Return to Proposal Finder FY 2000 Proposal 198805302

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Objectives, tasks and schedules
Section 5. Budget
Section 6. References
Section 7. Abstract

Reviews and Recommendations
Title Type File Size File Date


Section 1. General Administrative Information

Title of Project Proposal Plan, Site, Design and Construct Neoh Hatchery - Umatilla/Walla Walla Comp.
BPA Project Proposal Number 198805302
Business name of agency, institution,
or organization requesting funding
Confederated Tribes of the Umatilla Indian Reservation
Business acronym (if appropriate) CTUIR
 

Proposal contact person or principal investigator

Name Gary A. James
Mailing Address P.O. Box 638
City, State, Zip Pendleton, OR 97801
Phone 5412764109
Fax 5412764348
E-mail jaburke@ucinet.com
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Columbia Plateau
Subbasin Umatilla
 
Short Description Add incubation/juvenile rearing to the Walla Walla brood facility to rear summer steelhead and spring chinook salmon for acclimation/release in the Walla Walla and Umatilla Basins. Construct acclimation facilities to accommodate all juvenile salmon and st
Target Species Spring chinook salmon, summer steelhead


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 7.4L 1
FWS/NMFS Biological Opinion Number(s) which this project addresses: N/A
Other Planning Document References Wy Kan Ush Me Wa Kush Wit - Volume II.Subbasin Plans - Walla Walla River Umatilla Subbasin Plan - Section IV. Anadromous Fish Production Plans Umatilla Hatchery Master Plan - Production Profile Draft Umatilla Hatchery Supplemental Master Plan - Sections I. Executive Summary - Introduction, Facilities Needed to Implement Plan; II. Recommendations; III. D. Introduction - NEOH Master Plan Background; V. Production Profile; and VI. Facilities Needed to Implement Plan Walla Walla River Subbasin Plan - Section IV. Anadromous Fish Production Plans Draft Walla Walla Hatchery Master Plan - Sections I. Executive Summary - Introduction, Production Profile, Facilities Needed to Implement Program; II. Recommendations; IV. B. Fisheries Management Policies - Subbasin Goals and Policies; V. Production Profile - A. Introduction, B. Spring Chinook Hatchery Production, D. Summer Steelhead Hatchery Production; VI. Facilities Needed to Implement Program - B. Existing Facilites, C. New Facilities Corp


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

n/a or no information


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
8343500 Umatilla Hatchery Satellite Facilities O & M Project number 8343500 will provide for operation and maintenance of the facilities completed under this project. No
8802200 Umatilla and Walla Walla Basins Trap and Haul Program The trap and haul program will provide adult recovery information, broodstock for spawning, and they will trap and haul outmigrating hatchery produced juveniles during low water conditions. No
9000500 Umatilla Hatchery M & E The UHM&E project will provide biological information related to the operation of the facilities and will evaluate the success of the artificial production program. No
8343600 Umatilla Passage Facilities O & M The UPFO&M will assist in the maintenance of all facilities completed under this project. No


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Finalize designs and construct NEOH hatchery on the Walla Walla River. a. Finalize plans and designs for summer steelhead and spring chinook hatchery on the Walla Walla River.
1. b. Construct summer steelhead and spring chinook hatchery on the Walla Walla River. Project number 8343500 will provide operation and maintenance upon completion.
2. Plan, site and design juvenile acclimation and release facilities for the Walla Walla Basin. a. Plan, site and design two or three juvenile acclimation and release facilities for construction in 2001 in the Walla Walla Basin. Project number 8343500 will provide operation & maintenance upon completion.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 10/01/99 09/01/00 98.0%
2 10/01/99 09/01/00 2.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 2000 Cost
Personnel $ 0
Fringe $ 0
Supplies $ 0
Capital Walla Walla Hatchery Construction $6,300,000
Other Walla Walla Hatchery and Acclimation Facility siting, planning and design $100,000
Total Itemized Budget $6,400,000


Total estimated budget

Total FY 2000 project cost $6,400,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $6,400,000
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Schedule Constraints: Finalization of Walla Walla Hatchery Master Plan and NEOH Umatilla Hatchery Supplemental Master Plan or availability of funding may delay the project.


Section 6. References

Reference Watershed?
Confederated Tribes of the Umatilla Indian Reservation, Oregon Department of Fish and Wildlife, Washington Department of Fisheries, and Washington Department of Wildlife. 1990. Walla Walla River Subbasin Salmon and Steelhead Production Plan. Prepared No
Confederated Tribes of the Umatilla Indian Reservation. 1993. Northeast Oregon Hatchery Project - Umatilla Hatchery Supplemental Master Plan. Prepared for Bonneville Power Administration, Portland, Oregon. 27 pp. No
Confederated Tribes of the Umatilla Indian Reservation and the Oregon Department of Fish and Wildlife. 1990. Umatilla Hatchery Master Plan. Prepared for the Northwest Power Planning Council. Portland, Oregon. 118 pp. No
Confederated Tribes of the Umatilla Indian Reservation and Oregon Department of Fish and Wildlife. 1990. Umatilla Subbasin Salmon and Steelhead Production Plan. Prepared for the Northwest Power Planning Council. Portland, Oregon. No


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page