Section 1. General Administrative Information

Title of Project Proposal Power/Repay O&M For USBR CPR Pumping Project
BPA Project Proposal Number 198902700
Business name of agency, institution,
or organization requesting funding
PPL/UECA
Business acronym (if appropriate) PPL/UECA
 

Proposal contact person or principal investigator

Name
Mailing Address
City, State, Zip
Phone
Fax
E-mail
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Mid-Columbia
Subbasin Umatilla
 
Short Description
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

n/a or no information

Objective Schedules and Costs

n/a or no information

Itemized Budget

Item Note FY 1999 Cost
Subcontractor $ 0
Total Itemized Budget $ 0


Total estimated budget

Total FY 1999 project cost $ 0
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $ 0
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Not applicable


Section 6. References

n/a or no information


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$500,000 $500,000 $500,000
Comment:
Added pending NPPC/BPA approval; Need proposal

ISRP Review , ISRP 1998-1 Recommendation:
No proposal submitted.
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$1,000,000
FY06 NPCC Staff Preliminary:
$1,000,000
FY06 NPCC July Draft Start of Year:
$1,000,000
Sponsor (BPA) Comments (Go to Original on NPCC Website):

Return to top of page