Section 1. General Administrative Information

Title of Project Proposal Critical Ecosystem Reclamation, Recovery and Recharge Project
BPA Project Proposal Number 9042
Business name of agency, institution,
or organization requesting funding
Shoshone-Bannock Tribes
Business acronym (if appropriate) SBT
 

Proposal contact person or principal investigator

Name James M. Reed
Mailing Address P.O. Box 306
City, State, Zip Fort Hall, ID 82302
Phone 2082387721
Fax 2082387663
E-mail jreed@ida.net
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Upper Snake
Subbasin Upper Snake
 
Short Description Utilizing the youth of the Tribe, improve ongoing environmental problems in the upper Mount Putnam drainage basin through active restoration of terrestrial and aquatic systems.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): wildlife


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Renovation of building for Environmental Center to house operations of EnviroCorps. a. Planning and design of renovation.
1. Renovation of building for Environmental Center to house operations of EnviroCorps. b. Renovation
2. Development of EnviroCorps a. Develop curiculum for EnviroCorps.
2. Development of EnviroCorps b. Initiate training of EnviroCorps staff.
2. Development of EnviroCorps c. Train EnviroCorps members in necessary KSA's.
3. Environmental Assesment a. Conduct Environmental Assesment for Ecosystem Project
3. Environmental Assesment b. Scope project.
4. Begin EnviroCorps Pollution Prevention Program a. Educate public as to goals of the EnviroCorps and the Ecosystem Project through EcoNews.
5. Begin EnviroCorps Field Work a. BeginEnviroCorps work on Ecosystem Project.
6. Monitor and disseminate results a. Publish results through EnviroCorps "EcoNews."
7. Award scholarships a. EnviroCorps Members receive scholarships.
8. Begin FY2000 cycle. a. Planning for FY2000 according to adaptive management.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 01/01/99 03/01/99 10.0%
2 01/01/99 03/01/99 3.0%
3 01/01/99 06/01/99 5.0%
4 05/01/99 12/01/03 5.0%
5 05/01/99 12/01/03 60.0%
6 05/01/99 12/01/03 5.0%
7 08/01/99 08/01/03 10.0%
8 12/01/99 12/01/03 2.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 54,500
Fringe $ 15,550
Supplies $ 20,000
Operating $ 15,000
Capital $118,000
Travel $ 3,100
Indirect $ 17,410
Subcontractor $ 0
Other $ 23,000
Total Itemized Budget $266,560


Total estimated budget

Total FY 1999 project cost $266,560
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $266,560
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $175,560 $175,560 $175,560 $175,560
Total Outyear Budgets $175,560 $175,560 $175,560 $175,560
 

Other Budget Explanation

Schedule Constraints: None anticipated.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

The goal of the Shoshone-Bannock Critical Ecosystem Reclamation, Recovery and Recharge Project is to restore the upper Mount Putnam drainage basin while empowering future Tribal leaders through a new program called EnviroCorps. Overgrazing, mining and off road vehicle usages have degraded this systems ability to support wildlife crucial to Indian ways. Through a series of phases, the EnviroCorps will reclaim and restore critical riparian areas, re-establish self-sustaining fish populations and re-introduce beaver populations (and impoundments) to recharge the ground water in the Mount Putnam area. While accomplishing the goals of this project, the young people will gain experiences/knowledge which aid in life direction, self-esteem and spiritual fulfillment. This approach to educating youth, while solving environmental problems, is a proven success in Salmon Corps. This project will involve four phases. Phase one includes conducting an EA, soliciting the educating the Tribal membership and developing the EnviroCorps program. The main components of phase one should be accomplished by the end of FY99. The second phase, restores the lowest order streams and springs of the basin on a priority basis. Phase three focuses on the riparian areas of the higher order streams. Phases two and three will be ongoing in nature, completion dates will vary. Priority phase two projects should be near completion by FY2000; priority phase three projects by FY2003.Phase four will establish a monitoring/maintenance program. EnviroCorp will assume these tasks under the direction of the Environmental Program. Project accomplishments and results will be reported in EcoNews.