FY 1999 proposal 9138
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
9138 Narrative | Narrative |
Section 1. Administrative
Proposal title | Warm Springs Reservation 1999 Watershed Enhancement Project |
Proposal ID | 9138 |
Organization | Confederated Tribes of the Warm Springs Reservation of Oregon (CTWSRO) |
Proposal contact person or principal investigator | |
Name | Patty O’Toole |
Mailing address | P.O. Box C Warm Springs, OR 97761 |
Phone / email | 5415533233 / potoole@warmsprings.com |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Lower Mid-Columbia / Deschutes |
Short description | Protect and enhance key habitat for anadromous and resident fish using passive techniques and continue collecting information on habitat quality and stock status in tributaries to the Deschutes River. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
---|---|---|
Personnel | $51,100 | |
Fringe | $11,753 | |
Supplies | $95,000 | |
Travel | $2,500 | |
Indirect | $74,666 | |
Subcontractor | Salmon Corps | $121,100 |
$356,119 |
Total estimated budget
Total FY 1999 cost | $356,119 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $356,119 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Technical Issue: Explain how objective 2 –turning over soil to a grade of 24" - is the most appropriate technique. Objectives 2 and 3 appear contradictory because objective 2 proposes using non-native grasses.Comment:
Comment:
This proposal is well written and includes a clear statement of tasks and products. The project has been funded since 1980, but the project history did not give adequate description of past results. The objectives are not stated in a way that provides specific, measurable criteria for success. The budget for supplies needs more explanation and justification. It appears high.