Section 1. General Administrative Information

Title of Project Proposal Burlington Bottoms Wildlife Mitigation Project
BPA Project Proposal Number 199107800
Business name of agency, institution,
or organization requesting funding
Oregon Department of Fish and Wildlife
Business acronym (if appropriate) ODFW
 

Proposal contact person or principal investigator

Name Sue Beilke
Mailing Address 17330 SE Evelyn St.
City, State, Zip Clackamas, OR 97015
Phone 5036572000
Fax 5036572050
E-mail sbeilke@Europa.com
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Columbia
Subbasin Willamette
 
Short Description Maintenance and enhancement activities for wildlife habitat are being conducted by the Oregon Department of Fish and Wildlife, in order to meet the goals and objectives of the management plan, which includes protection of native fish and wildlife species
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 11.3F.1
FWS/NMFS Biological Opinion Number(s) which this project addresses: N/A
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): wildlife


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
92059 Willow Creek Mitigation Project Wildlife mitigation project under Council’s program managed by the Nature Conservancy in southern Willamette Valley No
5519500 Willamette Basin Project Willamette Basin acquisition targets acquisition of critical fish and wildlife habitat in Willamette Basin No
9565 Assessing OR Trust Agreement Using Gap Analysis Tool used to analyze and rank potential projects in Basin for implementation. No
9284 OR Trust Agreement Planning Project Methods developed for assembling trust agreement and list of potential projects. No
9705900 Securing Wildlife Mitigation Sites - Oregon Umbrella project which provides project location, priority, and data tracking. No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Maintain and enhance wildlife habitat. a. Includes control and/or removal of non-native plant populations, and planting of native plant species.
2. Gather information on certain wildlife species and habitat use; this information will be helpful in directing enhancement activities. a. Survey and monitor certain wildlife species, including neotropical migratory songbirds and amphibians (i.e. red-legged frog), including habitat use, etc.
. b. Describe and document condition of habitat types used by species included in task a.
3. Continue interim custodial management and oversight of the area. a. Conduct weekly visits to site; monitor off-site activities which may affect on-site water quality, etc (i.e. quarry opeations, etc.).
1. b. Replace burned timber bridge in order to access east portion of property to conduct enhancement activities.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 06/01/98 10/01/99 80.0%
2 05/01/98 11/01/99 5.0%
3 01/01/98 12/01/99 15.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 27,000
Fringe $ 10,260
Supplies Includes purchase of native plants. $ 3,000
Operating Includes hiring of field crews. $ 4,000
Travel Mileage reimbursement for personnel and volunteers $ 2,500
Indirect Overhead $ 10,755
Subcontractor $ 0
Other $ 57,515
Total Itemized Budget $115,030


Total estimated budget

Total FY 1999 project cost $115,030
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $115,030
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $ 62,000 $ 65,000 $ 68,000 $ 71,000
Total Outyear Budgets $ 62,000 $ 65,000 $ 68,000 $ 71,000
 

Other Budget Explanation

Schedule Constraints: Anticipated constraints include 1) delays in scheduling enhancement work due to unavailability of field crew(s); and 2) no access to a particular area due to flood conditions.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

Burlington Bottoms was purchased in 1991 by the BPA to mitigate for wildlife habitat losses in the Willamette Basin of the lower Columbia River Basin. Overall project goals and objectives include: 1) the maintenance and enhancement of wildlife habitat typical of that found in the Willamette and lower Columbia River basins; 2) maintaining a diversity of fish and wildlife and fish and wildlife habitat typical of a riverine floodplain; 3) maintain or improve water quality; and 4) meet BPA’s obligation under provisions of the Pacific NW Electric Power Planning and Conservation Act of 1980. The methods used to control non-native invasive plant populations include the use of mechanical equipment such as a field mower in upland habitats, and manpower supplied by field crews to assist in the hand removal of non-native plant species. In addition, the installation of a water control structure is being considered in order to control water levels to flood out invasive non-native plant species such as reed canary grass. Coordination with other agencies, groups, etc. will also continue in order to share information and explore all avenues for new methods to carry out enhancement work. The expected outcome from the above proposed methods includes: 1)the enhancement of wildlife habitat, with a resulting increase in habitat units as projected in the habitat evaluation (HEP) completed in 1993 (see separate report titled “Burlington Bottoms Habitat Evaluation”, prepared by ODF&W, August, 1993); and 2) the site is maintained according to direction from the management plan. Enhancement projects began in 1996, with projects being carried out on a yearly basis, and are expected to be completed by fiscal year 2001, at which time operations and maintenance of the habitat would ensure the maintenance of existing habitat values over the lifetime of the project. Results of the enhancement activities will be evaluated and monitored by 1) conducting a modified HEP in order to analyze changes in habitat units over time, 2) analyzing species presence and occurrence both before, during, and after project implementation in response to habitat enhancement (methods used include point count surveys and monitoring and mist netting), and 3) evaluate cost effectiveness of comparative methodologies used during the implementation phase.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$ 58,000 $ 62,000 $ 65,000
Comment:
Error in original project proposal. $58,000 is correct request

ISRP Review , ISRP 1998-1 Recommendation:
Inadequate proposal, adequate purpose
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:
The project has been ongoing for 5 years, so they should describe what they have learned from past actions and how this will affect future actions. It is good that they mention monitoring for biodiversity, but they do not present specifics on results measured to date.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$100,445
FY06 NPCC Staff Preliminary:
$100,445
FY06 NPCC July Draft Start of Year:
$100,445
Sponsor (ODFW) Comments (Go to Original on NPCC Website):

Sponsor (ODFW) Comments (Go to Original on NPCC Website):