Section 1. Administrative
Proposal title | Replace Chumstick Creek Culvert |
Proposal ID | 9044 |
Organization | Washington Department of Fish and Wildlife (WDFW) |
Proposal contact person or principal investigator |
Name | Bob Steele, Area Habitat Manager |
Mailing address | 3860 Chelan Hwy. North Wenatchee, WA 98801 |
Phone / email | 5096620503 / |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Upper Mid-Columbia / Wenatchee |
Short description | Replace Chumstick Creek culvert to allow salmonid passage. |
Target species | Spring Chinook salmon, Summer steelhead, bull trout, and coho (with possible reintroduction of coho into Wenatchee Subbasin in the near future |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Supplies |
|
$19,250 |
Subcontractor |
|
$152,130 |
| $171,380 |
Total estimated budget
Total FY 1999 cost | $171,380 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $171,380 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: Phase 1 will be complete in Sept/99. Phase 2, the implementation of restoration of nested watersheds, will be complete by Jun/02.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Return to Sponsor for Revision
Date:
May 13, 1998
Comment:
Technical Issue: Clearly describe the expected benefits (e.g., returns of fish.)Technical Issue: Proposal 9050 states that there are 23 more barriers – explain how removing this one culvert will open up a significant amount of habitat.
Management Issue: Consider combining this project with 9050.
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
The proposal adequately details methods and objectives for this type of project and describes some benefits to fish and wildlife, but it does not provide sufficient details on the populations that would be affected by opening access to additional reaches of Chumstick Creek. The ISRP questioned whether BPA was the appropriate funding agency for this project.