Title of Project Proposal Analyze and Improve Fish Screens
BPA Project Proposal Number 20085
Business name of agency, institution,
or organization requesting funding
Nez Perce Tribal Fisheries/Watershed Program
Business acronym (if appropriate) NPT
 

Proposal contact person or principal investigator

Name Elmer Crowe
Mailing Address P.O. Box 365
City, State, Zip Lapwai, ID 83540
Phone 2088432253
Fax 2088437322
E-mail elmerc@nezperce.org
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Mountain Snake
Subbasin Clearwater
 
Short Description Analyze and Improve Fish Screens on pump and water diversion in cooperation with the Idaho Fish and Game.
Target Species Chinook Salmon, Coho Salmon, Steelhead trout, Pacific Lamprey, and resident fish


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 2.2C.1; 7.10A.1-7
FWS/NMFS Biological Opinion Number(s) which this project addresses: None
Other Planning Document References Columbia River Basin Fish and Wildlife Program


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
8335000 Nez Perce Tribal Hatchery Supplementation No
9608600 Clearwater Focus Coordinator Idaho Soil Conservation Commission Co-coordinator for Clearwater River Subbasin No
9401500 Idaho Fish Screening Fish Screens No
9600600 Clearwater Focus Watershed/Co-coordinators was in umbrella table No
9607709 Protect and Restore Squaw and Papoose Watersheds was in umbrella table No
9607711 Restore McComas Meadows/Meadow Creek Watershed was in umbrella table No
9607708 Protect and Restore the Lolo Creek Watershed was in umbrella table No
9901700 Rehabilitate Lapwai Creek was in umbrella table No
9901600 Protect and Restore Big Canyon Creek Watershed was in umbrella table No
20087 Protect and Restore Mill Creek Watershed was in umbrella table No
20086 Rehabilitate Newsome Creek Watershed was in umbrella table No
20084 Protect and Restore North Lochsa Face Watershed Analysis Area was in umbrella table No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Coordinate with Federal & State agencies. a. Obtain necessary training.
1. b. Attend meetings in both the field and office settings.
2. Monitor & Evaluate irrigation pump screening requirements. a. Inventory of pump & dieversions and screens.
2. b. Field review of
3. Installation of screens as identified in the inventory a. Obtain necessary training.
3. b. Install screens where needed.
4. Disseminate information about project to all interested parties. a. Write quarterly reports.
4. b. Write annual reports.
4. c. Write future proposals for this project.
4. d. Prepare & deliver any public or interdepartment presentations.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 03/01/00 02/01/01 X  
2 03/01/00 02/01/01 X  
3 03/01/00 02/01/01 X  
4 03/01/00 02/01/01 X  


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 2000 Cost
Personnel $ 65,405
Fringe 24% Non-Tax-Exempt, Perm Staff 14% Tax-Exempt, Perm Staff $ 11,660
Supplies Monitoring equipment $ 5,000
Travel $ 6,740
Indirect 22.9% $ 20,336
Subcontractor Idaho Dept of Fish and Game $ 20,000
Total Itemized Budget $129,141


Total estimated budget

Total FY 2000 project cost $129,141
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $129,141
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Organization Item or service provided Amount Cash or In-Kind
Idaho Dept of Fish and Game Fish Screen Implementation, Maintenance, and Monitoring Support and Training $ 20,000 unknown

 

Outyear Budget Totals

2001 2002 2003 2004
All Phases $150,000 $175,000 $175,000 $185,000
Total Outyear Budgets $150,000 $175,000 $175,000 $185,000
 

Other Budget Explanation

Schedule Constraints: Unwilling landowner participation


Section 6. References

Reference Watershed?
Kappler, Charles J. Indian Affairs, Laws and Treaties, Treaty with the Nez Perces, 1855. 1904. Washington: Government Printing Office. No
Northwest Power Planning Council. 1994. Columbia River Basin fish and Wildlife Program. Northwest Power Planning Council, Portland, Oregon. No
USDA. 1997. National Indian Forest Resource Management Act, Public Law 101-630. No
U.S. Fish and Wildlife Service and U.S. Department of the Interior. 1973. Endangered Species Act of 1973. Washington, D.C. No
Washington Department of Fish and Wildlife. 1995. Screening Requirments for Water Diversions. No


Section 7. Abstract

Abstract

Fish screens are a high priority within the Columbia River Basin to protect anadromous fish from becoming entrained into irrigation diversions and pumps. The Nez Perce Tribe (NPT) will work with the Idaho Fish and Game (IDFG) in evaluating pumps to measure volume, identify screening needs, install and maintain screens for the protection of anadromous and resident fish. Planning , oversight, and coordination of the design and construction of thousands of fish screens and fish passage facilities in the Columbia River Basin is formulated by the Fish Screen Oversight Committee (FSOC). The goals of this project will be accomplished through coordination with Federal and State agencies, monitoring and evaluation of irrigation diversions and pump screening requirements, installation of screens as identified in the inventory, and dissemination of information to all significant parties.


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page