Section 1. General Administrative Information

Title of Project Proposal Idaho Model Watersheds Admin./Impl. Support
BPA Project Proposal Number 199202603
Business name of agency, institution,
or organization requesting funding
Idaho Soil Conservation Commission
Business acronym (if appropriate) ISCC
 

Proposal contact person or principal investigator

Name Biff Burleigh
Mailing Address P.O. Box 83720
City, State, Zip Boise, ID 83720-0083
Phone 2083328652
Fax 2083342386
E-mail bburleig@agri.state.id.us
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Snake
Subbasin Salmon
 
Short Description Provide basis of coordination & cooperation between local, private, state, tribal, federal fish & land managers, users & owners & other affected entities to manage the biological social & economic resources to protect, restore, enhance fish habitat.
Target Species Chinook salmon and steelhead


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Coordinate activities for fish habitat maintenance, enhancement and restoration. a. Meet regularly with SWCD boards and Advisory and Technical Committees to plan, approve and implement projects.
2. Coordinate activities that keep people involved in the Model Watershed process. a. Conduct and participate in tours and seminars to further education of local participants.
3. Work with groups and individuals in the Upper Salmon Basin to investigate expansion of the MWP. a. Meet with groups in the Upper Salmon Basin to assist with work and projects.
4. Document historical development and implementation of MWP. a. Maintain and update progress with photos and narrative on regular basis. Follow through with all aspects of project implementation to enhance fish habitat.
. .
. .

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 01/01/99 12/01/99 40.0%
2 01/01/99 12/01/99 30.0%
3 01/01/99 12/01/99 10.0%
4 01/01/99 12/01/99 20.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 69,000
Fringe $ 23,000
Supplies $ 24,000
Operating $ 3,600
Travel $ 9,000
Indirect $ 15,900
Subcontractor $ 25,000
Other $ 5,500
Total Itemized Budget $175,000


Total estimated budget

Total FY 1999 project cost $175,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $175,000
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $175,000 $175,000 $180,000 $185,000
Total Outyear Budgets $175,000 $175,000 $180,000 $185,000
 

Other Budget Explanation

Schedule Constraints: No constraints exist at this time. General project designs and draft approvals are in place.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

The Model Watershed Project (MWP) was initiated by the Northwest Power Planning Council in 1992 to improve chinook salmon and steelhead habitat in the Lemhi, Pahsimeroi, and East Fork of the Salmon River watersheds. These watersheds provide habitat for approximately 75% of the upper Salmon River anadromous fish. The goal of the project is to maintain, enhance, and restore anadromous and resident fish habitat while also achieving and maintaining a balance between resource protection and resource use on a holistic watershed management basis. This project is administered through The Idaho Soil Conservation Commission and is coordinated through the Idaho Model Watershed Project Advisory and Technical Committee in conjunction with the Lemhi and Custer Soil and Water Conservation Districts and various local, state and federal agencies. Additionally, the MWP provides a foundation for other groups such as the Lemhi County Riparian Habitat Conservation Agreement, Custer County Salmon River Conservation Plan, Idaho DEQ Basin and Watershed Advisory Groups, Bureau of Reclamation Water Conservation Program, IDFG screen program and others. The goal of the project is to maintain, enhance, and restore anadromous and resident fish habitat while also achieving and maintaining a balance between resource protection and resource use on a holistic watershed management basis. Specific habitat goals, as outlined in the Model Watershed Plan, (1995). The coordination and administration currently funded by BPA is essential to the continuation of habitat and migration enhancement project work in the Upper Salmon River Basin along with being the glue which holds the community together with responsible resource management. This work can only happen with the cooperation of local communities, SWCD’s, private landowners, NRCS, IDFG, BLM, USFWS, BoR, USFS, Tribes, NMFS, BPA and others.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA: Watershed Technical Group Comments Recommendation:
Return to Sponsor for Revision
Date:
May 13, 1998
[There are no budget numbers associated with this review.]
Comment:
Technical Issue: Provide more specifics on the specific measurable objective and expected results, and how these are tied to the overall goal of this project.

Technical Issue: Explain specifically what the staff will do?

Technical Issue: Explain the subcontract budget in context with the rest of the proposal.


CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$175,000 $175,000 $175,000
Comment:

ISRP Review , ISRP 1998-1 Recommendation:
Adequate after revision
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:
The original proposal was poor, giving inadequate description of benefits to fish and wildlife. The revised proposal described monitoring in greater depth, but still has only marginally adequate description of methods. 9202603 and 9401700 are linked and should be combined for project review.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$356,458
FY06 NPCC Staff Preliminary:
$356,458
FY06 NPCC July Draft Start of Year:
$356,458
Sponsor (ISCC/IOSC) Comments (Go to Original on NPCC Website):

Return to top of page