Section 1. General Administrative Information

Title of Project Proposal Operate and Maintain Umatilla Hatchery Satellite Facilities
BPA Project Proposal Number 198343500
Business name of agency, institution,
or organization requesting funding
Confederated Tribes of the Umatilla Indian Reservation
Business acronym (if appropriate) CTUIR
 

Proposal contact person or principal investigator

Name Gary A. James
Mailing Address P.O. Box 638
City, State, Zip Pendleton, OR 97801
Phone 5412764109
Fax 5422764348
E-mail jaburke@ucinet.com
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Columbia Plateau
Subbasin Umatilla
 
Short Description Acclimate juvenile salmon and steelhead prior to release in the Umatilla Basin. Collect, hold and spawn broodstock and provide eggs to ODFW and other hatcheries for incubation, rearing and later release into the Umatilla Basin.
Target Species Summer steelhead, coho, fall and spring chinook


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 7.4I.1., 7.4I.2
FWS/NMFS Biological Opinion Number(s) which this project addresses: Number 383 - NMFS Biop for 1995-1998 Hatchery Operations Section IV.C.3.b.
Other Planning Document References CRITFC, 1995. Wy-Kan-Ush Mi Wa-Kish-Wit , Volume II. Subbasin Plans - Umatilla River ODFW, 1986. Umatilla Fisheries Restoration Plan - Present and Proposed Flow Enhancement and Fishery Rehabilitation Projects and Costs CTUIR, 1990. Umatilla Subbasin Plan - Section IV. Andromous Fish Production Plans ODFW & CTUIR, 1990. Umatilla Hatchery Master Plan - Production Profile and Facilities Needed to Implement Program CTUIR, 1998. Draft Umatilla Hatchery Supplemental Master Plan - Section VI. Facilities Needed to Implement Plan ODFW/CTUIR 1998. Umatilla Hatchery and Basin Annual Operation Plan (AOP) - Sections II through VII


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1998 Acclimated and released 19.9 million summer steelhead, coho, and fall and spring chinook from project facilities from 1983 to 1998.
1998 Held and spawned approximatly 6,100 broodstock in project facilities from 1983 to 1998.


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
8802200 Umatilla Fish Passage Operations The passage operations project provides adult recovery information and broodstock for spawning, and provide passage for outmigrating hatchery produced juveniles. No
NEOH Hatchery - Walla Walla Component - Design, and Construction This project provides for design and construction of new artificial production facilities which will be operated under project no. 8343500 when completed. No
8805302 Umatilla Hatchery Supplement Facility Design, and Construction Same as box above No
9000501 Umatilla Natural Production M & E The UBNPM&E project provides biological information related to the outcome of the production goals. No
8710001 Umatilla River Basin Anadromous Fish Habitat Enhancement The URBAFHE project provides increased habitat for fish utilization. No
9000500 Umatilla Hatchery M & E The UHM&E project provides biological information related to the operation of the satellite facilities and evaluates the success of the artificial production program. No
8902401 Umatilla River WEID/Screens M & E The URW/SM&E project provides biological information related to the operation of the production program. No
8343600 Umatilla Passage Facilities O & M The UPFO&M project assists in preventative and heavy maintenance at all Umatilla hatchery satellite facilities. No
Little White Salmon Hatchery O & M LWSH provides fall and spring chinook smolts for acclimation and release into the Umatilla River basin. No
8403300 Umatilla Hatchery O & M (sub-proposal submitted separately) Yes
8343500 Umatilla Hatchery Satellite Facilities O & M (subject sub-proposal) Yes
Umatilla Artificial Production O & M Yes


