Proposal title | Toppenish-Simcoe Instream Flow Restoration and Assessment |
Proposal ID | 199705300 |
Organization | Yakama Nation Fisheries Management Program (YN) |
Proposal contact person or principal investigator |
Name | Kale Gullett |
Mailing address | Toppenish, WA 98948 |
Phone / email | 5098656262 / gullett@yakama.com |
Manager authorizing this project | Lynn Hatcher |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Columbia Plateau / Yakima |
Short description | Identify extent of anadromous populations, identify land status, characterize habitat and discharge; model irrigation use; restore instream flows by land lease or purchase and/or water substitution; modify irrigation diversions to mimic natural runoff. |
Target species | |
Year | Accomplishment |
1998 |
Project initiation (Feb, 1998), began weekly collection of discharge data in Project watercourses, baseline steelhead spawning and rearing information gathered, began Project GIS. |
1999 |
First complete year of discharge information gathered, began Project water budget model, began Draft Management Plan, augmented steelhead spawning and rearing information, updated Project GIS with flow and fish data, land status and cropping data. |
2000 |
Deployed screw trap, completed 2nd year of discharge and aquatic data, improved water budget model, began modeling water use in Project Area, secured lease option on 232 acres of riparian land w/ water, updated Project GIS and Management Plan. |
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Adaptively update Project Management Plan. |
1a. Update Project water model with most recent discharge data. |
1 (yearly activity) |
$8,800 |
|
|
1b. Update Project GIS with any new land status, delivery and drainage feature, orthophotos, district maps and non-YN coverages. |
1 (yearly activity) |
$20,595 |
|
|
1c. Calibrate water budget model with newest data. |
1 (yearly activity) |
$8,800 |
|
|
1d. Integrate most recent redd survey, smolt trap and fish census information to portray steelhead utilization and outmigrant timing in Project Area. |
1 (yearly activity) |
$8,800 |
|
|
1e. Incorporate groundwater data from piezometers in alluvial aquifer reach of Toppenish Creek to provide further data for land acquisition decision support system. |
1 (yearly activity) |
$10,200 |
|
|
1f. Update land acquisition decision support system and target lands list with output of Tasks 1a-e above. |
1 (yearly activity) |
$30,990 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Work with YN Wildlife Program and BIA Realty to acquire leases or purchase lands. |
1a. Prepare written justification for leases or purchase, assist other YN and BIA personnel with lease/purchase agreements. |
As Required |
$5,200 |
|
|
1b. Present any required background information to appropriate Council and colleagues. |
As Required |
$2,500 |
|
|
1c. Maintain and enforce lease requirements. |
Duration of leases (10 years) |
$50,000 |
|
|
1d. On lands purchased with Project funds, decommission withdrawal structures and work with other YN programs to inaugurate any restoration measures needed to return land to native state. |
As required |
$2,500 |
|
2. Restrict diversion timing, where possible, to periods when discharge is not limiting to aquatic ecosystem health. |
2a. Monitor discharge in and around project watercourses affected by Objective 2 to enforce Project goals. |
Duration of leases (10 years) |
$10,595 |
|
|
2b. Identify willing landowners to decrease or cease late spring-summer diversions to benefit fish and aquatic life (can hopefully be used in conjunction with Objective 3). |
As Required |
$5,000 |
|
3. Substitute out-of-stream withdrawals with alternate sources. |
3a. Work with BIA, YN and private landowners to develop plans for water substitution. |
As Required |
$8,000 |
|
|
3b. Identify funding sources when monies are needed to develop substitute water sources. |
As Required |
$7,500 |
|
|
3c. Enforce water substitution scenarios and monitor compliance. |
Duration of leases (10 years) |
$6,330 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Monitor Project Area water budget. |
1a. Measure watercourse discharge and temperature over time and space at key locations specified by O&M Objectives 1-3. |
10 (as long as funding continues) |
$10,164 |
|
|
1b. Monitor Toppenish Creek alluvial aquifer by maintaining collection and analysis of piezometric groundwater surface data. |
10 (as long as funding continues) |
$2,500 |
|
2. Maintain database of channel and riparian condition. |
Task 2a. Assess channel morphology and condition as necessary pursuant to streamflow restoration efforts. PFC index sites will be re-evaluated every 2 years to establish trends over time. |
10 (as long as funding continues) |
$1,200 |
|
3. Monitor aquatic ecosystem health and surface/groundwater species assemblages. |
3a. Continue operation of 5-foot screwtrap to describe steelhead smolt outmigration timing, age structure and relative number of outmigrants per year. |
10 (as long as funding continues) |
$7,800 |
|
|
3b. Monitor numbers of returning steelhead adults by yearly spawning ground surveys and adult counts at Prosser and Roza monitoring windows. |
10 (as long as funding continues) |
$10,164 |
|
|
3c. Monitor Toppenish Creek alluvial fan hyporheic macroinvertebrate community by continued pumping of groundwater/macroinvertebrate wells and collection/identification/enumeration of organisms. |
10 (as long as funding continues) |
$5,500 |
|
Item | Note | FY 2001 cost |
Personnel |
FTE: 1.19 |
$49,507 |
Fringe |
17.6% for exempt FTE's, 20% for non-exempt |
$9,330 |
Supplies |
Office supplies, field supplies, repairs, field and office equipment |
$3,400 |
Travel |
Travel, per diem, and tuition for presentations, workshops and meetings (lumped for all personnel) |
$750 |
Indirect |
23.5% on all items in budget |
$16,780 |
NEPA |
BPA Supplemental Analysis underway |
$0 |
Other |
Insurance, utilities, building depreciation, vehicle rental and mileage. |
$8,418 |
Personnel |
FTE: 0.225 |
$8,315 |
Fringe |
17.6% for exempt FTE's, 20% for non-exempt |
$1,627 |
Supplies |
Office supplies |
$200 |
Travel |
Travel, per diem, and tuition for presentations, workshops and meetings (lumped for all personnel) |
$750 |
Indirect |
23.5% on all items in budget |
$2,733 |
NEPA |
BPA Supplemental Analysis underway |
$0 |
Other |
Utilities, building depreciation |
$740 |
Personnel |
FTE: 0.54 |
$21,802 |
Fringe |
17.6% for exempt FTE's, 20% for non-exempt |
$4,057 |
Supplies |
Office supplies, field supplies, repairs, field and office equipment |
$1,700 |
Travel |
Travel, per diem, and tuition for presentations, workshops and meetings (lumped for all personnel) |
$750 |
Indirect |
23.5% on all items in budget |
$18,576 |
Capital |
Land Rental (1000 acres @ $50/acre) |
$50,000 |
NEPA |
BPA Supplemental Analysis underway |
$0 |
Other |
Utilities, building depreciation |
$740 |
Personnel |
FTE: 0.55 |
$22,366 |
Fringe |
17.6% for exempt FTE's, 20% for non-exempt |
$4,169 |
Supplies |
Office supplies, field supplies, repairs, field and office equipment |
$2,200 |
Travel |
Travel, per diem, and tuition for presentations, workshops and meetings (lumped for all personnel) |
$750 |
Indirect |
23.5% on all items in budget |
$7,103 |
NEPA |
BPA Supplemental Analysis underway |
$0 |
Other |
Utilities, building depreciation |
$740 |
| $237,503 |
The projection made for FY2001 during the FY2000 application process counted on receipt of land leasing/purchase funds during the FY2000 award period. However, the $52,000 land acquisition item was cut from our FY 2000 request. Having survived for two years on FY97 funds, we were able to modify our FY99 budget to pay for leasing 232 acres formerly irrigated with creek water at the end of CY1999. We have yet to receive any funding for land acquisition, an essential component of the Project. The 18.8% increase from the FY2000 forecast reflects the need to move the acquisition process along after earlier denials of this component.
No significant changes in scope have occurred since the inauguration of the Project.
This information was not provided on the original proposals, but was generated during the review process.
No significant changes in the scope of work have occurred since the inauguration of the Project.