FY 2004 Within-year Modification proposal 199104600

Section 1. Administrative

Proposal titleSpokane Tribal Hatchery Operation and Maintenance
Proposal ID199104600
OrganizationSpokane Tribe of Indians (STOI)
Proposal contact person or principal investigator
NameTim Peone, Hatchery Program Manager
Mailing addressPOB 100 Wellpinit, WA. 99040
Phone / email(509) 258-7297 / tpeone@aol.com
Manager authorizing this projectTim Peone
Review cycleWithin-year Modification
Province / SubbasinInter-Mountain / Columbia Upper
Short description
Target speciesKokanee Salmon and Rainbow Trout
Project location
LatitudeLongitudeDescription
Stevens County, Washington - 3 miles west of Ford, Washington - 45 miles north of Spokane, Washington - Twonship 28N, Range 39E, Section 23.
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
199104700 Sherman Creek Hatchery and Lake Roosevelt Kokanee Net Pen Rearing Projects Operation of the Spokane Tribal Hatchery compliments a joint artificial production program for Lake Roosevelt and Banks Lake.
199500900 Lake Roosevelt Rainbow Trout Net Pen Projects Operation of the Spokane Tribal Hatchery compliments a joint artificial production program for Lake Roosevelt and Banks Lake.
199404300 Lake Roosevelt Monitoring and Evalution Project Monitors and evaluates of artificial production component of Lake Roosevelt fisheries restoration and enhancement efforts. Provides management recommendations for operating hatcheries.
19901800 Lake Roosevelt Habitat Improvements Operation of the Spokane Tribal Hatchery compliments this Lake Roosevelt fisheries restoration and enhancemen effort.
19950110 Chief Joseph Kokanee Enhancement Project Operation of the Spokane Tribal Hatchery compliments this Lake Roosevelt fisheries restoration and enhancemen effort.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Artificial Production to meet annual release goal of 1.3 million kokanee salmon and 500,000 rainbow trout yearlings. Egg culturing, fry, fingerling and yearling production. In conjunction with cooperative artificial production projects, direct planting and transfer of 800,000 kokanee fingerlings, 500,000 kokanee yearlings and 500,000 rainbow trout fingerlings. per FY'04 $62,982
Plant/transfer 800,000 kokanee fingerlings, 500,000 kokanee yearlings and 500,000 rainbow trout fingerlings. per FY'04 $22,200
Fin clipping 1 million kokanee before release into Lake Roosevelt. per FY'04 $45,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2005FY 2006FY 2007FY 2008
$658,172$608,580$639,000$670,960

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2004 cost
Personnel FTE: July through September Wages $66,094
Fringe July through September Fringe $12,322
Supplies July through September Fish Feed & Supplies $15,860
Travel July through September Travel $288
Capital July through September Indirect $17,245
NEPA July through September Utilities $18,373
$130,182
Total estimated budget
Total FY 2004 cost$130,182
Amount anticipated from previously committed BPA funds$0
Total FY 2004 budget request$130,182
FY 2004 forecast from 2003$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$536,000 $536,000 $536,000

Sponsor comments: See comment at Council's website