Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Idaho Fish Screen Improvement - O-M
BPA Project Proposal Number 199401500
Business name of agency, institution,
or organization requesting funding
Idaho Department of Fish and Game
Business acronym (if appropriate) IDFG
 

Proposal contact person or principal investigator

Name Patrick Marcuson
Mailing Address PO Box 1336
City, State, Zip Salmon, ID 83467
Phone 2087566022
Fax 2087566274
E-mail pmarcuso@idfg.state.id.us
 
Manager of program authorizing this project Pat Marcuson
 
Review Cycle FY 2001 Ongoing
Province Mountain Snake
Subbasin Salmon
 
Short Description Enhance passage of juvenile and adult fish in Idaho's anadromous fish corridors by consolidation and elimination of irrigation diversions. Minimize adverse fish impacts of irrigation diversion dams, screen pump intakes and screen all irrigation canals.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: 1. Twelve tributary streams will be reconnected, providing over 100 miles of spawning and rearing habitat and delivering cold tributary water to the main stem of the Salmon River. 2. Fish passage will be enhanced by removal of 15 wing diversion dams across migrating routes of adult and juvenile salmon and steelhead, thus, reducing delays of smolts due to entering irrigation canals. 3. Minimize need for irrigators to push up (with heavy equipment) stream substrate gravel into a diversion dam, thus assisting stream stability and fish food produciton. 4. Increase in-stream flows by converting from flood irrigation to more efficient sprinkler water distribution. This not only increases stream flows but reduces temperature and silt loads associated with return flows from flood irrigation. 5. Fish of all species are diverted back to their source at the fish screen.
Biological Data: Several older evaluation studies described in the reference section of the FY2000 application established some of the parameters used to measure biological outcomes used today. Trap data on the return (by-pass) pipes indicate numbers and species of fish diverted by fish screens. Electrofishing and some snorkel counts down canal of fish screens and in-stream near the points of diversion are collected where needed and as time and funds allow.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1993 Build Anadromous Fish Screen Shop
1994 Equipment purchased and screen construction to NMFS
1997 Constructed fish screens on consolidated canals, three fish friendly diversions, 20 pump intake screens, 2 infiltration screens and 17 headgeates.
1998 Constructed fish screens, 4 fish friendly diversions, safety fences, canal eliminations and two stream reconnects, 20 pump intake screens and 12 headgate installations.
1999 Treated 62 sites, replaced 11 fish screens to NMFS criteria, eliminated 5 fish screens, installed 11 new screens on previously unscreened ditches, eliminated 2 diversion dams, installed 40 pump screens, 6 headgates, two safety fences and
provided 29 technical assistance. Saved 109,500 chinook, 15,150 steelhead and 600 bull trout at 35 Salmon River fish screens.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Complete surveys, designs, of Idaho's Anadromous fish corridors a. Complete topographic surveys of unscreened and obsolete fish screen sites. 4 $ 12,000 x
b. Design appropriate fish screen headgate and fish friendly diversion at each site. 4 $ 0  
c. Contract construction at each site. 4 $ 0  
2. Reduce the number of gravel push-up diversion dams by consolidation and elimination of irrigation ditches. a. Identify potential consolidation and ditch elimination sites. 4 $ 2,719  
b. Attain easements and flow agreements. 4 $ 0  
c. Design consolidations and replacement of surface water diversions to ground water systems. 4 $ 0  
3. Maximize any rearing habitat in appropriate irrigation canals. a. Evaluate fish habitat in irrigation ditches and in immediate stream fishery. 4 $ 2,715  
b. Locate fish screen to maximize rearing habitat. 4 $ 2,715  
4. Reconnect streams to anadromous fish corridors. a. Locate streams providing historic spawning and rearing for anadromous fish. 4 $ 2,717  
b. Determine if adequate water attracts anadromous fish. 4 $ 2,717  
c. Design 4 $ 0  
5. Install and evaluate alternative fish screens. a. Look for sites for infiltration and other simpler means of saving fish from irrigation practices. 4 $ 2,717 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 14,150 $ 14,150 $ 28,300 $ 28,300


