FY 2001 Ongoing proposal 199901700
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
| Title | Type |
|---|
Section 1. Administrative
| Proposal title | Protect & Restore Lapwai Creek Watershed |
| Proposal ID | 199901700 |
| Organization | Nez Perce Fisheries/Watershed Program (NPT) |
| Proposal contact person or principal investigator | |
| Name | Felix M. Mcgowan |
| Mailing address | P.O. Box 365 Lapwai, ID 83540 |
| Phone / email | 2088437320 / felixm@nezperce.org |
| Manager authorizing this project | Ira Jones |
| Review cycle | FY 2001 Ongoing |
| Province / Subbasin | Mountain Snake / Clearwater |
| Short description | Restore Lapwai Creek and tributaries to a more healthy and productive system which is capable of sustaining a self perpetuating population of anadromous and resident fish. |
| Target species | |
Project location
| Latitude | Longitude | Description |
|---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
| RPA |
|---|
Relevant RPAs based on NMFS/BPA review:
| Reviewing agency | Action # | BiOp Agency | Description |
|---|
Section 2. Past accomplishments
| Year | Accomplishment |
|---|---|
| 2000 | Completion of Watershed Assessment on Lapwai Creek Watershed. |
Section 3. Relationships to other projects
| Project ID | Title | Description |
|---|
Section 4. Budget for Planning and Design phase
Task-based budget
| Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
|---|---|---|---|---|
| 1. Plan restoration activities based on the assessment outcomes. | a. Identify priorities within the watershed. | 1, ongoing | $10,877 | |
| b. Develop agreements with land owners and tribal officials. | 1, ongoing | $10,877 | ||
| 2. Develop Monitoring and Evaluation plan for the watershed. | a. Create site specific plans for activities within the watershed. | 1, ongoing | $10,879 | |
| b. Identify data gaps from the assessment. | 1 | $10,877 | ||
| 3. Design any channel work to be accomplished. | a. Gather any additional data needed for design. | 1, ongoing | $10,877 | |
| b. Subcontract to complete design work. | 1, ongoing | $10,000 | Yes | |
| 4. Place watershed program in own work space. | a. Purchase office space for program. | 1 | $35,613 |
Outyear objectives-based budget
| Objective | Starting FY | Ending FY | Estimated cost |
|---|
Outyear budgets for Planning and Design phase
| FY 2005 | FY 2003 | FY 2004 | FY 2002 |
|---|---|---|---|
| $210,000 | $190,000 | $200,000 | $180,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
| Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
|---|
Outyear objectives-based budget
| Objective | Starting FY | Ending FY | Estimated cost |
|---|
Outyear budgets for Construction and Implementation phase
| FY 2005 | FY 2003 | FY 2004 | FY 2002 |
|---|---|---|---|
| $210,000 | $110,000 | $200,000 | $100,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
| Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
|---|
Outyear objectives-based budget
| Objective | Starting FY | Ending FY | Estimated cost |
|---|
Outyear budgets for Operations and Maintenance phase
| FY 2005 | FY 2003 | FY 2004 | FY 2002 |
|---|---|---|---|
| $50,000 | $50,000 | $50,000 | $50,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
| Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
|---|
Outyear objectives-based budget
| Objective | Starting FY | Ending FY | Estimated cost |
|---|
Outyear budgets for Monitoring and Evaluation phase
| FY 2005 | FY 2003 | FY 2004 | FY 2002 |
|---|---|---|---|
| $25,000 | $25,000 | $25,000 | $25,000 |
Section 8. Estimated budget summary
Itemized budget
| Item | Note | FY 2001 cost |
|---|---|---|
| Personnel | FTE: 2 | $5,750 |
| Fringe | 14% for tax exempt employees | $805 |
| Supplies | office, copies, etc. | $1,000 |
| Travel | field per diem, travel to PDX, BOI | $3,700 |
| Indirect | 26.61% | $3,473 |
| Subcontractor | Channel design work | $47,829 |
| Other | Vehicle expense, office lease | $37,443 |
| $100,000 | ||
Total estimated budget
| Total FY 2001 cost | $100,000 |
| Amount anticipated from previously committed BPA funds | $0 |
| Total FY 2001 budget request | $100,000 |
| FY 2001 forecast from 2000 | $100,000 |
| % change from forecast | 0.0% |
Cost sharing
| Organization | Item or service provided | Amount | Cash or in-kind |
|---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
CBFWA Funding Recommendation
Ongoing Funding: yes; New Funding: no
Jul 14, 2000
Comment:
There is no change in the budget or the scope of work.Comment:
Rationale: Budget increase inappropriate in this review.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
| FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
| $466,794 | $466,794 | $466,794 |
Sponsor comments: See comment at Council's website