FY 2000 proposal 199304001
Section 1. Administrative
Proposal title | Fifteenmile Creek Wild Steelhead Smolt Production |
Proposal ID | 199304001 |
Organization | Oregon Department of Fish and Wildlife (ODFW) |
Proposal contact person or principal investigator |
Name | Erik Olsen |
Mailing address | 3450 W 10th St. The Dalles, OR 97058 |
Phone / email | 5412968045 / |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Columbia Gorge / Fifteenmile |
Short description | Estimate subbasin smolt production for the wild population of winter steelhead in Fifteenmile Creek and collect information on selected life history and biological characteristics of downstream migrant fishes endemic to Fifteenmile Creek.. |
Target species | Winter steelhead |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Year | Accomplishment |
1988 |
Estimated subbasin wild winter steelhead and spring chinook salmon smolt production. Project was funded by the U.S. Fish and Wildlife Service. |
Section 3. Relationships to other projects
Project ID | Title | Description |
8805304 |
Hood River Production Program - ODFW M&E |
Project personal will provide the supervision and oversite on this project. |
9304000 |
Fifteenmile Creek Habitat Restoration Project |
Project personal will assist with the operation and maintenance of equipment. |
9145 |
Evaluate the Status of Columbia River Sea-Run Cutthroat Trout |
|
9802100 |
Hood River Fish Habitat Project |
|
9705909 |
Securing Wildlife Mitigation Sites - Oregon, Mitchell Point |
|
9500700 |
Hood River Production Program - PGE: O&M |
|
9301900 |
Hood River Production Program - CTWS & ODFW |
|
8902900 |
Hood River Production Program - Round Butte Hatchery/Pelton ladder |
|
8805304 |
Hood River Production Program - ODFW M&E |
|
8805303 |
Hood River Production Program - CTWS M&E |
|
20513 |
Hood River/Fifteenmile Creek (umbrella proposal) |
|
9304000 |
Fifteenmile Creek Habitat Restoration Project |
|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
Personnel |
|
$11,826 |
Fringe |
|
$4,730 |
Supplies |
|
$2,505 |
Travel |
|
$998 |
Indirect |
@ 35.5% |
$7,121 |
| $27,180 |
Total estimated budget
Total FY 2000 cost | $27,180 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $27,180 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: Accurately estimating winter steelhead smolt production in FY 2000 will be dependent on environmental conditions. The Fifteenmile Creek subbasin is subject to extreme flow fluctuations which can effect sampling.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Fund (high priority).
Date:
Jun 15, 1999
Comment:
Recommendation:
Fund (high priority). OK for multi-year funding; review on an annual basis for progress towards meeting objectives.
Comments:
This was a well written, reasonable proposal, which addressed an important issue in Fifteenmile Creek (tracking wild winter steelhead smolt production). The technical aspects seemed well covered. The relationship to the rest of the program was clear, as was the importance and value of this ongoing project. Information obtained from continued funding will be quite valuable. Objectives were clear and quite substantive. Activities planned would address them well and seem highly feasible. The narrative was very well written and showed how effort and personnel would be shared among agencies and projects. There was an honest assessment explaining how weather conditions could impair some components of the project, indicating a clear grasp of the real level of feasibility. However, it is not clear from the proposal why there is a reason that mean fork length, weight, and condition are being collected. What will be done differently if these numbers are high or low? What will be done with the results? How long must these data be collected? What is the programmatic value of the information gained? What will it tell us? No project completion date was given.
Recommendation:
Fund
Date:
Aug 20, 1999
Comment:
Recommendation:
Date:
Aug 20, 1999
Comment:
Technical Criteria 1: Met? yes - Describe how objectives can be accomplished with the uncertainty of operating trap during freshets.Programmatic Criteria 2: Met? yes - Defined yes - Achievable and measurable?
Milestone Criteria 3: Met? yes - What is final outcome?
Resource Criteria 4: Met? yes -
Recommendation:
Date:
Aug 20, 1999
Comment:
#1 m&e on Obj1-3; #2 studying it, #3 in kind, no $ assigned also Mitchell Act equipment, #7-Population proposed, sunk costs would be lost.
Recommendation:
Fund
Date:
Mar 1, 2000
Comment:
[Decision made in 9-22-99 Council Meeting]