FY 2001 Ongoing proposal 199404200

Additional documents

TitleType

Section 1. Administrative

Proposal titleTrout Creek Habitat Restoration Project
Proposal ID199404200
OrganizationOregon Department of Fish and Wildlife (ODFW)
Proposal contact person or principal investigator
NameTom Nelson
Mailing address1595 N Hwy 26 Madras, OR 97741
Phone / email5414752183 / troutck@madras.net
Manager authorizing this projectAllan R. Dale
Review cycleFY 2001 Ongoing
Province / SubbasinColumbia Plateau / Deschutes
Short descriptionOperation and Maintenance of instream and riparian habitat improvement; Monitoring and Evaluation of basin SSt smolt production and habitat recovery; coordination for basin long range plan; resulting in increased native salmonid and wildlife production.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
2000 Have built and continue ongoing maintaine of 132 miles of ripairan protection fence .
2000 Conduct out migrant monitoring, since 1998.
2000 Since 1986, have placed 19,500 feet of Juniper Rip Rap.
2000 Since 1986 have placed 3397 habitat boulders.
2000 Since 1986 have placed 498 pieces of LWD.
2000 Since 1986 have placed 189 log weirs.
2000 Since 1986 have built 236 rock weirs.
2000 Since 1988 have built and maintain 6 off channel water developments.
2000 Assisted in the removal of two gravel push up dams. Removal of 3 gravel push up dams scheduled for summer 2000.
2000 Assisted in the operation and maintenance of 45 fish screens in the Deschutes Basin.
2000 Assisted the Trout Creek watershed council on development of a Trout Creek basin long range plan.
2000 Assisted the Trout Creek watershed council with technical advice and input for demonstration projects.
2000 Continued working with COE on removal of 1964 berms and channel reconstruction.

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Develop Trout Creek long range plan a. Assist in the development of a long range plan and watershed action plan. 3 $9,231
2. Continuing education a. Attend Rosgen geomorphology class. 3 $7,150
3. Project coordination with Or. Screens a. Negoiate with landowners on ways to remove gravel push up dams in basin. 7 $13,847
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase
FY 2004FY 2005FY 2002FY 2003
$26,000$26,750$31,500$32,500

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Promote bank stability through riparian vegetation recovery. a. Inspect and maintain 132 miles of riparian fencing. 8 $157,188
b. Work with COE on 1964 berm removal and channel reconstruction. 6 $12,890
2. Increase instream habitat diversity. a. Inspect several hundred instream, structures and >20,000 feet of bank stabilization structures and maintain as necessary. 8 $72,890
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2004FY 2005FY 2002FY 2003
$265,500$273,463$250,257$257,765

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Determine riparian and instream habitat and sumer steelhead population response to project work. Gain additional knowledge as to what habitat actions produce the best results. Understand the idiosyncrasies of Trout Cr. SSt. a. Smolt Trapping 8 $39,130
b. Photo points 8 $5,590
c. Water temperature monitioring 8 $11,180
2. Determine water withdrawl timing and quantity in basin. a. Monitor water withdrawl and timing throughout irrigation season. Provide O&M on gauging stations. 5 $29,750 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase
FY 2004FY 2005FY 2002FY 2003
$93,593$96,401$88,220$90,867

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: 0.275 $11,353
Fringe OPE 0.395 $4,484
Supplies $2,890
Travel Rosgen training $5,150
Indirect 0.266 $6,351
Personnel FTE: 3.2 $105,332
Fringe OPE 0.395 $41,606
Supplies $42,480
Travel $2,500
Indirect 0.266 $51,050
Personnel FTE: 0.73 $22,154
Fringe OPE 0.395 $8,751
Supplies $13,250
Indirect $11,745
Capital If 2-3' screw traps become available $0
Subcontractor Oregon Water Resources $29,750
$358,846
Total estimated budget
Total FY 2001 cost$358,846
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$358,846
FY 2001 forecast from 2000$389,800
% change from forecast-7.9%
Reason for change in estimated budget

Elimination of Oregon State Police task from proposed budget.

Reason for change in scope

NA

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000

Comment:

There is an elimination of Oregon State Police task from proposed budget. There is no change in scope of work.
Recommendation:
Fund
Date:
Sep 13, 2000

Comment:


REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$383,662 $383,662 $383,662

Sponsor comments: See comment at Council's website