Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
Title Type File Size File Date


Section 1. General Administrative Information

Title of Project Proposal Map Subtidal Large Woody Debris and Other Habitat Features in Relation to Fish Distribution in the Lower Columbia River Estuary
BPA Project Proposal Number 30014
Business name of agency, institution,
or organization requesting funding
Battelle Marine Sciences Laboratory
Business acronym (if appropriate) Battelle
 

Proposal contact person or principal investigator

Name Dana Woodruff
Mailing Address Battelle Marine Sciences Laboratory, 1529 West Sequim Bay Rd.
City, State, Zip Sequim, WA 98382
Phone 3606813608
Fax 3606813681
E-mail dana.woodruff@pnl.gov
 
Manager of program authorizing this project Ron Thom, Battelle Marine Sciences Laboratory
 
Review Cycle Columbia Estuary
Province Columbia Estuary
Subbasin Columbia Estuary
 
Short Description Map location and type of large woody debris (LWD) using side scan sonar and quantify conditions where it is most commonly found. Map fish distributions in relation to LWD using underwater video and a DIDSON acoustic camera.
Target Species Snake River Fall Chinook Salmon, Upper Willamette River Chinook Salmon Lower Columbia River Chinook Salmon Columbia River Chum Salmon


Project Location

Latitude Longitude Description
46 11' 19" 123 38' 18" Site 1 South Cathlamet Bay, near Svensen Island
46 12' 39" 123 37' 39" Site 2 Cathlamet Bay, near Seal Island
46 15' 34" 123 35' 45" Site 3 North Cathlamet Bay, near Elliot Point


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

RPA
RPA 158
RPA 159

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Information Transfer

The expected outcomes of this project are:
Indirect

Data generated by this project are:
Derived

Are there restrictions on the use of this data?
None

Where do the data reside?
Private/Managed Locally:

Printed
Electronic

Public Access: [no information]


In what other ways will information from this project be transferred or used?

This data will be merged with selected LCREP GIS hyperspectral imagery habitat classification layers collected as part of the effort to map estuarine habitats along the Lower Columbia River.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
N/A


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
1. Map LWD using side scan sonar a. Planning, site selection 3 $ 18,347  


Outyear Objective-Based Budget

Objective Starting FY Ending FY Estimated cost
1. Map LWD using side scan sonar 2004 2005 $ 42,990
2. Assess density and distribution of fish 2005 2005 $ 54,305


Outyear Budgets for Planning and Design Phase

FY 2004 FY 2005
$ 42,990 $ 54,305


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
1. Map LWD using side scan sonar a. Mobilize and test sonar gear 3 $ 15,155  
b. Collect sonar data at selected sites 3 $ 33,477  
c. Video drops at high LWD locations 3 $ 11,503  
d. Analyze sonar and develop LWD polygons 3 $ 22,755  
e. Assess ands refine sonar and video methods 1 $ 32,833  
2. Assess density and distribution of fish a. Assess with video 3 $ 0  


Outyear Objective-Based Budget

Objective Starting FY Ending FY Estimated cost
1. Map large woody debris using side scan sonar 2004 2004 $ 87,837
2. Assess density and distributin of fish 2005 2005 $ 90,486


Outyear Budgets for Construction and Implementation Phase

FY 2004 FY 2005
$ 87,837 $ 90,486


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
$ 0  
$ 0  
$ 0  
$ 0  


Outyear Objective-Based Budget

Objective Starting FY Ending FY Estimated cost
$ 0
$ 0
$ 0
$ 0


Outyear Budgets for Operations and Maintenance Phase

n/a or no information


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
$ 0  
$ 0  
$ 0  
$ 0  


Outyear Objective-Based Budget

Objective Starting FY Ending FY Estimated cost
$ 0
$ 0
$ 0
$ 0


Outyear Budgets for Monitoring and Evaluation Phase

n/a or no information


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2003 Cost
Personnel FTE: 0.51 Man Years $ 37,747
Fringe $ 9,852
Supplies $ 13,771
Travel $ 3,606
Indirect USDOE/DCAA Approved Indirects $ 56,906
Capital NA $ 0
NEPA NA $ 0
PIT tags # of tags: NA $ 0
Subcontractor NA $ 0
Other Fee $ 12,188
Total Itemized Budget $134,070


Total estimated budget

Total FY 2003 project cost $134,070
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2003 budget request $134,070
FY 2003 forecast from 2002 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2004 2005
Planning and design $ 42,990 $ 54,305
Construction/implementation $ 87,837 $ 90,486
Total Outyear Budgets $130,827 $144,791
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed