Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Protect And Enhance Anadromous Fish Habitat In The Umatilla River Subbasin
BPA Project Proposal Number 198710002
Business name of agency, institution,
or organization requesting funding
Oregon Department of Fish & Wildlife
Business acronym (if appropriate) ODFW
 

Proposal contact person or principal investigator

Name Troy Laws
Mailing Address 73471 Mytinger Lane
City, State, Zip Pendleton, OR 97801
Phone 5412762344
Fax 5412764414
E-mail troyfishab@oregontrail.net
 
Manager of program authorizing this project Bruce Eddy
 
Review Cycle FY 2001 Ongoing
Province Columbia Plateau
Subbasin Umatilla
 
Short Description Protect and enhance coldwater fish habitat on private lands in the Umatilla River Basin in a manner that achieves self-sustaining salmonid populations and their associated habitat by utilizing natural stream functions to the fullest extent.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: This project is expected to result in improved water quality, increased instream habitat diverstiy and complexity and increased quantity of usable habitat by salmonid fish. Through deriving these benefits we expect that the overall ecological productivity of stream ecosystem will be improved. This includes increased productivity of anadromous salmonid populations. Increased productivity of anadromous salmonid populations should lead to increased numbers where feshwater habitat is a primary limiting factor.
Biological Data: Because of the lag time of habitat recovery using passive approaches, our first priority is to measure the physical changes in the stream environment. They are the most direct and easily measured results of this project. Riparian vegetation, stream channel morphology, instream habitat diversity and water temperature are monitored. It is only after significant changes in the physical elements of streams and their riparian zones that changes will take place in fish production and the 15-year life span of the project is not adequate time to show the biological results. However, basin-wide and project specific spawning ground surveys and juvenile density estimates are conducted to monitor trends in adult and juvenile salmonid abundance.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
2000 Protected, restored and/or enhanced 11 miles of stream by installing 16 miles of fence and retrofitting existing projects with bioengineering treatments.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Obj. 1. Develop plans for enhancing fish habitat and riparian areas. Task 1.1. Develop "reference reach" data to determinie functionality and stability of project streams. 3-5 $ 7,500  
Task 1.2. Work cooperatively with private landowners to develop long-term riparian leases, cooperative agreements or easements. On-going $ 7,500  
Task 1.3. Conduct Rosgen (1996) level III assessment of instream project streams. On-going $ 4,000  
Task 1.4. Conduct project design surveys. On-going $ 4,980  
Task 1.5. Develop instream project designs. On-going $ 20,000 x
Task 1.6. Prepare contract documents and specifications. On-going $ 15,000  
Obj 2. Develop plans for maintaining fish habitat improvement projects. Task 2.1. Prepare contract documents and specifications. On-going $ 2,500  
Task 2.2 Conduct on-site preparation activities. On-going $ 2,500  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 70,000 $ 74,000 $ 67,200 $ 70,000


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Obj. 1. Improve stream channel function, instream habitat diversity and streambank stability by constructing bioengineering treatments, instream structures and placing large wood. Task 1.1. Reconstruct a sinuous stream channel along one mile of East Birch Creek. 1 $ 17,500 x
Task 1.4. Reconstruct a sinuous stream channel along 1.5 miles of West Birch Creek. 1 $106,516 x
Objective 2. Improve the quantity and quality of riparian communities. Task 2.1. Use intensive bioengineering techniques to revegetate the riparian zone and floodplain on one mile of East Birch Creek. 3 $ 22,319 x
Task 2.2. Construct 2 miles of riparian exclosure fencing on one mile of East Birch Creek. 1 $ 25,000 x
Task 2.3. Use intensive bioengineering techniques to revegetate the riparian zone and floodplain on 1.5 miles of West Birch Creek. 3 $ 50,000 x
Task 2.4. Construct 3 miles of riparian exclosure fencing along 1.5 miles of West Birch Creek. 1 $ 2,500 x
Task 2.5. Construct four off-site water developments to encourage livestock utilization of uplands and divert grazing pressure from streams and riparian areas. 1 $ 10,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2004 FY 2005 FY 2002 FY 2003
$254,325 $264,500 $246,825 $254,325


