FY 2000 proposal 20530
    
    
    Section 1. Administrative
    
        | Proposal title | Multi-Year Tucannon Anadromous Fish Plan | 
        | Proposal ID | 20530 | 
        | Organization | Columbia Basin Fish & Wildlife Authority (CBFWA) | 
        | Proposal contact person or principal investigator | 
        | Name | Tom Giese | 
        | Mailing address | 2501 SW First Ave., Suite 200 Portland, OR 97201 | 
        | Phone / email | 5032290191 / tom@cbfwf.org | 
        | Manager authorizing this project |  | 
        | Review cycle | FY 2000 | 
        | Province / Subbasin | Columbia Plateau / Tucannon | 
        | Short description |  | 
        | Target species |  | 
    
    Project location
    
        
            | Latitude | Longitude | Description | 
        
    
    Reasonable and Prudent Alternatives (RPAs)
    
        
        
            Relevant RPAs based on NMFS/BPA review:
            
                | Reviewing agency | Action # | BiOp Agency | Description | 
            
         
     
    
    Section 2. Past accomplishments
    
    
    Section 3. Relationships to other projects
    
        | Project ID | Title | Description | 
            
                | 9401807 | 
                Specific actions critical to objectives and strategies. | 
                 | 
            
            
                | 20530 | 
                MYP Tucannon Anadromous Fish Plan | 
                 | 
            
            
                | 9401806 | 
                Specific actions critical to objectives and strategies. | 
                 | 
            
            
                | 9401805 | 
                Specific actions critical to objectives and strategies. | 
                 | 
            
    
        
        Section 4. Budget for Planning and Design phase
        Task-based budget
        
            | Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor | 
        
        Outyear objectives-based budget
        
            | Objective | Starting FY | Ending FY | Estimated cost | 
        
        Outyear budgets for Planning and Design phase
        
        
        Section 5. Budget for Construction and Implementation phase
        Task-based budget
        
            | Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor | 
        
        Outyear objectives-based budget
        
            | Objective | Starting FY | Ending FY | Estimated cost | 
        
        Outyear budgets for Construction and Implementation phase
        
        
        Section 6. Budget for Operations and Maintenance phase
        Task-based budget
        
            | Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor | 
        
        Outyear objectives-based budget
        
            | Objective | Starting FY | Ending FY | Estimated cost | 
        
        Outyear budgets for Operations and Maintenance phase
        
        
        Section 7. Budget for Monitoring and Evaluation phase
        Task-based budget
        
            | Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor | 
        
        Outyear objectives-based budget
        
            | Objective | Starting FY | Ending FY | Estimated cost | 
        
        Outyear budgets for Monitoring and Evaluation phase
        
    
    Section 8. Estimated budget summary
    Itemized budget
    
        | Item | Note | FY 2000 cost | 
            
                | Personnel | 
                 | 
                $0 | 
            
            
                | Fringe | 
                 | 
                $0 | 
            
            
                | Supplies | 
                 | 
                $0 | 
            
         | $0 | 
    
    Total estimated budget
    
        | Total FY 2000 cost | $0 | 
            | Amount anticipated from previously committed BPA funds | $0 | 
        | Total FY 2000 budget request | $0 | 
            | FY 2000 forecast from 1999 | $0 | 
            | % change from forecast | 0.0% | 
    
    Cost sharing
    
        | Organization | Item or service provided | Amount | Cash or in-kind | 
    
    
    
    Reviews and recommendations
    This information was not provided on the original proposals, but was generated during the review process.
        
            
            Recommendation:
NA - Umbrella Proposal
            Date:
Jun 15, 1999
         
        Comment:
Recommendation:
NA - Umbrella Proposal
Comments:
This is an umbrella proposal for 3 projects, all ongoing, which relate primarily to habitat restoration in the Tucannon River basin.  There is little information in the proposal. The apparent lack of effort given to it is indication of a lack of coordination and focus in watershed restoration efforts within the basin.  Rather than an enhancement this umbrella proposal has instead become a liability for all three component projects.        
        
            
            Recommendation:
Do Not Fund
            Date:
Aug 20, 1999
         
        Comment:
        
        
            
            Recommendation:
            Date:
Aug 20, 1999
         
        Comment:
Criteria all: Met? N/A -