FY 2000 proposal 199700200

Additional documents

TitleType
199700200 Narrative Narrative

Section 1. Administrative

Proposal titlePath - UW Technical Support
Proposal ID199700200
OrganizationUniversity of Washington (UW)
Proposal contact person or principal investigator
NameJames J. Anderson
Mailing address1325 - 4th Ave., Suite 1820 Seattle, WA 98101
Phone / email2065434772 / jim@fish.washington.edu
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinMainstem/Systemwide / Systemwide
Short descriptionTest hypotheses underlying key salmon recovery management decisions, develop decision analyses to evaluate alternative management strategies, and assist in designing research monitoring and adaptive mangement experiments.
Target speciesChinook and steelhead
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1996 Participated in initial stages of PATH planning and helped develop suite of hypotheses to test.
1997 Produced preliminary retrospective and prospective passage model runs for spring chinook. Proposed althernative forms for the life cycle model. Developed hypotheses about post-Bonneville "extra-mortality."
1998 Produced updated prospective and retrospective passage model runs for spring chinook. Participated in weight of evidence process by contributing reports.
Calibrated CRiSP passage model with new survival data and produced preliminary retrospective and prospective runs.

Section 3. Relationships to other projects

Project IDTitleDescription
9601700 Technical support for PATH-Chapman Consulting Path scientific report
9600600 Path-Facilitation, Technical Assistance, and Peer Review Path scientific report
9600800 Path-Participation by State & Tribal Agencies Path scientific report
90898 Technical support for PATH-JJA Path scientific report
9800100 Analytical Support - PATH and ESA Biological Assessments Path scientific report
9303701 Technical Assistance with Life Cycle Modeling Path scientific report
9007800 Evaluate Predator Control and Provide Technical Support Path scientific report
9007700 Northern Squawfish Management Program Scientific report
20537 Bonneville Power Administration Non-Discretionary Projects
9700200 PATH - UW Technical Support

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel Direct salary $158,950
Fringe Standard UW benefit rates $35,834
Supplies $7,912
Operating $14,241
Capital Office Lease $16,657
Travel $7,500
Indirect $58,354
Other Tuition fees $1,633
$301,081
Total estimated budget
Total FY 2000 cost$301,081
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$301,081
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Other budget explanation

Schedule Constraints: Changes in PATH process may alter task timeline.


Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Do Not Fund
Date:
Jun 15, 1999

Comment:

Recommendation: Do not fund. PATH, in its present form, with its present mission, should be phased out. A simpler process could be created to meet the continuing need for evaluation of the limited data now available to address management questions relative to the hydro biological opinion. A more ambitious and comprehensive scientific consensus process should be developed, somewhat along the lines of PATH, to address data collection design issues for the basin, to identify data needs that are critical to the actual management questions, and to ensure that data needs are met, to the extent practical, as quickly as possible, in a coordinated and efficient manner.

Comments: Relates closely to 8910800. Why is this separate from 9800600? There should be a better description of the indirect costs to the UW and the direct costs for office space.


Recommendation:
Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

PATH projects reviewed in detail last year, little has changed. Appears to duplicate Project #9800600. Question amount of hours. Needs to be related through an umbrella. Due to budget constraints, AFM suggests holding these projects to the FY99 funding level.
Recommendation:
Date:
Aug 20, 1999

Comment:

Technical Criteria 1: Met? Yes - Needs to be put under PATH umbrella. Needs multi-year budget.

Programmatic Criteria 1: Met? Yes - Question what aspect of PATH is being covered here that is not covered in the above project. Put under the PATH umbrella if it is not duplicative of 9700200.

Milestone Criteria 2: Met? Yes -

Resource Criteria 2: Met? Inc -


Recommendation:
Date:
Aug 20, 1999

Comment:

Technical Criteria 3: Met? Yes -

Programmatic Criteria 3: Met? Yes -

Milestone Criteria 4: Met? Yes -

Resource Criteria 4: Met? No -


Recommendation:
Fund for the transition period
Date:
Oct 29, 1999

Comment:

Fund for transition period. See the programmatic recommendation in project 9600600.
Recommendation:
Fund for transition
Date:
Nov 8, 1999

Comment:


Recommendation:
Money placed in BPA Tech Support Project Placeholder
Date:
Mar 1, 2000

Comment:

[Decision made in 12-7-99 Council Meeting]; Funding subject to independent review: BPA non-discretionary (Technical Support Project Placeholder)