Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Lake Creek Land Acquisition and Enhancement
BPA Project Proposal Number 199004401
Business name of agency, institution,
or organization requesting funding
Coeur d'Alene Tribe
Business acronym (if appropriate) CDA Tribe
 

Proposal contact person or principal investigator

Name Robert Matt, Wildlife Manager
Mailing Address P.O. Box 408
City, State, Zip Plummer, ID 83851
Phone 2086866008
Fax 2086863021
E-mail RMATTAMW@IEA.COM
 
Manager of program authorizing this project Robert Matt
 
Review Cycle FY 2001 Ongoing
Province Mountain Columbia
Subbasin Coeur d'Alene
 
Short Description Protect, enhance, and maintain wetland and riparian habitat in the Lake Creek drainage as partial mitigation for the impacts attributed to the construction and operation of the Albeni Falls hydroelectric facility.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: This proposal is based on a watershed management concept and will assist in equally protecting and enhancing both fish and wildlife resources throughout the watershed. It represents an opportunity to protect and enhance fish and wildlife habitat in the Lake Creek Watershed. Lake Creek drains approximately 23,117 acres and empties into Windy Bay at the southwest end of Lake Coeur d'Alene. The watershed provides valuable habitat for populations of black bear, moose, elk, white-tailed deer, muskrat, Canada geese, mallards, westslope cutthroat trout, bull trout, and many species of song birds as well as other non-target wildlife species. This project will target species used to assess the impacts of Albeni Falls Dam. This will include mallard duck, Canada goose, bald eagle, black-capped chickadee, white-tailed deer, muskrat, and yellow warbler. BPA will receive baseline protection credit for the habitat units provided on the wildlife portion of the project. All baseline habitat units will be maintained through the life of the project. The perpetual protection, enhancement, and maintenance of wetland and riparian habitat will provide immediate and long term benefits to the target species as well as additional non-target wildlife species through the provision of dependable habitat elements necessary for satisfying various life requirements for these species. In addition, project activities will provide immediate and long term benefit to a high priority westslope cutthroat trout population as well as assist in expanding the potential for Lake Creek to support historical bull trout populations through the improvement of both habitat and water quality. Expansion of the project area will contribute to this effort.
Biological Data: Baseline habitat evaluation efforts will be conducted during the 2001 field season. Habitat Evaluation Procedures will be used to determine the appropriate level of protection crediting for the target species identified above as well as to provide the baseline suitability indeces required for monitoring the effectiveness of land management practices. This baseline suitability index will then be used during routine habitat evaluation efforts to provide a picture of the effectiveness of enhancement efforts for both management and crediting purposes. Types of data to be collected during the HEP will be species dependent. Sample types include such information as canopy closure, canopy height, percent canopy cover of emergent herbaceous vegetation, percent distribution and average height of deciduous shrub canopy cover, etc.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): wildlife


Section 2. Past Accomplishments

Year Accomplishment
2000 Completion of appraisal and other pre-acquisition requirements.
2000 Purchase of property.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Plan and coordinate baseline wildlife and habitat evaluation surveys for Godde property. a. Plan baseline HEP: includes model design, interagency coordination, assembly of HEP team, compilation of existing information, etc. 1 $ 16,519  
b. Plan baseline wildlife survey: includes survey design, interagency coordination, compilation of existing information. 1 $ 13,056  
2. Draft site specific management plan for Godde property. a. Draft management plan for the site including management goals, objectives, strategies, expected outcomes, and monitoring and evaluation needs. 3 $ 42,996  
3. Plan and identify project expansion opportunities. a. Plan and identify future opportunities to secure land management rights to additional properties in Lake Creek Watershed, including identification of willing land owners. 5 $ 0  
4. Completion for pre-acquisition work associated with securing management rights to new properties. a. Completion of appraisals, property surveys, haz-mat surveys, cultural resource surveys, NEPA checklist, etc. 5 $ 0  
5. Plan and coordinate baseline wildlife and habitat evaluation surveys for secured properties. a. Plan baseline HEP: includes model design, interagency coordination, assembly of HEP team, compilation of existing information, etc. 5 $ 0  
b. Plan baseline wildlife survey: includes survey design, interagency coordination, compilation of existing information. 5 $ 0  
6. Draft site specific management plan(s) for secured properties. a. Draft management plan for each new site including management goals, objectives, strategies, expected outcomes, and monitoring and evaluation needs. 5 $ 0  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 84,008 $ 88,209 $ 76,198 $ 80,008


