Section 1. General Administrative Information

Title of Project Proposal Propagate Native Plant Species for Revegetation & Riparian Restoration Proj
BPA Project Proposal Number 9085
Business name of agency, institution,
or organization requesting funding
USFS, Wallowa-Whitman National Forest, La Grande Ranger District
Business acronym (if appropriate) USFWS
 

Proposal contact person or principal investigator

Name Penny Hall
Mailing Address 3502 Hwy. 30
City, State, Zip La Grande, OR 97850
Phone 5419628558
Fax 5419628580
E-mail
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Snake
Subbasin Grande Ronde
 
Short Description Develop diverse species program for La Grande Ranger District. Collect seed and cuttings from several native plant species, and propagate materials to be used in revegetation and restoration projects
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Collect appropriate plant material for propagation (seeds or cuttings). a. Identify species desired and appropriate material and time for collection.
1. Collect appropriate plant material for propagation (seeds or cuttings). b. Survey, locate and map collection sites.
1. Collect appropriate plant material for propagation (seeds or cuttings). c. Collect propagation material from identified sites, at appropriate time (approximately June through December).
1. Collect appropriate plant material for propagation (seeds or cuttings). d. Send collected materials to nursery (Forest Service or Private) for cleaning, seed extraction, and storage).
2. Propagate plant materials to specified size and type. a. Sow and propagate materials at nursery.
2. Propagate plant materials to specified size and type. b. Coordinate with CTUIR Botanist and Nursery Program Manager
2. Propagate plant materials to specified size and type. c. Request lift, pack and delivery from nursery.
3. Outplant desired revegetation materials for project, ongoing at La Grande Ranger District. a. Plant 80 (1999) acres riparian habitat using approved techniques and appropriate plant material
3. Outplant desired revegetation materials for project, ongoing at La Grande Ranger District. b. Plant 10 acres of disturbed areas and seed 10 miles obliterated road, using approved techniques and appropriate plant materials.
4. Provide protection measures a. Determine need and type of measures for project maintenance.
5. Determine growth and survival a. Suvival monitoring, transects and photo points

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 06/01/98 11/01/01 25.0%
2 10/01/98 04/01/02 40.0%
3 04/01/99 05/01/03 20.0%
4 05/01/99 06/01/03 5.0%
5 05/01/00 10/01/04 10.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 10,900
Supplies $ 500
Travel $ 500
Indirect $ 6,142
Subcontractor $ 29,050
Total Itemized Budget $ 47,092


Total estimated budget

Total FY 1999 project cost $ 47,092
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $ 47,092
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $ 86,810 $ 85,000 $ 80,000 $ 75,000
Total Outyear Budgets $ 86,810 $ 85,000 $ 80,000 $ 75,000
 

Other Budget Explanation

Schedule Constraints: Scheduling constraints could be determined by crop failure (seed production) or other weather related delays.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

This project will promote the use of adapted, native stock for revegetation and restoration work. Obtaining sufficient supplies of genetically diverse, high quality native seed or vegetative plant materials, which are locally adapted, is not possible at this time. Availability of native seed or plant material is limited and current nursery stock of native species is not adequate for the needs of the district. It is important to establish a program that supplies a reliable source for desirable materials. This project will facilitate the revegetation needs of the district, promote the use of adapted native vegetation, and help to maintain the native flora and biodiversity of forest, rangeland and aquatic ecosystems. This project will be invaluable in determining better approaches to riparian and native vegetation restoration projects for riparian areas and aquatic habitat in the Snake River Basin for summer steelhead and spring/summer chinook salmon. This project will be ongoing.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page