Section 1. General Administrative Information

Title of Project Proposal Multi-Year Deschutes Anadromous Fish Plan
BPA Project Proposal Number 20521
Business name of agency, institution,
or organization requesting funding
Columbia Basin Fish & Wildlife Authority
Business acronym (if appropriate) CBFWA
 

Proposal contact person or principal investigator

Name Tom Giese
Mailing Address 2501 SW First Ave., Suite 200
City, State, Zip Portland, OR 97201
Phone 5032290191
Fax 5032290443
E-mail tom@cbfwf.org
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Columbia Plateau
Subbasin Deschutes
 
Short Description
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses:
FWS/NMFS Biological Opinion Number(s) which this project addresses:
Other Planning Document References


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
20521 MYP Deschutes Anadromous Fish Plan Yes
9404200 O&M for Trout Creek Habitat Improvement Project. Yes
9306600 Trout Creek screen maintenance. Yes
9138 Watershed enhancement activities. Yes
9005 Riparian restoration and enhancement projects with private landowners. Yes
9007 Complete watershed assessments, develop goals, objectives, lists, plans. Yes
9133 Initiate riparian work as second phase of comprehensive watershed approach. Yes


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Improve quantity and quality of aquatic and riparian habitat. a. Improve habitat through use of riparian fencing, grazing management and instream structures.
1. b. Improve screens on irrigation diversions.
2. Maintain and improve upland watershed conditions to sustain high water quality. a. Improve habitat through use of riparian fencing, grazing management and instream structures.
3. Maintain genetic diversity, adaptiveness, abundance of indigenous wild fish. a. Increase harvest opportunities for tribal and non-tribal fisheries using artificial production while maintaining genetic integrity of wild fish by not allowing hatchery fish above hatcheries.
4. Provide opportunities to harvest anadromous species, while maintaining adequate wild spawning escapement and hatchery broodstock. a. Increase harvest opportunities for tribal and non-tribal fisheries using artificial production while maintaining genetic integrity of wild fish by not allowing hatchery fish above hatcheries.
5. Increase harvest opportunity for hatchery-origin summer steelhead and spring chinook through use of acclimation and adult capture facilities. a. Increase harvest opportunities for tribal and non-tribal fisheries using artificial production while maintaining genetic integrity of wild fish by not allowing hatchery fish above hatcheries.

Objective Schedules and Costs

n/a or no information

Itemized Budget

Item Note FY 2000 Cost
Personnel $ 0
Fringe $ 0
Supplies $ 0
Total Itemized Budget $ 0


Total estimated budget

Total FY 2000 project cost $ 0
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $ 0
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Not applicable


Section 6. References

Reference Watershed?
Draft Multi-Year Anadromous Fish Plan, CBFWA, February 4, 1998 No
FY1999 Draft Annual Implementation Work Plan, Vol. 1 Tab. 5, CBFWA May 13, 1998 No


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed