Section 1. Administrative
Proposal title | Sandy River Delta Riparian Reforestation |
Proposal ID | 199902600 |
Organization | USDA Forest Service, Columbia River Gorge National Scenic Area (USFS) |
Proposal contact person or principal investigator | |
Name | Virginia Kelly |
Mailing address | 902 Wasco Ave., Suite 200 Hood River, OR 97031 |
Phone / email | 5413081720 / vkelly@fs.fed.us |
Manager authorizing this project | Arthur Carroll, Area Manager |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Lower Columbia / Sandy |
Short description | Restore 250 acres of rare Columbia River floodplain ‘gallery’ riparian forest (dense, unbroken stands of black cottonwood, willow, ash). Reforestation will improve habitat for riparian forest species. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1997 | Restored (cleared and planted) 3 acres riparian forest. |
1998 | Restored (cleared and planted) 8 acres riparian forest. Follow-up clearing on 3 acres previously restored riparian forest. |
1999 | Cleared 45 acres, planted 22,300 trees on 27 acres, did follow-up clearing on 30 acres previously restored riparian forest. |
2000 | Planned restoration of 40 to 60 acres riparian forest, establish HEP values. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
All planning and design is completed by Forest Service. | $0 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Site Preparation | 1a. Site clearing, spraying, pre-planting grubbing, etc) | 10 | $20,000 | Yes |
2. Planting (no BPA funds requested) | 2a. Planting | 10 | $0 | |
3. Post Planting Site Clearing | 3a. Grub, mow, etc around seedlings | 10 | $1,500 | Yes |
4. Establish HEP Values | 4a. Write report based on FY2000 field work (approx. $1,375 carryover from FY2000 budget) | 2 | $1,375 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2005 | FY 2003 | FY 2004 | FY 2002 |
---|---|---|---|
$21,500 | $21,500 | $21,500 | $21,500 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
No BPA funds requested. | $0 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Monitor Seedlings (no BPA funds requested) | a. Visual Observation/Measure Seedling Survival | 20 | $0 | |
2. Monitor Wildlife Populations (no BPA funds requested) | a. Monitor neo-tropical migrant populations | 20 | $0 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Subcontractor | 1a. Hydro-ax, mower, county crews, etc | $21,500 |
Subcontractor | 4a. University of Idaho (HEP report-FY2000 carry-over funds) | $1,375 |
$22,875 |
Total estimated budget
Total FY 2001 cost | $22,875 |
Amount anticipated from previously committed BPA funds | $1,375 |
Total FY 2001 budget request | $21,500 |
FY 2001 forecast from 2000 | $21,500 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.