Section 1. General Administrative Information

Title of Project Proposal Lake Creek Land Acquisition and Enhancement
BPA Project Proposal Number 199004401
Business name of agency, institution,
or organization requesting funding
Coeur d’Alene Tribe
Business acronym (if appropriate) CDA Tribe
 

Proposal contact person or principal investigator

Name Kelly Lillengreen
Mailing Address P.O. Box 408
City, State, Zip Plummer, ID 83851
Phone 2086865302
Fax 2086863021
E-mail kellylil@iea.com
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Upper Columbia
Subbasin Coeur d'Alene
 
Short Description Purchase and enhance 70 acres of emergent wetlands, 180 acres of forested/riparian wetlands, and 1850 acres of adjacent upland forest and shrub communities. Protects and enhances a key watershed on the Reservation; complements ongoing fisheries work.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: Sections 11.3.F.3, 10.8.B, 10.8.B.20, 10.8B.21
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): wildlife


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
9004400 Implement Fisheries Enhancement Opportunities Coeur d’Alene Reservation Project focuses on protection and restoration in four key watersheds on the Reservation. Lake Creek is one of these drainages. Complements existing resident fish habitat restoration work. No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Purchase 2,100 acres in the Lake Creek Drainage a. Conduct necessary coordination activities to secure title to property; includes but is not limited to negotiations with land owner, complete necessary NEPA documents, etc.
. b. HEP analysis to determine HUs for wildlife crediting issues
. c. Develop mitigation plan, HU contract with BPA
2. Enhancement, Operation and Maintenance of property a. Design and implement enhancement projects including such things as riparian and upland planting, etc.
. b. Develop long term O & M contract

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 10/01/97 06/01/99 90.0%
2 06/01/99 09/01/00 10.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 28,000
Fringe $ 8,400
Operating also includes projected enhancement costs $120,000
Travel $ 5,000
Indirect 31.6% minus capital and subcontracts $ 51,002
Subcontractor Not determined yet\ $ 0
Total Itemized Budget $212,402


Total estimated budget

Total FY 1999 project cost $212,402
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $212,402
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $200,000 $200,000 $200,000 $200,000
Total Outyear Budgets $200,000 $200,000 $200,000 $200,000
 

Other Budget Explanation

Schedule Constraints: Negotiation of purchase price may be a constraint


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

Project proposes the acquisition of approximately 2,100 acres in the Lake Creek Watershed. The focus of the project is the enhancement and conservation of high value habitat for species which were affected by construction and operation of Albeni Falls. Acquisition is intended to complement ongoing stream restoration work and establishes a precedent for watershed management efforts on the reservation. BPA will receive wildlife credit for approximately 760 habitat units (preliminary estimate) as a result of acquisition of high value wetlands habitat. Additional habiat units will be gained as a result of susbequent enhancement efforts. Enhancement and protection of riparian and upland areas will provide measurable improvements in channel stability, sediment abatement, water quality, and habitat suitability for wildlife and fish. Benefits to wildlife under the mitigation plan address habitat losses attributed to Construction of Albeni Falls. Benefits to resident fish will mitigate for Coeur d’Alene Tribal subsistence losses related to construction and operation of Grand Coulee Dam.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$186,083 $200,000 $200,000
Comment:
Operations and maintenance budget reduced because acquisition is not completed

ISRP Review , ISRP 1998-1 Recommendation:
Adequate
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:
This proposal is well organized and gives important details for judging its value to the fish and wildlife program: specific parcels of land appear to have been selected for acquisition, the focus of activities is on riparian habitat, and benefits to both fish and wildlife are listed. However, the methods for restoration are not well described and the proposal is inconsistent on objectives and budget. The budget for land acquisition appears not to be included.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$160,020
FY06 NPCC Staff Preliminary:
$160,020
FY06 NPCC July Draft Start of Year:
$160,020
Sponsor (Coeur D'Alene Tribe) Comments (Go to Original on NPCC Website):

Sponsor (Coeur D'Alene Tribe) Comments (Go to Original on NPCC Website):

Return to top of page