Return to Proposal Finder FY 2003 Lower Columbia Proposal 31006

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
Title Type File Size File Date


Section 1. General Administrative Information

Title of Project Proposal Protect Wood's Landing Chum Spawning Site
BPA Project Proposal Number 31006
Business name of agency, institution,
or organization requesting funding
City of Vancouver
Business acronym (if appropriate) Vancouver, WA
 

Proposal contact person or principal investigator

Name Vicky Ridge-Cooney
Mailing Address PO Box 1995
City, State, Zip Vancouver WA 98668
Phone 3606968981
Fax 3606968029
E-mail vicky.ridge-cooney@ci.vancouver.wa.us
 
Manager of program authorizing this project Vicky Ridge-Cooney
 
Review Cycle Lower Columbia
Province Lower Columbia
Subbasin Columbia Lower
 
Short Description Through acquisition of property and easements on 12 acres and 1000 feet of shoreline the project will protect a significant chum spawning site on the mainstem of the Columbia and will also restore the lower 350 feet of the adjacent creek.
Target Species Columbia River chum


Project Location

Latitude Longitude Description
45 35 35 122 31 50 Site is in Vancouver, WA. From I-5 in Vancouver, E on Hwy 14, S on Ellsworth Rd, E on Evergreen Hwy, S across rr at Riverwood Lane, E then S to end of road


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

RPA
157
152
150

Relevant RPAs based upon NMFS & BPA Review

This information comes from National Marine Fisheries Service (NMFS) and Bonneville Power Administration (BPA) reviews of this project proposal. The following table represents BPA & NMFS determinations as to this proposal's relevance to particular Biological Opinion Reasonable and Prudent Alternatives (RPAs).

Reviewing Agency Action Number BiOp Agency Description
NMFS Action 150 NMFS In subbasins with listed salmon and steelhead, BPA shall fund protection of currently productive non-Federal habitat, especially if at risk of being degraded, in accordance with criteria and priorities BPA and NMFS will develop by June 1, 2001.


Information Transfer

The expected outcomes of this project are:
Quantitative
Qualitative

Data generated by this project are:
Primary
Indirect Data

Are there restrictions on the use of this data?
None

Where do the data reside?
Private/Managed Locally:

Electronic

Public Access:
Internet at BPA


In what other ways will information from this project be transferred or used?

[no information]


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
2001 WDFW restored habitat and Duncan Creek and re-introduced chum from Ives Island
2000 Columbia Land Trust acquired properties and easements at Gray's River, Eagle Island, Kalama River, and many other sites


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
Objective 1. Plan acquisition of properties and easements Task 1a. Appraise parcel B and north half of parcel D for fee simple value. 1 $ 10,000 x
Task 1b. Appraise parcels A, C, and south half of D for conservation easement value. 1 $ 15,000 x
Task 1c. Perform baseline inventory of parcels A,B,C,D. 1 $ 2,000  
Task 1d. Assess parcels A, B, C, D for hazardous substances. 1 $ 14,000 x
Task 1e. Assess parcels A, B,C, D for archaeological resources. 1 $ 4,000 x
Task 1f. Carry out NEPA process for acquisition sites. 1 $ 5,000 x
Objective 2. Design Joseph’s Creek restoration. Task 2a. Survey site. 1 $ 10,000 x
Task 2b. Develop engineering plans. 1 $ 15,000 x
Task 2c. Obtain permits. 1 $ 2,000  
Task 2d. Conduct Environmental Assessment including hazards assessment. 1 $ 3,000 x
Task 2e. Carry out the NEPA process for the restoration. 1 $ 2,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2003 cost Subcontractor
Objective 1. Acquire properties and easements Task 1a. Purchase parcel B. 1 $400,000  
Task 1b. Purchase north half and tidelands of parcel D. 1 $360,110  
Task 1c. Purchase easement of Parcel C. 1 $100,000  
Task 1d. Record titles for Parcels A, B, C, D. 1 $ 200  
Task 1e. Pay taxes for all parcels. 1 $ 10,000  
Task 1f. Get title reports for all parcels. 1 $ 6,100  
Task 1g. Pay closing costs for all parcels. 1 $ 800  
Task 1h. Manage the acquisitions. 1 $ 64,350  
Objective 2. Restore the lower 350 feet of Joseph’s Creek to provide additional spawning gravel and stable banks vegetated with native riparian vegetation $ 0  
Task 2a. Excavate sediment. 1 $ 31,600 x
Task 2b. Dewater stream. 1 $ 28,000 x
Task 2c. Control erosion. 1 $ 19,000 x
Task 2d. Mobilize for project. 1 $ 25,000 x
Task 2e. Place spawning rock. 1 $ 96,000 x
Task 2f. Place toe rock. 1 $ 26,000 x
Task 2g. Place stream channel structures. 1 $ 26,000 x
Task 2h. Remove invasive plants, stabilize banks, revegetate. 1 $ 13,000 x
Task 2i. Repair access road. 1 $ 2,200 x
Task 2j. Provide contingency funds. 1 $ 62,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

n/a or no information


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

n/a or no information


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

n/a or no information


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2003 Cost
Supplies $ 2,000
Capital Acqsition costs excluding NEPA $943,560
NEPA $ 28,000
Subcontractor $378,800
Total Itemized Budget $1,352,360


Total estimated budget

Total FY 2003 project cost $1,352,360
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2003 budget request $1,352,360
FY 2003 forecast from 2002 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Organization Item or service provided Amount Cash or In-Kind
Wood family Easement on parcel A $220,000 in-kind
Wood family Easement on south half of parcel D $154,500 in-kind

 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Not applicable