FY 2000 proposal 199700200
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199700200 Narrative | Narrative |
Section 1. Administrative
Proposal title | Path - UW Technical Support |
Proposal ID | 199700200 |
Organization | University of Washington (UW) |
Proposal contact person or principal investigator | |
Name | James J. Anderson |
Mailing address | 1325 - 4th Ave., Suite 1820 Seattle, WA 98101 |
Phone / email | 2065434772 / jim@fish.washington.edu |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | Test hypotheses underlying key salmon recovery management decisions, develop decision analyses to evaluate alternative management strategies, and assist in designing research monitoring and adaptive mangement experiments. |
Target species | Chinook and steelhead |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1996 | Participated in initial stages of PATH planning and helped develop suite of hypotheses to test. |
1997 | Produced preliminary retrospective and prospective passage model runs for spring chinook. Proposed althernative forms for the life cycle model. Developed hypotheses about post-Bonneville "extra-mortality." |
1998 | Produced updated prospective and retrospective passage model runs for spring chinook. Participated in weight of evidence process by contributing reports. |
Calibrated CRiSP passage model with new survival data and produced preliminary retrospective and prospective runs. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
9601700 | Technical support for PATH-Chapman Consulting | Path scientific report |
9600600 | Path-Facilitation, Technical Assistance, and Peer Review | Path scientific report |
9600800 | Path-Participation by State & Tribal Agencies | Path scientific report |
90898 | Technical support for PATH-JJA | Path scientific report |
9800100 | Analytical Support - PATH and ESA Biological Assessments | Path scientific report |
9303701 | Technical Assistance with Life Cycle Modeling | Path scientific report |
9007800 | Evaluate Predator Control and Provide Technical Support | Path scientific report |
9007700 | Northern Squawfish Management Program | Scientific report |
20537 | Bonneville Power Administration Non-Discretionary Projects | |
9700200 | PATH - UW Technical Support |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
---|---|---|
Personnel | Direct salary | $158,950 |
Fringe | Standard UW benefit rates | $35,834 |
Supplies | $7,912 | |
Operating | $14,241 | |
Capital | Office Lease | $16,657 |
Travel | $7,500 | |
Indirect | $58,354 | |
Other | Tuition fees | $1,633 |
$301,081 |
Total estimated budget
Total FY 2000 cost | $301,081 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $301,081 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Other budget explanation
Schedule Constraints: Changes in PATH process may alter task timeline.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Recommendation: Do not fund. PATH, in its present form, with its present mission, should be phased out. A simpler process could be created to meet the continuing need for evaluation of the limited data now available to address management questions relative to the hydro biological opinion. A more ambitious and comprehensive scientific consensus process should be developed, somewhat along the lines of PATH, to address data collection design issues for the basin, to identify data needs that are critical to the actual management questions, and to ensure that data needs are met, to the extent practical, as quickly as possible, in a coordinated and efficient manner.Comments: Relates closely to 8910800. Why is this separate from 9800600? There should be a better description of the indirect costs to the UW and the direct costs for office space.
Comment:
Comment:
PATH projects reviewed in detail last year, little has changed. Appears to duplicate Project #9800600. Question amount of hours. Needs to be related through an umbrella. Due to budget constraints, AFM suggests holding these projects to the FY99 funding level.Comment:
Technical Criteria 1: Met? Yes - Needs to be put under PATH umbrella. Needs multi-year budget.Programmatic Criteria 1: Met? Yes - Question what aspect of PATH is being covered here that is not covered in the above project. Put under the PATH umbrella if it is not duplicative of 9700200.
Milestone Criteria 2: Met? Yes -
Resource Criteria 2: Met? Inc -
Comment:
Technical Criteria 3: Met? Yes -Programmatic Criteria 3: Met? Yes -
Milestone Criteria 4: Met? Yes -
Resource Criteria 4: Met? No -
Fund for the transition period
Oct 29, 1999
Comment:
Fund for transition period. See the programmatic recommendation in project 9600600.Comment:
Money placed in BPA Tech Support Project Placeholder
Mar 1, 2000
Comment:
[Decision made in 12-7-99 Council Meeting]; Funding subject to independent review: BPA non-discretionary (Technical Support Project Placeholder)