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Increase adult salmon and steelhead survival and homing to the Umatiila River Basin a. Hold (acclimate) and feed groups of juvenile salmonids at Bonifer, Minthorn, Imeques C-mem-ini-kem, Thornhollow and another acclimation facility (to be constructed in 1999) before release into the Umatilla River Basin
1. b. Collect species composition, marks, size and numbers of fish trapped at Westland Canal juvenile facility during trapping operations to give an indication of outmigration timing
1. c. Determine total survival, contribution to ocean and Columbia River fisheries and escapement to the Umatilla River and other terminal areas of all coded-wire tagged groups released into the Umatilla River Basin
1. d. Maintain juvenile acclimation release facilities in good working order
2. Provide eggs for Umatilla River production programs a. Collect, hold and artificially spawn broodstock at the Threemile Dam (fall chinook and coho), S. Fk. Walla Walla (spring chinook), and Minthorn (steelhead) adult holding/ spawning facilities.
2. b. Assist ODFW in collecting samples from prespawn mortalities and spawned fish for disease analysis
2. c. Maintain adult holding/spawning facilities in good working order
3. Participate in planning and review process for the new Umatilla Hatchery supplement and the NEOH - Walla Walla Hatchery a. Review and comment on engineering designs and follow up with engineers as necessary during planning and construction of incubation and rearing facilities planned at the S. Fk. Walla Walla River site
4. Increase production of Carson Stock CHS for release ino the Umatilla River a. USFWS to provide services needed to mark100,000 CHS from Carson Hatchery
4. b. USFWS toprovide services needed to produce 350,000 from Little White Salmon Hatchery

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 01/01/00 06/01/00 Achieve targets for juvenile salmon and steelhead acclimation and release Document increasing trends in adult returns and natural production 45.0%
2 01/01/00 12/01/00 Achieve Umatilla broodstock and egg targets and provide to ODFW and other hatcheries Successfully hold and spawn adults annually 35.0%
3 01/01/00 12/01/00 4.0%
4 01/01/00 12/01/00 Successfully produce 100,000 spring chinook at Carson Hatchery and 350,000 at Little White Salmon Hatchery prior to release in the Umatilla River Basin Annually receive designated numbers of healthy fish at Umatilla Basin juvenile acclimation/release facilities 16.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 2000 Cost
Personnel 7.9 FTE $287,401
Fringe 28% $ 80,472
Supplies $ 30,720
Operating $ 88,897
Travel $ 25,735
Indirect 34% $174,497
Other (fish rearing/marking support serv. to USFWS) $134,439
Total Itemized Budget $822,161


Total estimated budget

Total FY 2000 project cost $822,161
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $822,161
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2001 2002 2003 2004
All Phases $1,486,066 $1,549,511 $1,612,714 $1,675,574
Total Outyear Budgets $1,486,066 $1,549,511 $1,612,714 $1,675,574
 

Other Budget Explanation

Schedule Constraints: Availability of broodstock and smolt production levels below targets may constrain or limit satellite facility operations or schedules.


Section 6. References

Reference Watershed?
Columbia River Inter-Tribal Fish Commission. 1995. Wy-Kan-Ush-Mi Wa-Kish-Wit, Volume II. Subbasin Plans - Umatilla River. No
Confederated Tribes of the Umatilla Indian Reservation and Oregon Department of Fish and Wildlife. 1989. Umatilla Hatchery Master Plan. Prepared for Northwest Power Planning Council, Portland, Oregon. No
Confederated Tribes of the Umatilla Indian Reservation and Oregon Department of Fish and Wildlife. 1990. Columbia Basin System Planning, Umatilla Subbasin, September, 1990. Prepared for Northwest Power Planning Council and Columbia Basin Fish and Wildl No
Confederated Tribes of the Umatilla Indian Reservation and Oregon Department of Fish and Wildlife. 1998. Umatilla Hatchery and Basin Annual Operation Plan for the period September, 1998 to August, 1999. Oregon Department of Fish and Wildlife, Pendleton, No
Lofy, Peter T. and Gerald D. Rowan. 1990. Operation, Maintenance and Evaluation of the Bonifer and Minthorn Springs Juvenile Release and Adult Collection Facilities. Annual Report - 1989. Contract No. DE-B179-84BP17622. Prepared for Bonneville Power Admin No
National Marine Fisheries Service. 1995. Biological Opinion for 1995 to 1998 Hatchery Operations in the Columbia River Basin. National Marine Fisheries Service, Portland, Oregon. No
Oregon Department of Fish and Wildlife. 1986. Umatilla Fisheries Restoration Plan - Present and Proposed Flow Enhancement and Fishery Rehabilitation Projects and Costs No
Oregon Department of Fish and Wildlife. 1986. A Comprehensive Plan for Rehabilitation of Anadromous Fish Stocks in the Umatilla River Basin. Project No. 84-10, Contract No. DE-AI179-84BP18008, Bonneviller Power Administration. No
Rowan, Gerald D.1991-1998. Operate and Maintain Umatilla Hatchery Satellite Facilities. Annual Reports 1990 - 1997. Contract No. DE-B179-84BP17622. Prepared for Bonneville Power Administration, Portland No


