Section 1. General Administrative Information

Title of Project Proposal Protecting and Restoring the Squaw and Papoose Creek Watersheds
BPA Project Proposal Number 199607703
Business name of agency, institution,
or organization requesting funding
Nez Perce Tribal Fisheries/Watershed Management Program
Business acronym (if appropriate) NPT
 

Proposal contact person or principal investigator

Name Ira Jones
Mailing Address P.O. Box 365
City, State, Zip Lapwai, ID 83540
Phone 2088437406
Fax 2088437322
E-mail iraj@nezperce.org
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Lower Snake
Subbasin Clearwater
 
Short Description PROTECTING AND RESTORING THE SQUAW AND PAPOOSE CREEK WATERSHEDS IS THE OVERALL GOAL OF THIS PROJECT. WE WILL ACHIEVE THIS WORKING WITHIN AN OVERALL WATERSHED APPROACH, COMPLETING FOUR OBJECTIVES IN MANY AREAS OF THE WATERSHED.
Target Species Fall Chinook, Coho, Resident Fish (Bull Trout, Cut Throat)


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: Section 7.1 - Ensuring Biodiversity; Section 7.6 - Habitat Goals, Policies, and Objectives; Section 7.7 - Cooperative Habitat Protection and Improvement with Private Landowners; Section 7.8 - Implement State, Federal, and Tribal Habitat Improvements
FWS/NMFS Biological Opinion Number(s) which this project addresses: THE CLEARWATER AND NEZ PERCE NATIONAL FOREST HAVE COMPLETED A BIOLOGICAL ASSESSMENT FOR ACTIVITIES AFFECTING STEELHEAD TROUT. THE NATIONAL MARINE FISHERIES SERVICE IS PRESENTLY PREPARING THE BIOLOGICAL OPINION, WHICH WILL BE COMPLETED IN JANUARY, 1998.
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
83350 NEZ PERCE TRIBAL HATCHERY WATERSHED PROTECTION AND RESTORATION FOR ANADROMOUS AND RESIDENT FISH. No
970600 NEZ PERCE TRIBE FOCUS WATERSHED PROGRAM FOCUS PROGRAM IS CO-COORDINATED BETWEENM NPT AND STATE OF IDAHO. No
9608600 IDAHO SOIL CONSERVATION COMMISSION FOCUS WATERSHED PROGRAM FOCUS PROGRAM IS CO-COORDINATED BETWEEN NPT AND STATE OF IDAHO. No
9809802 SALMON SUPPLEMENTATION IN IDAHO RIVERS. WATERSHED PROTECTION AND RESTORATION FOR ANADROMOUS AND RESIDENT FISH. No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Alleviate Sediment Input from Road Sources in the Squaw and Papoose Creek Watersheds. a. Coordinate with the Clearwater National Forest (CNF) on 12 miles of road to be obliterated.
. b. Obliterate roads.
. c. Revegetate obliterated roads with native plant species.
. d. Monitor and evaluate obliterated roads for blow-outs, vegetation growth, and soil stabilization.
. e. Complete report on effects of road obliteration on the affected watershed over time.
2. Abate potential for immediate sediment and delivery. a. Coordinate with Clearwater National Forest on areas of deposited sediment within riparian areas that have the potential for adding sediment in the near term.
. b. Construct sediment fences, mulch and re-seed sediment areas to stabilize soils.
3. Stabilize existing landslides. a. Coordinate with Clearwater National Forest on landslide areas needing stabilization
. b. Stabilize landslides by installing check dams, mulching and re-vegetating.
4. Operation and maintanence (O&M) of sediment fences, check dams, and the re-vegetation associated with them that was completed in previous years. a. Observe and evaluate the sediment fences, check dams, and associated re-vegetation for any problems that will discourage them from accomplishing their original goals.
. b. Perform required work to enable sediment fences and check dams to accomplish their original goals.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 07/01/99 11/01/99 85.0%
2 07/01/99 07/01/99 5.0%
3 07/01/99 07/01/99 5.0%
4 08/01/99 08/01/99 5.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 58,525
Fringe $ 8,546
Supplies $ 1,263
Operating COSTS ABSORBED IN REST OF TABLE. $ 0
Travel $ 23,176
Indirect $ 29,398
Subcontractor Clearwater Nat’l Forest; Earth Conservation Corps/Salmon Corps at Nez Perce $111,616
Other $ 9,169
Other $ 9,169
Total Itemized Budget $250,862


