FY 1999 proposal 9125

Additional documents

TitleType
9125 Narrative Narrative

Section 1. Administrative

Proposal titleColumbia River Basin Fish Key
Proposal ID9125
OrganizationEastern Washington University Biology Department
Proposal contact person or principal investigator
NameAllan T. Scholz, Ph.D.
Mailing addressEWU Biology Department, MS#72 Cheney, WA 99004
Phone / email5093596397 /
Manager authorizing this project
Review cycleFY 1999
Province / SubbasinSystemwide / Systemwide
Short descriptionWrite book about taxonomy and life histories of fishes inhabiting the Columbia River System
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 1999 cost
Personnel $55,350
Fringe $14,368
Supplies $18,232
Travel $12,982
Indirect $14,945
Subcontractor $14,500
$130,377
Total estimated budget
Total FY 1999 cost$130,377
Amount anticipated from previously committed BPA funds$0
Total FY 1999 budget request$130,377
FY 1999 forecast from 1998$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Date:
May 13, 1998

Comment:

Criteria 1: Technical Criteria - Yes

Criteria 2: Objectives Criteria - Yes

Criteria 3: Milestones Criteria - Yes

Criteria 4: Resources Criteria - Yes:


Recommendation:
Do Not Fund
Date:
May 13, 1998

Comment:

urgent. Proposed activities would not produce significant near-term survival improvement nor risk a lost opportunity within the next 1-3 years.

Duplicates ongoing work. Some or all of proposed activities are similar or identical to work already funded. Better knowledge or coordination of past or ongoing projects would have reduced or eliminated project need.


Recommendation:
Inadequate
Date:
Jun 18, 1998

Comment:

The proposal title "key" does not match the proposed objectives: to write a comprehensive book on fishes of the basin. The full proposal was too long for the Fish and Wildlife Program format, and was not included. The need is not justified (the work may be needed, but this is not demonstrated in the abbreviated proposal). No attempt was made to coordinate with other projects except to get information from them. The proposal does not provide context of what is already known about fishes in the system. The proposal ranked near the bottom of the set.