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

ISRP Preliminary Review , ISRP 99-2 Recommendation:
Delay Funding
Date:
Jun 15, 1999
[There are no budget numbers associated with this review.]
Comment:
Recommendation: Delay funding until the proposal addresses specific deficiencies noted in the comments. This project should be included in an Independent Programmatic Review of the Umatilla and Walla Walla hatchery programs.

Comments: A number of objectives listed here are also covered in other proposals, which raises the question of whether there is duplication of effort or a lack of coordination. The budget is not satisfactorily justified. The number of full time personnel seems high. No explanation is given for increased out-year costs. In fact, the proposal says it expects costs to reach a maximum of $661,000 in FY 1999, but shows $1,486,000 in FY 2000, increasing to $1,675,000 in FY 2004. It is not clear, given the high rate of straying of returning adults, that the acclimation facilities are accomplishing their presumed objective of encouraging return of adults to upstream areas. Is there any evidence that fish held in acclimation ponds are any more likely to return to the area as adults than fish released directly from the trucks?


CBFWA: Nonwatershed Technical Group Comments Recommendation:
Date:
Aug 20, 1999
[There are no budget numbers associated with this review.]
Comment:
Technical Criteria 1: Met? yes -

Programmatic Criteria 2: Met? yes - O&M - na for these criteria?

Milestone Criteria 3: Met? yes -

Resource Criteria 4: Met? yes -


CBFWA: Subregional Team Comments Recommendation:
Date:
Aug 20, 1999
[There are no budget numbers associated with this review.]
Comment:
Reducing staff time.

CBFWA Funding Recommendation Recommendation:
Fund
Date:
Aug 20, 1999
2000
$775,000
Comment:

ISRP Final Review , ISRP 99-4 Recommendation:
Fund existing activities
Date:
Oct 29, 1999
[There are no budget numbers associated with this review.]
Comment:
Fund existing activities. See programmatic recommendation for Umatilla and Walla Walla under project 8903500. Most concerns were addressed in the review response, except the issue of whether or not smolt-to-adult survival has been increased.

NWPPC Funding Recommendation Recommendation:
Fund existing activities
Date:
Nov 8, 1999
[There are no budget numbers associated with this review.]
Comment:

NWPPC Funding Recommendation , NWPPC 2000-6 Recommendation:
Fund
Date:
Mar 1, 2000
2000
$775,000
Comment:
[Decision made in 11-3-99 Council Meeting]; Address ISRP comments in BPA contract

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$1,018,147
FY06 NPCC Staff Preliminary:
$1,018,147
FY06 NPCC July Draft Start of Year:
$1,018,147
Sponsor (Confederated Tribes Of The Umatilla Indian Reservation) Comments (Go to Original on NPCC Website):

Sponsor (Confederated Tribes Of The Umatilla Indian Reservation) Comments (Go to Original on NPCC Website):

Return to top of page