Total estimated budget

Total FY 1999 project cost $250,862
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $250,862
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $265,862 $ 39,879 $ 43,867 $ 48,254
Total Outyear Budgets $265,862 $ 39,879 $ 43,867 $ 48,254
 

Other Budget Explanation

Schedule Constraints: EXISTING SCHEDULES FOR THE 1999 BUDGET YEAR MAY CHANGE DUE TO WEATHER CONDITIONS. ALL ON-THE-GROUND PROJECTS OCCUR IN MOUNTAINOUS AREAS AT ELEVATIONS UP TO 5500 FEET ABOVE SEA LEVEL, WHERE UNPREDICTABLE WEATHER PATTERNS MAY OCCUR.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

Protecting and restoring the Squaw and Papoose Creek Watersheds to assist in increasing anadromous fish populations is the overall goal of this project. We will achieve this working within an overall watershed approach, completing four objectives in many areas of the watersheds. The first objective is road obliteration, which is a priority activity within the watersheds to reduce sediment delivery into streams. Monitoring and evaluation (M&E) will be completed and a report produced researching how road obliteration has decreased sediment loads into the streams over time. The second objective is abating the potential for immediate sediment delivery into streams from identified areas of deposited sediment within riparian areas. Stabilizing landslides is the third objective to reduce potential for contributing sediment. The fourth objective in the proposal is operation & maintenance (O&M) of structures constructed in previous years in the effort to reduce sediment into steams. These structures include check dams, sediment fences, and the re-vegetation associated with them. The expected outcome of our work will decrease sediment loads into streams and tributaries within the watersheds, which will in turn increase available fish and wildlife habitat, assist in enlarging their populations, and protect Nez Perce tribal treaties and culture.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA: Watershed Technical Group Comments Recommendation:
Return to Sponsor for Revision

Date:
May 13, 1998
[There are no budget numbers associated with this review.]
Comment:
Management Issue: Management flag – concern about the "in-lieu" issue and the delegation of funding responsibility. The Forest Service should fund some of this work because their activities caused many of the problems.

Technical Issue: Explain how placing logs and backfill reduces surface erosion.

Technical Issue: Explain how the action proposed by this technique will not cause another failure?

Technical Issue: Explain how the costs are not excessive for road obliteration.


CBFWA Funding Recommendation Recommendation:
Fund
Date:
May 13, 1998
1999 2000 2001
$241,693 $265,862 $ 39,879
Comment:

ISRP Review , ISRP 1998-1 Recommendation:
Adequate
Date:
Jun 18, 1998
[There are no budget numbers associated with this review.]
Comment:
These proposals (199607703 and 199607707) adequately describe the problems and the likely benefits to fish and wildlife. However, each also has some negative aspects, as detailed below. The proposals do not tell how reduction in sediment delivery will be measured. BPA should look at the budget. Is this cost sharing for BPA when Forest Service and NPT do the work and BPA is the funding source for both. It appears that in 1998, $109,328 will be spent to obliterate 10 miles of road. This is $10,900 per mile or 4 times as much as in project #9607706 (Lolo Watershed). Why the disparity?

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$420,000
FY06 NPCC Staff Preliminary:
$420,000
FY06 NPCC July Draft Start of Year:
$420,000
Sponsor (Nez Perce Tribe) Comments (Go to Original on NPCC Website):