FY 1999 proposal 9024

Additional documents

TitleType
9024 Narrative Narrative

Section 1. Administrative

Proposal titleMethow Tributaries Fish Passage
Proposal ID9024
OrganizationUSDA Forest Service, Okanogan National Forest, Methow Valley Ranger District (USFS)
Proposal contact person or principal investigator
NameJennifer Molesworth
Mailing addressP.O. Box 97 Winthrop, WA 98862
Phone / email5099964010 / usinfo@methow.com
Manager authorizing this project
Review cycleFY 1999
Province / SubbasinUpper Mid-Columbia / Methow
Short descriptionEvaluate barriers to fish passage (mainly culverts) in main tributaries tothe Methow River, and prioritize some barriers for removal.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
not applicable

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 1999 cost
Personnel $4,442
Supplies snorkeling gear, flow meter, measure tapes, and miscellaneous $800
Travel 15 days of 4-wheel drive truck time $458
Subcontractor none $0
$5,700
Total estimated budget
Total FY 1999 cost$5,700
Amount anticipated from previously committed BPA funds$0
Total FY 1999 budget request$5,700
FY 1999 forecast from 1998$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Other budget explanation

Schedule Constraints: Deep snows and high stream flows could slow inventory start, move project completion back. Project would still be completed in 1999.


Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Pass (Fundable)
Date:
May 13, 1998

Comment:

Management Issue: Management concern that the USFS should have included this work as part of the original assessment (in-lieu issue).
Recommendation:
Fund (low priority)
Date:
May 13, 1998

Comment:

In-lieu funding issue. Proposed tasks appear to be "in lieu of other expenditures authorized or required from other entities under other agreements or provisions of law". (Section 4.(h)(10)(A) of PNW Power Act).
Recommendation:
Adequate
Date:
Jun 18, 1998

Comment:

The proposal was not related to the Fish and Wildlife Program. It was a good idea to determine where road crossings are a barrier to bull trout. The ISRP questioned whether BPA should fund this project or the USFS.