Section 1. General Administrative Information

Title of Project Proposal Billy Shaw Wetlands catch and release fishery O&M
BPA Project Proposal Number 199501500
Business name of agency, institution,
or organization requesting funding
Shoshone-Paiute Tribes
Business acronym (if appropriate) SBT
 

Proposal contact person or principal investigator

Name Guy Dodson Sr.
Mailing Address P.O. Box 219
City, State, Zip Owyhee, NV 89832
Phone 2087593246
Fax 2087593248
E-mail
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Upper Snake
Subbasin Owyhee
 
Short Description Enhance & develop Billy Shaw tributaries, restore to once pristine condition; partial wages for temp. employee to keep lake & campgrounds clean, pollution-free.
Target Species rainbow trout wildlife


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): resident


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Maintenance of wetlands area a. hire part-time employee
2. Protect wetlands from pollution and degradation a. pick up debris and littler
. b. maintain fence around wetlands area
3. Protect spawning streams a. renaturalize streams (logs, gravel, trees)

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 03/01/99 02/01/00 30.0%
2 03/01/99 02/01/00 30.0%
3 03/01/99 02/01/00 40.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 70,000
Supplies $ 75,000
Operating $ 38,500
Indirect $ 66,500
Subcontractor $ 0
Total Itemized Budget $250,000


Total estimated budget

Total FY 1999 project cost $250,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $250,000
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $250,000 $250,000 $250,000 $250,000
Total Outyear Budgets $250,000 $250,000 $250,000 $250,000
 

Other Budget Explanation

Schedule Constraints: Only constraints will be problems in finding part time worker. Likely will not be a major problem.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

The purpose of this Operation and maintenance (O&M) money is to enhance and develop the Billy Shaw Wetlands fishery area as a trophy catch and release fishery. The O&M will include maintaining the area as a high quality camping and fishing area in the West. Trash and litter will be picked up weekly to prevent pollution of the new lake. Interpretive signs will be updated and maintained to instruct anglers and campers of regulations. This money will be used for our initial stocking of fish in the lake and to help keep the riparian areas of the spawning streams feeding into the lake in high quality condition (planting trees, shrubs, willows). This lake will become a self supporting fishery with the trout spawning in the streams feeding the lake. Maintenance will be needed on these streams to protect them from degradation and maintain high water quality. Fish screens will also need to be maintained to prevent entrance of non-game fish into the new lake. Water quality of the lake and streams will be measured throughout the year, and habitat condition evaluated twice a year..


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA: Resident Fish Review Comments Recommendation:
Fundable if funds available
Date:
May 13, 1998
[There are no budget numbers associated with this review.]
Comment:
Presentation: Reservoir construction should begin this begin this spring. FY 99 money is for operation and maintenance plus habitat work (fences, fish screens, monitoring water quality before fish come in, public education, catch-and-release). Fish for the reservoir are expected to come from the Joint Culture Facility (9500600) but if that doesn't work, then there is money in the FY 99 budget for fish from another source. At this point we are not sure which species will be stocked in the reservoir. The project also includes some tributary habitat work to generate natural production to support a self-sustaining system. We may not spend all of the $250,000 this year.

Questions/Answers:

There was a large amount of carry forward from previous years, what will it cover? Answer: Those funds cover the construction of the reservoir and have nothing to do with fish production.

Will the fish screens stay in place? Answer: Yes, they will not be washed out during run-off.

What percent of the budget is for the park? Answer: This funding will not be used to develop a campground. It will be used to maintain the reservoir, keep debris out of the reservoir (maintain water quality), clean up the access sites, and clean up after campers.

Are these activities consistent with the Council's Program? Answer: Yes, this addresses the measure.

Is the project committed to stocking redband trout? Answer: Our focus is on weak but recoverable stocks rather than on production.

How many tributaries enter Billy Shaw Reservoir? Answer: Two perennial streams and 2-3 intermittent streams.

Are the site evaluations done? Answer: Yes.

Screening Criteria: Yes

Technical Criteria: No. Tasks are not clearly aligned with program. Trash removal (1/3 of costs) is not a BPA responsibility.

Programmatic Criteria: No. Project does not satisfy criteria 12, 13, and 14.

General Comment: Project needs closer coordination and consolidation of objectives and tasks with 9701100, 9020, and 8815600.


CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$215,000 $250,000 $250,000
Comment:
Deferred fish stocking task

ISRP Review , ISRP 1998-1 Recommendation:
Inadequate
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:
This proposal is disjointed. Proposed work ranges from protecting and enhancing wetlands to cleaning campgrounds and stocking undetermined fish species. The plan to develop a sport trophy fishery is shaky, particularly because the fish species to be used has not been selected. Do the proposers know that native fishes (trout and others) are not already present? The need for the project is not demonstrated. The planned stream habitat techniques are questionable. The combination of habitat work and stocking is not well related or well justified and appears to be questionable. The ISRP believes the proposed work could be harmful to native fish and is not biologically supportable.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$456,899
FY06 NPCC Staff Preliminary:
$456,899
FY06 NPCC July Draft Start of Year:
$456,899
Sponsor (Shoshone Paiute Tribe) Comments (Go to Original on NPCC Website):