Section 1. General Administrative Information

Title of Project Proposal Powerdale, Parkdale, and Oak Springs O&M
BPA Project Proposal Number 199301900
Business name of agency, institution,
or organization requesting funding
Oregon Department of Fish and Wildlife / Confederated Tribe of the Warm Springs Reservation
Business acronym (if appropriate) ODFW/CTWSRO
 

Proposal contact person or principal investigator

Name Mick Jennings
Mailing Address 3450 W 10th St.
City, State, Zip The Dalles, OR 97058
Phone 5412966866
Fax 5412968886
E-mail mickjennings@netcnct.net
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Columbia Gorge
Subbasin Hood
 
Short Description Restore depressed populations of summer and winter steelhead and re-establish a self-sustaining spring chinook salmon population in the Hood River subbasin. Broodstock will be collected at the Powerdale Facility. Broodstock will be held and spawned at th
Target Species spring chinook, summer and winter steelhead


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 7.4L.2
FWS/NMFS Biological Opinion Number(s) which this project addresses: NA
Other Planning Document References CRITFC. 1996. WY-KAN-USH-MI WA-KISH-WIT, Cited: Volume II:25-26. Department of Natural Resources, CTWS, October, 1993. Hood River/Pelton Ladder Master Agreement. Cited: entire document. DOE and BPA. March, 1996. Draft Environmental Impact Statement (DOE/EIS-0241). Cited: entire document. DOE and BPA. July, 1996. Final Environmental Impact Statement (DOE/EIS-0241). Cited: entire document. ODFW and CTWS. September, 1990. Hood River Subbasin Salmon and Steelhead Production Plan. NPPC. 1992. NPPC approval letter for the Hood River Master Plan. April 16, 1992. NPPC. 1994. Columbia River Basin Fish and Wildlife Program. Adopted November 15, 1982. Amended December 14, 1994. O’Toole, P., and ODFW. 1991a. Hood River Production Master Plan. Cited: entire document.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1994 Collected first Hood River native winter steelhead broodstock at Powerdale Trap.
1996 began releases of Deschutes stock spring chinook in Hood River subbasin.
1996 Powerdale Trapping Facility completed.
1997 Collected first Hood River native summer steelhead broodstock at Powerdale Trap
1997 Hood River Production Program EIS completed.
1998 Parkdale Fish Facility completed and operational.
1998 Oak Springs Hatchery - addition to hatchery building completed, including isolation/incubation and early rearing. New raceways and water supply nearing completion - will be completed for spring, 1999 rearing.


Section 3. Relationships to Other Projects

Project ID Title Description Umbrella
9802100 Hood River Fish Habitat / Implement habitat improvement actions Yes
8805304 Hood River Production Program/ODFW M&E Yes
8805303 Hood River Production Program/CTWS M&E Yes
9500700 Pelton Ladder Hood River Production/PGE O&M Yes
20513 Hood River / Fifteenmile Creek Umbrella Yes
8902900 Hood River Production Program/Round Butte Hatchery production and Pelton La Yes


