ 18.59/hr) 24 mo.of tech time (@11.53/hr) $86,700
Fringe 35% $30,300
Supplies radio tags, reciever, field gear, computer, office furniture $30,000
Travel per diem, attendance at meetings/conferences $4,000
Indirect IDFG overhead at @ 21% $40,700
Capital jet boat suited for winter/foul weather telemetry $30,000
Subcontractor air service for telemetry $15,000
Other Equipment rental, mileage, boat gas $28,000
$264,700
Total estimated budget
Total FY 2003 cost$264,700
Amount anticipated from previously committed BPA funds$0
Total FY 2003 budget request$264,700
FY 2003 forecast from 2002$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
U.S. Forest Service Stream habitat surveys $25,000 cash
Trout Unlimited stream restoration and diversion screening $25,000 cash

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable only if response is adequate
Date:
Mar 1, 2002

Comment:

Excellent presentation. A response is needed that better describes the proposed screening inventory activities, prioritization protocol, etc. Objective 3 (examining juvenile flow survival relationships) seems to be a reasonable approach to try, but reviewers were somewhat skeptical of whether it would meet the project's goal. Should the project focus on tributaries as cutthroat spawning refuges?

All would agree that the Great Feeder (Objective 4) is a major problem, but to what extent would the hard data that would result from this objective provide better justification regarding what actions are warranted? The approach to solving that problem (a tracking study) seems a very oblique way of initiating change. The proposal should lay out in some detail possible management options for reducing impacts of the Feeder.

It would be helpful if the project sponsors could clarify an apparent contradiction between a statement from IDFG from email and a meeting last year: "To date we have not found a significant relationship between winter flows and following year juvenile densities or total trout densities. ...over a wide range of flows during the past 15 years, the South Fork fishery has maintained a remarkable degree of stability and angling quality." This statement does not mesh with statements in the proposal about the likely effects of winter flow levels.

Some effort should also be directed at getting local landowners to use cutthroat or sterile rainbow when stocking rainbows in their private waters. IDFG could (and probably should) play an active role in this area, as continued stocking of non-native rainbows in adjacent and occasionally connected waters will continue to exacerbate the hybridization issue in the South Fork Snake. Project sponsors should address these concerns in their response.


Recommendation:
High Priority
Date:
May 17, 2002

Comment:


Recommendation:
Fund
Date:
Jun 7, 2002

Comment:

Fundable. The response addresses the ISRP concerns in a thoughtful and thorough manner. The project presentation was also excellent. In the presentation and response, the project sponsor's demonstrated considerable background knowledge of the issues about which the ISRP requested additional information, including prioritization, protocols, and questions about the Great Feeder. Also, an apparent contradiction between statements about flow levels and overwinter mortality in Lower and Upper River sections was clarified and resolved.
Recommendation:
C
Date:
Jul 23, 2002

Comment:

Do not recommend. Consistent with the Council's 1995 FWL Program, BPA recommends development of "assessments of resident fish losses and gains related to construction and operation of each hydropower facility throughout the Columbia River Basin...". Section 10.1C.1. BPA stands ready to fund completion of appropriate assessments as part of subbasin planning. Section 10.1C.3.
Recommendation:
Fund
Date:
Oct 30, 2002

Comment:

Project Issue 3: New projects that were prioritized by the Upper Snake Province group

The province group reached a consensus that the following new projects were of the highest management priority after funding the ongoing projects discussed above. There are two projects recommended:

(a) IDFG # 33009 (Improve Yellowstone cutthroat trout recruitment and survival in S. Fork Snake R.) ($155,600 in Fiscal Year 2003, $226,550 in Fiscal Year 2004 and $230,900 in Fiscal Year 2005)

The ISRP rated this proposal as "Fundable" and CBWA as "High Priority". The ISRP comments found the proposal to be "thoughtful and thorough". Bonneville rated the project as a "C" stating that the 1995 program called for resident fish loss assessments on a project- by-project basis be established, and that this could be done with currently available money that was provided for subbasin planning.

Council Recommendation: The sponsor reports that the project is linked to the Palisades project, for which Bonneville has acknowledged at least partial responsibility. The Council believes that the project should be funded at this time, and does not believe that the subbasin planning budget that was agreed to by the Council and Bonneville contemplated funding a thorough loss assessment for each hydropower facility throughout the Columbia basin as called for in measure 10.1C.1. of the 1995 program.


Recommendation:
Fund when Funds available. Not critical.
Date:
Apr 30, 2003

Comment:

Phase 3 will be initiated upon resolution of identified issues. BPA will reengage with the Council regarding applicability of this project to the FCRPS mitigation responsibility for Palisades project prior to issuing a final decision.
Recommendation:
Fund
Date:
Sep 20, 2003

Comment:

Phase III. Opportunity to implement full project in 2004 is available (catch up). Reduced first year budget was a result of budget cutting exercise. Option to just realign - project still valid.
Recommendation:
Date:
Sep 20, 2003

Comment: