FY 2001 Ongoing proposal 199801700

Additional documents

TitleType

Section 1. Administrative

Proposal titleEliminate Gravel Push-up Dams in Lower North Fork John Day
Proposal ID199801700
OrganizationNorth Fork John Day Watershed Council (NFJDWC)
Proposal contact person or principal investigator
NameRobert Stubblefield
Mailing addressP.O. Box 95 Monument, OR 97864
Phone / email5419342141 / waterguy@transport.com
Manager authorizing this projectJack Cavender, Chairman, Monument SWCD
Review cycleFY 2001 Ongoing
Province / SubbasinColumbia Plateau / John Day
Short descriptionEliminate gravel push-up dams in the lower North Fork John Day River. Replace with permanent pumping stations resulting in removal of passage impediments and elimination of annual instream modification.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1998 Replaced gravel push-up dams at River Meadows Ranch and Schultz Ranches with permanent pumping stations.
1998 Monitored water temperatures and overall water quality throughout summer season.
1998 Initiated and proposed projects to replace five additional push-up dams.
1999 Completed design for installations to replace three push-up dams with permanent pumping stations.

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. NEPA Review a. Complete NEPA checklist 1 $2,000
2. NMFS Consultation b. Complete Section 7 Consultation 1 $2,000
3. Design Projects a. Engineer Project Designs 1 $7,600 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase
FY 2002
$12,000

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Power Installation a. Relocate powerlines to location of permanent pumping installations. 1 $18,000 Yes
2. Install permanent pumping stations a. Purchase materials for installations. 1 $50,500
b. Install materials. 1 $20,000 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase
FY 2002
$90,000

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Clean permanent pumping stations. a. Annually pump accumulated silt from systems. 1 $2,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2005FY 2003FY 2004FY 2002
$1,000$1,000$1,000$1,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Monitor water quality. a. Install temperature monitors at each project site. 1 $500
b. Compute and store data. 1 $1,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase
FY 2005FY 2003FY 2004FY 2002
$1,500$1,500$1,500$1,500

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: .1 $3,000
Travel $500
Indirect $1,100
Subcontractor $7,000
Supplies $47,000
Travel $1,000
Indirect $4,500
Subcontractor $36,000
Supplies $2,000
Personnel FTE: .05 $1,500
$103,600
Total estimated budget
Total FY 2001 cost$103,600
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$103,600
FY 2001 forecast from 2000$90,250
% change from forecast14.8%
Reason for change in estimated budget

Cost of installation materials (PVC pipe) have risen dramatically due to higher oil prices.

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000

Comment:

The budget has increased due to a dramatic rise in the cost of installation materials (PVC pipe) because of higher oil prices. There is no change in the scope of work.
Recommendation:
Fund
Date:
Sep 13, 2000

Comment:

Rationale: Budget increase inappropriate in this review. Project has not used $90,250 budgeted for 2000. Check availability of carry-forward.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$105,134 $105,134 $105,134

Sponsor comments: See comment at Council's website