FY 2000 proposal 20515

Additional documents

TitleType
20515 Narrative Narrative

Section 1. Administrative

Proposal titleMainstem Columbia River Umbrella Proposal
Proposal ID20515
OrganizationOregon Department of Fish and Wildlife (ODFW)
Proposal contact person or principal investigator
NameTony Nigro / Susan Barnes
Mailing addressP.O. Box 59 Portland, OR 97207
Phone / email5038725310 / tony.nigro@state.or.us
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinMainstem/Systemwide / Systemwide
Short descriptionThis proposal explains the management intent for anadromous and resident fish, and for wildlife in and along the mainstem Columbia and Snake rivers. Objectives for key species are described, as are strategies and actions to meet those objectives.
Target speciesAll species of anadromous and resident salmonids; white sturgeon and other resident species; native wildlife species, including habitat indicator species.
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1992 Determined status of sturgeon populations downstream from McNary Dam; recommended development of mitigation actions.
1993 Identified potential wildlife mitigation opportunities by priority (OTAP Project).
1997 Created series of databases and GIS layers to assist in the evaluation of potential wildlife mitigation projects (GAP Analysis Project).
1997 Implemented actions to mitigate and restore white sturgeon populations.
1997 Reduced predation on juvenile salmonids through sustained harvest of northern pikeminnow.
1998 Established StreamNet as a data management tool used by a number of fish management agencies.
1998 Through PATH, completed assessments of the likelihood of recovery for Snake River chinook salmon under various hydrosystem operations.
1998 Maintained and continued to improve the CWT database.
1998 Demonstrated the potential for establishing fisheries in select areas.
1998 Documented mainstem spawning of chinook salmon.
1998 Maintained real-time data collection of juvenile salmonid outmigrations.
1998 Annual estimates of salmonid returns to the Columbia River, and estimates of recreational and commercial harvest.
1998 Identified 3 potential sites in Columbia River mainstem area that would meet wildlife mitigation objectives.

Section 3. Relationships to other projects

Project IDTitleDescription
9702400 Avian Predation on Juvenile Salmonids in the Lower Columbia River Complementary study of predation by birds downstream from area covered by 9007700.
9700900 Evaluate Means of Rebuilding White Sturgeon Populations in the Snake River Complementary project to study and restore white sturgeon populations outside the geographical bounds of 8605000.
9093 Consumptive Sturgeon Fishery - Hells Canyon and Oxbow Reservoirs Complementary project to study and restore white sturgeon populations outside the geographical bounds of 8605000.
9084 Assessing Genetic Variation Among Columbia Basin White Sturgeon Populations Genetic analyses from project 9084 will be used to guide supplementation and propagation developed by project 8605000 (under this umbrella).
9603201 Begin Implementation of Year 1 of the K-Pool Master Plan Program Propagation techniques developed as part of project 8605000 will be used by project 9603201.
8906500 Annual Fish Marking Program-Missing Production Groups OR/WA/ID Recovery of CWTs from marked fish released by BPA-funded program.
8906600 Annual Coded Wire Tag Program-Missing Production WA HTCH Recovery of CWTs from marked fish released by BPA-funded program.
9701400 Evaluation of Juvenile Fall Chinook Stranding on the Hanford Reach Provides information relating to operation of the hydrosystem.
9602100 Gas Bubble Disease Research and Monitoring of Juvenile Salmonids Provides information relating to operation of the hydrosystem.
9300802 Symptoms of GBT Induced in Salmon by TDGS of the Columbia and Snake Rivers Provides information relating to operation of the hydrosystem.
8712700 Smolt Monitoring by Non-Federal Agencies
9705909 Securing Wildlife Mitigation Sites in Oregon - Mitchell Point
9705911 Securing Wildlife Mitigation Sites in Oregon - Irrigon WMA Addition
9705904 Securing Wildlife Mitigation Sites in Oregon - Horn Butte
9705900 Securing Wildlife Mitigation Sites in Oregon (Umbrella)
9079 Inventory Resident Fish in Bonneville, The Dalles, & John Day Reservoirs
9007800 Evaluate Predator Control and Provide Technical Support for PATH
9007700 Northern Pikeminnow Management Program
9600800 PATH-Participation by State & Tribal Agencies
8810804 Streamnet: The Northwest Aquatic Information Network
9105 Determine if Salmon Are Successfully Spawning Below Lower Columbia Dams
8201300 Coded Wire Tag Recovery Program
8906900 Annual Coded Wire Tag Program - Missing Production Oregon Hatcheries
9306000 Evaluate Columbia River Select Area Fisheries
20515 Mainstem Columbia River Umbrella Proposal
8605000 White Sturgeon Mitigation & Restoration in the Columbia & Snake Rivers

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel N/A $0
Fringe N/A $0
Supplies N/A $0
Travel N/A $0
Indirect N/A $0
Other N/A $0
$0
Total estimated budget
Total FY 2000 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$0
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Other budget explanation

Schedule Constraints: N/A


Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
NA - Umbrella Proposal
Date:
Jun 15, 1999

Comment:

Recommendation: NA - Umbrella Proposal

Comments: This umbrella proposal gave an informative overview of the problems but did not provide significant description of what the individual projects were going to accomplish. What is the role of BPA funding? Is it to cover the basic operation of State agencies? What is basic agency funding? BPA should set up guidelines for funding agencies and identify those things that constitute base funding.


Recommendation:
Do Not Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Criteria all: Met? NA -