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Construction & installation of all unscreened gravity and pump intakes in Idaho's anadromous fish corridors. a. Fabricate and install fish screen and associated components at each site. 4 $400,000 x
b. Locate, measure, design, build and install fish screens on pump intakes. 4 $ 26,087  
2. Reduce the number of gravel push-up diversion dams by consolidation and elimination of irrigation ditches. a. Replace surface water diversions to ground water systems. $ 50,000  
b. Construct by contract and IDFG crew. 4 $200,000 x
3. Maximize any rearing habitat in appropriate irrigation canals. a. Locate fish screen to maximize rearing habitat. 4 $ 10,000  
4. Reconnect streams to anadromous fish corridors. a. Implement the reconnect. 4 $ 17,139  
b. Install fish screens where needed. 4 $135,089 x
5. Install alternative fish screens. a. Construct and install. 4 $ 30,000  
6. Make accessible fish screens safer to humans and domestic pets. a. Fence accessible screen sites. 4 $ 2,500  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2004 FY 2005 FY 2002 FY 2003
$435,407 $435,407 $870,815 $870,815


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Complete surveys, designs, construction and installations of all unscreened, obsolete gravity and pump intakes in Idaho's anadromous fish corridors. a. Maintain fish screens and by-pass pipe operation. 20+ $ 0  
b. Maintain occasional pump screen. 4 $ 2,500  
2. Reduce the number of gravel push-up diversion dams by consolidation and elimination of irrigation ditches. a. Check integrity and fix deficiencies. 4 $ 48,391  
3. Reconnect streams to anadromous fish corridors. a. Fix deficiencies. 4 $ 2,800  
b. Maintain screens. 20+ $ 1,766  
4. Install and evaluate alternative fish screens. a. Maintain alternative fish screens. 20+ $ 15,000  
5. Make accessible fish screens safer to humans and domestic pets. a. Repair fences as needed. 20+ $ 500  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 35,478 $ 35,478 $ 70,957 $ 70,957


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Complete surveys, designs, construction and installations of all unscreened, obsolete gravity and pump intakes in Idaho's anadromous fish corridors. a. Check selected screens for numbers and kinds of fish returned to stream. 20+ $ 5,518  
b. Monitor presence or absence of fish down canal of fish screen. 20+ $ 3,500  
2. Reduce the number of gravel push-up diversion dams by consolidation and elimination of irrigation ditches. a. Evaluate and adjust as needed for proper function. 20+ $ 3,600  
3. Maximize any rearing habitat in appropriate irrigation canals. a. Electrofish or snorkel. 20+ $ 3,500  
b. Observation of fish utilizing irrigation canals. 20+ $ 4,000  
4. Reconnect streams to anadromous fish corridors. a. Resurvey fish presence or absence in re-connected stream. 4 $ 5,910  
5. Install and evaluate alternative fish screens. a. Monitor and evaluate function of alternative fish screens. 4 $ 3,900  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2004 FY 2005 FY 2002 FY 2003
$ 14,964 $ 14,964 $ 29,928 $ 29,928


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: .50 fisheries tech. (wages primarily paid from other sources) $ 6,638
Fringe One fisheries technician on BPA grant $ 2,300
Travel $ 1,750
Indirect Indirect rate on personnel and operations only $ 5,612
Other Professional services $ 12,000
Personnel FTE: .65 fisheries tech. (wages come for other sources) $ 17,139
Fringe $ 5,929
Travel $ 1,750
Indirect Indirect rate on personnel and operations only $ 6,087
Capital $629,840
Subcontractor Subcontractors in this program are state bid awards for cement work $210,070
Personnel FTE: .20 Fish tech. (most wages from cost share sources) $ 1,350
Fringe $ 466
Supplies $ 54,000
Travel $ 1,750
Indirect Indirect rate on personnel and operating only $ 13,391
Personnel FTE: .75 fisheries tech. (most wages come from other sources) $ 16,543
Fringe $ 5,725
Travel Indirect rate on personnel and operations only $ 1,750
Indirect $ 5,910
Total Itemized Budget $1,000,000


Total estimated budget

Total FY 2001 project cost $1,000,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $1,000,000
FY 2001 forecast from 2000 $1,000,000
% change from forecast 0.0%


Reason for change in estimated budget

None


Reason for change in scope

None


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 28,300 $ 28,300 $ 14,150 $ 14,150
Construction/implementation $870,815 $870,815 $435,407 $435,407
Operations and maintenance $ 70,957 $ 70,957 $ 35,478 $ 35,478
Monitoring and evaluation $ 29,928 $ 29,928 $ 14,964 $ 14,964
Total Outyear Budgets $1,000,000 $1,000,000 $499,999 $499,999
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$1,000,000
Comment:
There is no change in scope or budget.

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$1,000,000
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$1,000,000
FY06 NPCC Staff Preliminary:
$1,000,000
FY06 NPCC July Draft Start of Year:
$1,000,000
Sponsor (IDFG) Comments (Go to Original on NPCC Website):

Return to top of page