FY 2001 Ongoing proposal 200002800

Additional documents

TitleType

Section 1. Administrative

Proposal titleEvaluate Status of Pacific Lamprey in the Clearwater River Drainage, Idaho
Proposal ID200002800
OrganizationIdaho Department of Fish and Game (IDFG)
Proposal contact person or principal investigator
NameTim Cochnauer
Mailing address1540 Warner Lewiston, ID 83501
Phone / email2087995010 / tcochnau@idfg.state.id.us
Manager authorizing this project
Review cycleFY 2001 Ongoing
Province / SubbasinMountain Snake / Clearwater
Short descriptionThe Pacific Lamprey life history is poorly known throughout its range. This project will collect information to add to Pacific Lamprey population status and life history in Idaho.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
2000 This is the first year of the project with only logistical planning and equipment acquisition accomplished through April, 2000.

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Determine life history characteristics of ammocoetes and macrothalmia 1.1 Determine age, size, and timing of outmigrant juveniles by collecting and measuring ammocoetes and macrothalmia in downstream floating rotary traps on Red and American rivers. 3 $10,873
1.2 Determine relative abundance of outmigrants by marking juveniles prior to outmigration and at capture locations upstream of traps. 3 $10,873
1.3 Determine age class distribution and density of ammocoetes and estimate population size by capturing lamprey juveniles utilizing electroshocking or other applicable methods. 3 $11,386
1.4 Provide a maximum of 50 ammocoetes collected in Task 1.3 to the Columbia River Research Laboratory for rearing to transformation and genetic analysis 3 $979
1.5 Coordinate with US Army Corps of Engineers, Washington Department of Fisheries, National Marine Fisheries Service and other personnel working at mainstem Snake River and Columbia River dams for information on any marked juvenile outmigrants. 3 $6,726
2. Determine Pacific lamprey habitat requirements in the Clearwater River basin. 2.1 Sampling locations will be the same as those utilized in Task 1.3. Habitat parameters to be measured include: substrate type, substrate temperature, water depth, water velocity, water temperature, gradient, cover and light intensity. 3 $10,861
2.2 On random encounter of any adult lamprey, all parameters described in Task 2.1 will be measured. 3 $10,349
3. Document distribution of Pacific lamprey and habitat in S.F. Clearwater River 3.1 Coordinates will be recorded at each site of collection or observation and habitat measurement, and linked to GIS overlays. 3 $5,992
4. Data analysis, coordination and data sharing 4.1 Coordinate activities with Pacific lamprey technical work group and other interested parties. 3 $6,344
4.2 Data assimilation, analysis, and reporting. $10,179
4.3 Coordinate activities with graduate program at University of Idaho. 3 $6,405 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase
FY 2005FY 2003FY 2004FY 2002
$49,500$105,100$47,000$97,800

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Protect and restore critical juvenile rearing and adult spawning habitat 1.1 Utilizing GIS maps, identify critical habitat in need of protection and degraded habitat in need of restoration. 2 $0
1.2 Work with land management agencies in S. F. Clearwater River drainage to develop long term strategies to protect existing critical habitat. 2 $0
1.3 Work with land management agencies in S.F. Clearwater River drainage to develop strategies to restore degraded lamprey habitat. 2 $0
1.4 Implement restoration and protection strategies and monitor effectiveness of each. 10 $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase
FY 2005FY 2004
$69,000$67,000

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: Biologist-2 mos; Fish Tech-8 mos;Bio-aide-6 mos $32,423
Fringe @36.5% $11,833
Supplies $18,040
Travel $2,000
Indirect @28.1% $19,471
Subcontractor $5,000
Other Computer and accessories $2,200
$90,967
Total estimated budget
Total FY 2001 cost$90,967
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$90,967
FY 2001 forecast from 2000$72,992
% change from forecast24.6%
Reason for change in estimated budget

Reasons for increase in budget include projected inflationary increases, an increase in manpower-months and state legislated salary increases. The majority of the increase is a result of including 2 months of biologist's salary for the project. The original project proposal included 20 months of personnel time, but was reduced to 14 months for FY2000. The additional biologist time will provide better coordination with other agencies and the University of Idaho, and provide more manpower for field sampling.

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000

Comment:

Reasons for increase in budget from FY 2000 include projected inflationary increases, an increase in manpower-months and state legislated salary increases. The majority of the increase is a result of including two months of biologist's salary for the project. The original project proposal included 20 months of personnel time, but was reduced to 14 months for FY 2000. The additional biologist time will provide better coordination with other agencies and the University of Idaho, and provide more manpower for field sampling. There is no change in the scope of work.
Recommendation:
Fund
Date:
Sep 13, 2000

Comment:


REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$82,913 $82,913 $82,913

Sponsor comments: See comment at Council's website