Section 1. General Administrative Information

Title of Project Proposal Restore West Fork Little Bear Creek For Steelhead
BPA Project Proposal Number 9118
Business name of agency, institution,
or organization requesting funding
Palouse-Clearwater Environmental Institute
Business acronym (if appropriate) PCEI
 

Proposal contact person or principal investigator

Name Thomas C. Lamar
Mailing Address P.O. Box 8596
City, State, Zip Moscow, ID 83843
Phone 2088821444
Fax 2088828029
E-mail lamar@pcei.org
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Snake
Subbasin Clearwater
 
Short Description Restoring natural/wild steelhead/rainbow trout to the upper reaches of the West Fork of Little Bear Creek will be accomplished through the biophysical restoration of those reaches of the West Fork of Little Bear Creek that have been urbanized.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 7.6, 7.8D.2
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Reduce width/depth ratio a. Stream assessment
. b. Design stable cross section
. c. Model with HEC-2 hydraulic model to determine floodway impacts
2. Increase sinuosity a. Stream assessment
. b. Design meander width
. c. Model with HEC-2 hydralic model to determine extent of flooding
3. Reestablish a riffle/pool spacing of one half a meander wavelength a. Stream assessment
. b. Determine by meader wavelength
. c. Model with HEC-2 hydralic model to determine flood elevations
4. Reconnect the active channel with a constructed functional floodplain a. Permitting
. b. Bidding
. c. Construction
5. Stabilize eroding streambanks with habitat improvement structures a. Stream assessment
. b. Determine appropiate structures
. c. Install sturctures after earthmoving is complete
. d. Install erosion control products to help with herbaceous vegetation establishment
6. Reestablish native woody and herbaceous plant community a. Stream assessment
. b. Determine native plant community
. c. Plant herbaceous plants immediately after earthmoving
. d. Plant woody plants the following spring

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 10/01/98 03/01/99 7.0%
2 10/01/98 03/01/99 7.0%
3 10/01/98 03/01/99 7.0%
4 03/01/99 10/01/99 60.0%
5 08/01/99 11/01/99 10.0%
6 09/01/99 06/01/00 9.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel Coordination staff $ 40,000
Fringe $ 8,000
Supplies Geotextiles, Plants, Revetments $100,000
Travel Local Travel $ 2,000
Indirect %10 $ 47,000
Subcontractor Terragraphics Environmental Engineering; City of Troy $ 20,000
Other $300,000
Other $300,000
Total Itemized Budget $817,000


Total estimated budget

Total FY 1999 project cost $817,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $817,000
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $ 50,000 $ 20,000 $ 20,000 $ 10,000
Total Outyear Budgets $ 50,000 $ 20,000 $ 20,000 $ 10,000
 

Other Budget Explanation

Schedule Constraints: Permitting


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

Restoring natural/wild steelhead/rainbow trout to the upper reaches of the West Fork of Little Bear Creek will be accomplished through the biophysical restoration of those reaches of the West Fork of Little Bear Creek that have been urbanized. This goal is in concert with the 1994 Fish and Wildlife Program and recommendations of the Columbia River Inter-Tribal Fish Commission (CRITFC) and the Columbia Basin Fish and Wildlife Authority (CBFWA) contained within the document. Objectives include: Restoring natural/wild steelhead/rainbow trout populations to upper reaches of the West Fork of Little Bear Creek; Restoring anadromous and resident fisheries habitat on the West Fork of Little Bear Creek through the City of Troy, ID.; Reducing width/depth ratio; Increasing sinuosity; Reestablish a riffle/pool spacing of one half a meander wavelength; Reconnect the active channel with a constructed functional floodplain; Stabilize eroding streambanks with habitat improvement structures; Reestablish native woody and herbaceous plant community. Project scope includes design, engineering, and construction of a biophysical restoration. The design methodology used will adhere to Rosgen’s River Restoration Principles (Rosgen, 1996)