Return to Proposal Finder FY 1999 Proposal 199700300

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Objectives, tasks and schedules
Section 5. Budget
Section 6. References
Section 7. Abstract

Reviews and Recommendations
Title Type File Size File Date


Section 1. General Administrative Information

Title of Project Proposal Box Canyon Watershed Project
BPA Project Proposal Number 199700300
Business name of agency, institution,
or organization requesting funding
Kalispel Tribe of Indians
Business acronym (if appropriate) KNRD
 

Proposal contact person or principal investigator

Name Gregory S. Olenik
Mailing Address P.O. Box 39
City, State, Zip Usk, WA 99180
Phone 5094451147
Fax 5094455302
E-mail osterman@povn.com
 
Manager of program authorizing this project
 
Review Cycle FY 1999
Province Upper Columbia
Subbasin Pend Oreille
 
Short Description Compliment efforts of the Kalispel Resident Fish Project through protection and enhancement of upland areas in a target watershed.
Target Species bull trout (proposed ESA listing) westslope cutthroat trout


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 10.8B.15
FWS/NMFS Biological Opinion Number(s) which this project addresses: Does not apply
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): resident


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
9500100 Kalispel Tribe Resident Fish Complimentary No
9700400 Resident Fish Stock Status Above Chief Joseph and Grand Coulee Dams Complimentary No
9106000 Pend Oreille Wetlands Wildlife Mitigation Project Wildlife habitat improvement on adjacent land No
9106001 Pend Oreille Wetlands II Wildlife habitat improvement on adjacent land No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Identify degraded fish habitat a. Search and analyze existing data on Cee Cee Ah creek
2. Identify upland management strategies that impact fish habitat b. Associate upland manaement with degraded fish habitat
3. Prioritize upland watershed problem areas c. Identify upland management activities most significantly contributing to degraded fish habitat
4. Prioritize protection, enhancement , and restoration projects within the target watershed d. Develop on-the-ground projects
. e. Implement prioritized projects
5. Use information gathered in Objectives 1, 2, 3, & 4 to address other watersheds within the Box Canyon reach f. Same as above tasks.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 05/01/97 12/01/97 20.0%
2 05/01/97 12/01/98 15.0%
3 01/01/98 12/01/99 15.0%
4 01/01/98 12/01/03 40.0%
5 01/01/03 12/01/03 10.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 1999 Cost
Personnel $ 30,371
Fringe 33% $ 10,022
Supplies $ 5,091
Travel $ 5,500
Indirect 28.7% $ 16,825
Subcontractor $ 0
Other $ 3,000
Total Itemized Budget $ 70,809


Total estimated budget

Total FY 1999 project cost $ 70,809
Amount anticipated from previously committed BPA Funds $ 0
Total FY 1999 budget request $ 70,809
FY 1999 forecast from 1998 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2000 2001 2002 2003
All Phases $ 72,000 $ 74,900 $ 77,900 $ 81,200
Total Outyear Budgets $ 72,000 $ 74,900 $ 77,900 $ 81,200
 

Other Budget Explanation

Schedule Constraints: It is impossible to identify all constraints and problems that may occur. While we will make every attempt to stay on schedule, unforseen assignments, bad weather, equipment failure, etc. will delay progress.


Section 6. References

n/a or no information


Section 7. Abstract

Abstract

The Box Canyon Watershed Project (BCWP) (NWPPC program measure 10.8B.15) was initiated by the Kalispel Natural Resource Department to assist in meeting biological objectives of the Kalispel Resident Fish Project. Initial focus of the project is Cee Cee Ah Creek watershed due to its proximity to the reservation, importance as a traditional fishery, and potential for bull and cutthroat trout recovery. The ongoing Kalispel Resident Fish Project is focused mainly on instream assessment and improvements. Implementing upland watershed protection and enhancement through the BCWP will reduce negative impacts of upland management strategies and increase protection and enhancement efforts of the ongoing Kalispel Resident Fish Project.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page