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Achieve an interim adult return of 1800 hatchery summer steelhead to the mouth of Hood River.(See umbrella for long range run size objectives) a. Collect 40 Hood River wild summer steelhead broodstock at Powerdale Dam. Transfer fish to Parkdale. (observe Wild Fish Management Policy and Broodstock Collection Protocol)
1. b. Hold and spawn 40 wild summer steelhead. (observe Spawning Protocol)
1. c. Transfer eggs to Oak Springs Hatchery. Incubate, rear and fin-mark 40,000 summer steelhead smolts.
1. d. Produce smolt that averages 18 cm and has a condition factor of 1.00 or less.
1. e. Transport smolts to Hood River acclimation sites.
1. f. Monitor and evaluate the operation and maintenance of each fish facility.
2. Achieve an interim adult return of 2250 hatchery winter steelhead to the mouth of Hood River. (See umbrella for long range run size objectives) a. Collect 70 Hood River winter steelhead broodstock (50% wild/50% hatchery) at Powerdale Dam (observe Wild Fish Management Policy and Broodstock Collection Protocol). Transfer fish to Parkdale.
2. b. Hold and spawn 70 winter steelhead. (observe Spawning Protocol)
2. c. Transfer eggs to Oak Springs Hatchery. Incubate, rear and fin-mark 50,000 winter steelhead smolts.
2. d. Produce smolt that averages 18 cm and has a condition factor of 1.00 or less.
2. e. Transfer smolts to Hood River acclimation sites.
3. Achieve an interim adult return of 850 hatchery spring chinook to the mouth of Hood River. (See umbrella for long range run size objectives) a. Collect 110 Deschutes stock spring chinook broodstock at Powerdale Dam. (observe Broodstock Collection Protocol) Transfer fish to Parkdale.
3. b. Hold and spawn 110 spring chinook. (observe Spawning Protocol)
3. c. Transfer eyed eggs to Round Butte Hatchery.
3. d. Assist in acclimating a portion of 125,000 spring chinook smolts.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 10/01/99 09/01/00 Achieve an interim adult return of 1800 hatchery summer steelhead to the mouth of Hood River. (See Hood River / Fifteenmile Creek Umbrella for long range run size objectives) This milestone will not be attainable for several years. (The first release of approximately Hood River stock smolts is scheduled for the spring of 1999.) 25.0%
2 10/01/99 09/01/00 Achieve an interim adult return of 2250 hatchery winter steelhead to the mouth of Hood River. (See Hood River / Fifteenmile Creek Umbrella for long range run size objectives) This milestone will be attainable by year 2002. 35.0%
3 10/01/99 09/01/00 Achieve an interim adult return of 850 hatchery spring chinook to the mouth of Hood River. (See Hood River / Fifteenmile Creek Umbrella for long range run size objectives) This milestone will be attainable by year 2002. 45.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 2000 Cost
Personnel Manager, assistant, seasonal Tech 1 $189,774
Fringe 23% $ 59,096
Supplies utility trailer, wood stove, marlow pump, pallet jack, shop supplies $ 62,909
Operating GMS support, EG servicing contract $ 0
Capital Carport addition to Oak Springs HRPP residence $ 15,000
Travel per diem, air fare $ 6,400
Indirect ODFW and CTWS average 37.4% $119,226
Other Employee training $ 1,400
Subcontractor Electrician, plumber, diesel mechanic, pump servicing and repairs $ 33,000
Total Itemized Budget $486,805


Total estimated budget

Total FY 2000 project cost $486,805
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $486,805
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Organization Item or service provided Amount Cash or In-Kind
See Hood River / Fifteenmile Creek Umbrella $ 0 unknown

 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Schedule Constraints: NONE


Section 6. References

Reference Watershed?
CRIFC. 1996. WY-KAN-USH-MI WA-KISH-WIT. The Columbia River Anadromous Fish Restoration Plan of the Nez Perce, Umatilla, Warm Springs, and Yakama Tribes. Portland, Oregon. No
CTWS and ODFW, cooperators. 1996. Annual progress report. Hood River and Pelton Ladder evaluation studies. Annual Progress Report of the CTWS and ODFW (Projects 88-053-03 and 88-053-04) to Bonneville Power Administration (BPA), Portland, Oregon. No
CTWS and ODFW, cooperators. January 1998. Annual progress report. Hood River and Pelton Ladder evaluation studies. Annual Progress Report of the CTWS and ODFW (Projects 88-053-03 and 88-053-04) to BPA, Portland, Oregon. No
DOE and BPA (U.S. Department of Energy and Bonneville Power Administration). March 1996. Hood river fisheries project. Draft Environmental Impact Statement (DOE/EIS-0241). Bonneville Power Administration, Portland, Oregon. No
DOE and BPA (U.S. Department of Energy and Bonneville Power Administration). July 1996. Hood River fisheries project. Final Environmental Impact Statement (DOE/EIS-0241). Bonneville Power Administration, Portland, Oregon. No
Northwest Power Planning Council (NPPC). 1987. Columbia River basin fish and wildlife program. Portland, Oregon. No
O’Toole, P., and ODFW. 1991a. Hood River production master plan. Final report of the CTWS and the ODFW (Project 88-053-03, Contract DE-BI79-89BP00631) to BPA, Portland, Oregon. No
O’Toole, P., and ODFW. 1991a. Hood River production master plan (Appendices). Final report of the CTWS and the ODFW (Project 88-053-03, Contract DE-BI79-89BP00631) to BPA, Portland, Oregon. No


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page