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Protect and enhance wetland and riparian habitat in the Lake Creek Watershed. a. Secure management rights to high priority wildlife habitat areas in the Lake Creek watershed. 5 $ 0  
b. Enhance project lands as identified in the site specific management plans. 5 $ 0  
2. Implement appropriate enhancement measures on project lands. a. Complete all enhancement activities identified in each of the site-specific management plans: includes Godde property and new acquisitions. 5 $ 0  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2004 FY 2005 FY 2002 FY 2003
$1,000,000 $1,000,000 $1,000,000 $1,000,000


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Identify and secure boundary of Godde property to prevent livestock trespass and control access. a. Confirm property boundaries and mark with appropriate signage, gates and fencing as necessary. 3 $ 45,000  
2. Maintain the existing habitat units on Godde property. All activities will be consistent with the O&M Guidelines document prepared by the wildlife managers. a. Maintain property boundary, gates, and perimeter fencing as necessary. ongoing for life of project $ 9,200  
b. Control the spread of invasive noxious weeds as necessary. ongoing for life of project $ 14,529  
c. Maintain and control public access as appropriate. ongoing for life of project $ 17,000  
d. Use adaptive management principles to address unforeseen management concerns. ongoing for life of project $ 35,000  
e. Consult and coordinate land management activities with NWPPC, BPA, CBFWA, Albeni Falls Work Group, local governments, and the public. ongoing for life of project $ 6,700  
3. Maintain the existing habitat units on new project lands. Tasks same as identified in objective 2. ongoing for life of project $ 0  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2004 FY 2005 FY 2002 FY 2003
$250,000 $250,000 $133,800 $250,000


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Monitor and evaluate project implementation activities. a. Monitor and evaluate the effectiveness of land management activities on all project lands as described in site specific management plan(s). ongoing for life of project $ 0  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2004 FY 2005 FY 2003
$ 50,000 $ 50,000 $ 50,000


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: .6 $ 29,328
Fringe 40% $ 11,732
Supplies $ 10,197
Travel $ 5,600
Indirect 27.6% $ 15,714
Personnel FTE: Tech 1.50; Biologist .60 $ 49,296
Fringe 40% $ 19,719
Supplies up to 8 miles of fence $ 19,500
Travel GSA lease, training, etc. $ 12,000
Indirect 27.6% $ 26,914
Capital Tractor w/ accessories and facilities expansion necessary for outyears $ 0
Total Itemized Budget $200,000


Total estimated budget

Total FY 2001 project cost $200,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $200,000
FY 2001 forecast from 2000 $200,000
% change from forecast 0.0%


Reason for change in estimated budget

No change in budget.


Reason for change in scope

No change in scope identified for FY 2001. Expansion of project to include securing of additional project lands in outyear budgets was identified as a future need in the original proposal.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 76,198 $ 80,008 $ 84,008 $ 88,209
Construction/implementation $1,000,000 $1,000,000 $1,000,000 $1,000,000
Operations and maintenance $133,800 $250,000 $250,000 $250,000
Monitoring and evaluation $ 0 $ 50,000 $ 50,000 $ 50,000
Total Outyear Budgets $1,209,998 $1,380,008 $1,384,008 $1,388,209
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Date:
Jul 14, 2000
2001
$200,000
Comment:

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$150,000
Comment:
Rationale: Budget increase inappropriate in this review. Project has balance of $2.4 million. Reduction is from O&M, pending provincial review

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$160,020
FY06 NPCC Staff Preliminary:
$160,020
FY06 NPCC July Draft Start of Year:
$160,020
Sponsor (Coeur D'Alene Tribe) Comments (Go to Original on NPCC Website):

Sponsor (Coeur D'Alene Tribe) Comments (Go to Original on NPCC Website):