Section 1. General Administrative Information

Title of Project Proposal North Fork John Day Area Riparian Fencing
BPA Project Proposal Number 199303800
Business name of agency, institution,
or organization requesting funding
USDA Forest Service, Umatilla National Forest
Business acronym (if appropriate) USFS
 

Proposal contact person or principal investigator

Name Dell Groat
Mailing Address Umatilla NF, 2517 S.W. Hailey Ave.
City, State, Zip Pendleton, OR 97801
Phone 5412783819
Fax 5412783730
E-mail dgroat@fs.fed.us
 
Manager of program authorizing this project
 
Review Cycle FY 2000
Province Columbia Plateau
Subbasin John Day
 
Short Description Protect riparian vegetation on 60 miles of streams in the North Fork John Day drainage that has recovered due to past project work. Primary project activities are resetting seasonal electric fence and construction of barbwire riparian exclosures.
Target Species John Day River Summer Steelhead, John Day River Spring Chinook, Redband Trout, Bull Trout


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


NPPC Program Measure Number(s) which this project addresses: 7.6B.5 7.6B.4 7.6C.5
FWS/NMFS Biological Opinion Number(s) which this project addresses: None
Other Planning Document References Umatilla National Forest Plan


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: Contact info updated from Council, 11/10/03
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1995 Protect 60 miles of riparian habitat
1996 Protect 60 miles of riparian habitat
1997 Protect 60 miles of riparian habitat
1998 Protect 60 miles of riparian habitat


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Objectives, Tasks and Schedules

Objectives and Tasks

Objective Task
1. Protect Riparian Recovery on 60 miles of streams in the North Fork John Day drainage a. Set 50 miles seasonal electric fence
1. b. Maintain electric fence
1. c. Construct 3 miles barbwire fence
1. d. Maintain constructed barbwire exclosures.

Objective Schedules and Costs

Objective Start Date End Date Measurable Biological Objectives Milestone FY 2000 Cost %
1 05/01/00 11/01/00 100.0%


Section 5. Estimated Budget Summary

Itemized Budget

Item Note FY 2000 Cost
Personnel $ 34,700
Fringe $ 0
Supplies $ 4,000
Operating $ 1,000
Travel $ 3,800
Indirect $ 6,500
Subcontractor $ 18,000
Total Itemized Budget $ 68,000


Total estimated budget

Total FY 2000 project cost $ 68,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2000 budget request $ 68,000
FY 2000 forecast from 1999 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2001 2002 2003
All Phases $ 68,000 $ 68,000 $ 68,000
Total Outyear Budgets $ 68,000 $ 68,000 $ 68,000
 

Other Budget Explanation

Schedule Constraints: None


Section 6. References

Reference Watershed?
Land and Resource Management Plan, Umatilla National Forest No


Section 7. Abstract

Abstract


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed

Return to top of page