FY 2000 proposal 199405000

Additional documents

TitleType
199405000 Narrative Narrative

Section 1. Administrative

Proposal titleSalmon River Habitat Enhancement M&E
Proposal ID199405000
OrganizationShoshone-Bannock Tribes (SBT)
Proposal contact person or principal investigator
NameJeffry L. Anderson
Mailing addressP.O. Box 306 Fort Hall, ID 83203
Phone / email2082383743 / salmon1@cyberhighway.net
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinMountain Snake / Salmon
Short descriptionMaintain habitat improvements and evaluate benefits; monitor salmonid populations; coordinate evaluation of land and water stewardship activities; coordinate the planning, implementation, monitoring, and evaluation of new improvements and protections.
Target speciesSnake River spring/summer chinook salmon, Snake River summer steelhead, bull trout.
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1989 Reclamation of 2.5 km of floodplain in Bear Valley Creek eliminated a substantial source of fine sediment into the remaining 50 km of stream and the Middle Fork Salmon River.
1988 Successful interconnection of four series of remnant dredge ponds with the mainstem Yankee Fork Salmon River, creating over 1.5 ha of additional rearing habitat for anadromous salmonids.
1991 Successful modification of a debris jam and removal of an abandoned dam has allowed access to an additional 3.2 km of spawning habitat and 7.7 km of rearing habitat for anadromous salmonids and bull trout.
1992 Fencing constructed on Herd Creek to discourage livestock use of streambank and riparian areas, thus improving streambank stability and reducing sediment input into the stream.
1994 Vertical banks in a cutoff channel in Big Boulder Creek were sloped, the stream was diverted away from high cutbanks, returned to a more natural meander pattern within 0.5 km of affected floodplain, eliminating the cutoff channel of BBC as a sediment sou.

Section 3. Relationships to other projects

Project IDTitleDescription
8909803 Salmon supplementation studies in Idaho Rivers - Shoshone-Bannock Tribes Coordinate field work, share field personnel and equipment while monitoring salmonid population status in the Salmon River Basin.
9705700 Salmon River Production Program Provide assistance in developing low-tech bioenhancment facilities on the Yankee Fork Salmon River.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel 3 FTE's, 2 seasonal $113,000
Fringe 34% of FTE salary $33,000
Supplies Field Equipment and office supplies $4,200
Operating MOA with USFS, Salmon Corps field work, structural maintenance $15,000
Travel Field per diem, vehicle leases, travel $34,500
Indirect 30% of Personnel and fringe $43,800
Other Training/workshops $1,500
$245,000
Total estimated budget
Total FY 2000 cost$245,000
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$245,000
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Other budget explanation

Schedule Constraints: Some target changes for this project are dependent upon uncontrollable factors such as snow pack and run-off, which can substantially affect stream characteristics. Out-of-basin survival currently limits recovery efforts, the ultimate goal of the project.


Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fund (medium priority)
Date:
Jun 15, 1999

Comment:

Recommendation: Fund (medium priority)

Comments: This proposal focuses on monitoring and evaluation of results of previously completed "enhancement" work. This is appropriate, but there is no indication whether before-project habitat and fish data exist as a comparison. Proposed methods seem reasonable and standardized. There is to be little or no active collaboration with others, apparently, although there is mention of working cooperatively. Alternative approaches and unwanted side-effects are inadequately addressed.


Recommendation:
Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Will require BPA O&M
Recommendation:
Technically Sound? No
Date:
Aug 20, 1999

Comment:

Considerable concern about whether this long-term project has improved fish production and survival. No information is presented in Section 4 (Objectives, Costs, Schedules) about biological objectives and milestones.

Overhead rate (68%) seems high.

It is not clear how the tasks will achieve the stated objectives.

Reports to BPA should be referenced.


Recommendation:
Fund
Date:
Mar 1, 2000

Comment:

[Decision made in 9-22-99 Council Meeting]
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$245,000 $245,000 $245,000

Sponsor comments: See comment at Council's website