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Obj. 1. Provide maiximum project benefits by providing maintenance on existing projects. Task 1.1 Inspect and maintain 13.9 miles of riparian corridor fence. On-going $ 5,000  
Task 1.3. Inspect completed instream work on 3.25 miles of stream and conduct maintenance where necessary. On-going $ 2,500  
Task 1.4. Inspect all leased areas for revegetation success and plant native trees, shrubs and grasses where needed. On-going $ 12,443  
Task 1.5. Irrigate vegetative plantings installed in 1998, 1999 and 2000 on east and mainstem Birch Creek. On-going $ 10,000  
Task 1.6. Inspect and maintain 7 livestock water developments. On-going $ 3,500  
Task 1.7. Coordinate O & M activities with private landowners. On-going $ 5,000  
Task 1.8. Conduct weed control activities on 120 acres. On-going $ 9,500  
Task 1.9. Repair and maintain project vehicles, tools and equipment. On-going $ 5,000  
Obj. 2. Provide administrative oversight and secretarial support for project activities. Task 2.1. Prepare and review all contract documents, competitive bid packages, riparian leases and reports. On-going $ 2,500  
Task 2.2. Prepare annual work statements and budgets for submittal to BPA. On-going $ 7,500  
Task 2.3 Liaison with BPA, federal and state agencies and tribes on issues that effect successful implementation of on-the-ground projects. On-going $ 2,000  
Task 2.4 Supervision of project personnel. On-going $ 5,000  
Task 2.5. Provide secretarial support for project activities. On-going $ 2,983  
Task 2.6 Provide offices and support services for project personnel On-going $ 3,000  
Task 2.7. Develop project procedures and protocols for development, maintenance and construction of projects. On-going $ 2,500  
Obj. 3. Insure maximum communication, education and coordination of habitat enhancement activities by actively pursuing opportunities to work with, educate and learn from individuals and entities. Task 3.1. Work cooperatively with the Umatilla County SWCD and Umatilla Basin Watershed Council to identify and prioritize projects. On-going $ 7,500  
Task 3.2. Coordinate field activities with other agencies. On-going $ 7,500  
Task 3.3. Answer correspondence, respond to information needs and make presentations to other agencies, private organizations, school/youth groups and the news media. On-going $ 2,500  
Task 3.4. Work cooperatively with private landowners to promote projects and management activities beneficial to the protection and restoration of fish habitat. On-going $ 7,500  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2004 FY 2005 FY 2002 FY 2003
$117,725 $122,600 $110,775 $117,725


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Objective 1. Monitor and evaluate existing riparian habitat enhancement projects. Task 1.1. Establish 20 new photopoints on new project sites and retake pictures at selected established photopoint sites. On-going $ 3,500  
Task 1.2.Monitor temerature changes as a result of enhancement activities at 11 sites. On-going $ 3,000  
Task 1.3. Summarize and report monitoring results in annual report. On-going $ 4,522  
Task 1.4. Collect data from 15 channel morphology transects. Conduct longitudinal surveys on four sites. On-going $ 5,000  
Task 1.5. Conduct juvenile population estimates on Meacham Creek. On-going $ 1,500  
Task 1.6. Update monitoring approach to utilize state of the art methodologies and to more effectively document improvements. 1 $ 6,500  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 26,200 $ 27,200 $ 25,200 $ 26,200


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: .29 NRS 2, .13 Tech 2, .08 SFWB $ 21,304
Fringe $ 8,500
Supplies $ 500
Travel Vehicle lease and mileage $ 1,133
Indirect $ 8,663
Subcontractor Design Consultant $ 22,750
Other Training $ 1,130
Personnel FTE: .33 NRS 2, .5 Tech 2, .5 Tech 1, .33 laborer 1 $ 44,202
Fringe $ 17,637
Supplies $ 13,650
Travel Vehicle lease and mileage $ 9,360
Indirect $ 22,570
Subcontractor Construction contractors, technical consultants $126,416
Personnel FTE: .21 NRS 2, .29 Tech 2, .5 Tech 1, .33 Laborer 1, .13 SFWB, .08 Clerical Spec. $ 42,055
Fringe $ 16,780
Supplies $ 15,490
Travel Vehicle lease, mileage and perdiem $ 5,163
Indirect $ 21,458
Subcontractor weed control $ 2,000
Other Training $ 480
Personnel FTE: .13 NRS 2, .08 Tech 2, .07 SFWB $ 11,734
Fringe $ 4,682
Supplies $ 750
Travel Vehicle lease and mileage $ 680
Indirect $ 5,046
Other Training $ 1,130
Total Itemized Budget $425,263


Total estimated budget

Total FY 2001 project cost $425,263
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $425,263
FY 2001 forecast from 2000 $450,000
% change from forecast - 5.5%


Reason for change in estimated budget

Smaller projects


Reason for change in scope

No change in scope of work


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 67,200 $ 70,000 $ 70,000 $ 74,000
Construction/implementation $246,825 $254,325 $254,325 $264,500
Operations and maintenance $110,775 $117,725 $117,725 $122,600
Monitoring and evaluation $ 25,200 $ 26,200 $ 26,200 $ 27,200
Total Outyear Budgets $450,000 $468,250 $468,250 $488,300
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$425,263
Comment:
Implementation was cut last year for budget reasons. That work has been brought back up to planned levels. There are also matching funds available through COE for this project ($780,000). The increase in the budget is due mainly to implement 1½ miles of channel restoration.

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$361,428
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$300,264
FY06 NPCC Staff Preliminary:
$300,264
FY06 NPCC July Draft Start of Year:
$300,264
Sponsor (ODFW) Comments (Go to Original on NPCC Website):