FY 2001 Ongoing proposal 199500100
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | Kalispel Tribe Resident Fish |
Proposal ID | 199500100 |
Organization | Kalispel Tribe of Indians (KNRD) |
Proposal contact person or principal investigator | |
Name | Todd Andersen/Stan Bluff Jr |
Mailing address | Usk, WA 99180 |
Phone / email | 5094451147 / tandersen@knrd.org |
Manager authorizing this project | Joseph Maroney |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Mountain Columbia / Lower Pend Oreille |
Short description | Assess native trout habitat in tributaries to the Pend Oreille River and implement recommendations for enhancement. Provide largemouth bass habitat in mainstem Pend Oreille River and supplement population. Monitor and evaluate all enhancement measures. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1995 | Assess priority tributaries |
1995 | Developed recommendations for tributary enhancement |
1995 | Designed largemouth bass hatchery |
1995 | Developed recommendations for warmwater habitat enhancement |
1996 | Constructed largemouth bass hatchery |
1996 | Implement tributary enhancement measures |
1996 | Implement warmwater enhancement measures |
1997 | Monitor and evaluate warmwater habitat enhancement (ongoing) |
1997 | Monitor and evaluate tributary enhancement (ongoing) |
1999 | Released 150,000 largemouth bass |
2000 | Released 150,000 largemouth bass |
2000 | Monitor and evaluate largemouth bass supplementation |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Plan and design instream restoration measures based upon recommendations. | a. With specific reaches identified for enhancement, coordinate with landowners (e.g. USFS, private) | 5 | $2,000 | |
b. Obtain necessary permits (e.g. HPA, USFWS permit) | 5 | $2,000 | ||
2. Plan and design for exotic brook trout removal in upper Cee Cee Ah Creek. | a. Gather necessary information pertaining to exotic fish removal with toxicants. | 1 | $2,000 | |
b. Write a study design plan for brook trout removal with a pre-implementation and post-implementation monitoring phase. | 1 | $5,000 | ||
c. Coordinate with landowners, WDFW, USFWS and other regulatory agencies on proposal of brook trout removal. | 1 | $4,000 | ||
d. Obtain necessary permits (e.g. HPA, USFWS permit) | 1 | $2,100 | ||
e. NEPA compliance | 1 | $10,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
FY 2003 | FY 2004 | FY 2005 | FY 2002 |
---|---|---|---|
$18,000 | $19,000 | $20,000 | $17,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Implement instream restoration structures. | a. Install instream structures in selected tributaries to Box Canyon Reservoir. | 8 | $67,000 | |
2. Implement fencing exclosures within riparian areas. | a. Construct fencing exclosures in riparian areas affected by grazing. | 8 | $23,000 | |
b. Plant within fencing exclosures. | 8 | $12,000 | ||
3. Implement brook trout removal | a. Remove exotic brook trout with toxicants in upper Cee Cee Ah Creek. | 1 | $50,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2004 | FY 2005 | FY 2002 |
---|---|---|---|
$154,000 | $157,000 | $160,000 | $151,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Operate and maintain largemouth bass hatchery to increase harvestable biomass in Box Canyon Reservoir. | a. Egg collection, spawning and incubation of largemouth bass to meet 2001 APG. | 10+ | $49,000 | |
b. Hatch, rear and train on feed, juvenile largemouth bass. | 10+ | $41,000 | ||
c. Mark all hatchery production and outplant fry and fingerlings to Box Canyon Reservoir. | 10+ | $24,000 | ||
d. Maintain daily operations for hatchery. | 10+ | $45,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2002 |
---|---|---|---|
$172,000 | $176,000 | $180,000 | $168,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Monitor and evaluate habitat enhancement projects | a. Conduct post-assessments on enhancement structures built during 1996-1998 by an intensive assessment of the enhancement area and fish snorkel survey. | 3 | $21,000 | |
b. Conduct post-assessments on fencing and riparian planting reaches completed during 1996 and 1997 through an intensive assessment of the enhancement area and fish snorkel survey. | 3 | $9,000 | ||
c. Develop recommendations for additional enhancement structures. | 4 | $3,000 | ||
d. Maintenance of habitat enhancement structures. | 10 | $3,000 | ||
e. Prepare and submit quarterly and annual reports. | 10 | $5,000 | ||
2. Monitor and evaluate warmwater habitat enhancement project. | a. Electroshock warmwater enhancement structures placed in Box Canyon Reservoir to determine fish utilization and enhancement effectiveness. | 5 | $14,900 | |
b. Based on information collected in monitoring and evaluation phase, develop recommendations for additional warmwater enhancement structures. | 2 | $3,000 | ||
c. Prepare and submit quarterly and annual reports. | 5 | $3,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
FY 2003 | FY 2004 | FY 2005 | FY 2002 |
---|---|---|---|
$76,000 | $78,000 | $80,000 | $74,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | FTE: .25 | $10,000 |
Fringe | 33% | $3,300 |
Travel | $1,000 | |
Indirect | 20% | $2,800 |
NEPA | $10,000 | |
Personnel | FTE: 2.0 | $64,000 |
Fringe | 33% | $21,000 |
Supplies | $25,000 | |
Travel | $12,000 | |
Indirect | 20% | $25,000 |
NEPA | $5,000 | |
Personnel | FTE: 2 | $64,000 |
Fringe | 33% | $21,000 |
Supplies | $18,000 | |
Travel | $11,000 | |
Indirect | 20.0% | $22,500 |
Subcontractor | Fish tagging equipment | $12,000 |
Other | $10,500 | |
Personnel | FTE: 1.0 | $34,000 |
Fringe | 33% | $11,000 |
Supplies | $1,900 | |
Travel | $5,000 | |
Indirect | 20% | $10,000 |
$400,000 |
Total estimated budget
Total FY 2001 cost | $400,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $400,000 |
FY 2001 forecast from 2000 | $400,000 |
% change from forecast | 0.0% |
Reason for change in estimated budget
N/A
Reason for change in scope
N/A
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Comment:
Rationale: Budget increase inappropriate in this review. Expansion of effort should depend on provincial reviewNW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$429,600 | $429,600 | $429,600 |
Sponsor comments: See comment at Council's website